The Project Control Meeting
Agenda for Monday September 27, 1999 will be:
(Meeting time: 10:30 am Pacific Time)
LHO Vacuum Bake Oven A load #57, consisting of two LOS structures + misc. fasteners, was released earlier this week. The damaged flanges (see previous report) leak at about 9E-10 (torr*L)/(sec) which is unfortunate but we have no plans at this time to attempt to repair them any further.
Load #58, consisting of one LOS structure + Kapton cables, has been loaded but is on "hold" as we have a new problem. Starting with load #58 we began using the first of a new batch of wire seals. It now looks as though there may be a "quality" issue with these new seals as they seem to fit very loosely and we have not been able to get them to seal satisfactorily. Bartie has requested a few seals from LLO to see if they will work with our oven in an attempt to buy us some time as we sort this out with the vendor.
Seismic Systems:
HAM work: Currently, HAMs 1&4 have Support Tubes, Support Tables and Bellows installed. The vertex is now pumped down and the Bellows are awaiting leak checks; once the Bellows pass their leak checks (which they will!), the Support Tubes can then be connected to the external SEI hardware. We will then move on to HAMs 2&3.
BSC work: Beginning prep work for first "wet Seat" replacement on Monday; we plan on making the switch-out and sealing up the chamber all on Monday. Today we plan on removing the dome and installing the platforms at Y-MID.
Instrumentation work: Hugh made a data run with Shourov C.'s portable cabinet over the weekend. He had several channels (6 or 7 I believe--3 channels were for the seismometer and another 3 or 4 were from the Mode Cleaner). The data is currently being downloaded so that it can be analyzed through MatLab.
We (M.Lubinski, J.Myers, F.Raab, H.Radkins, R.Savage, and myself) finished up work on the checking of the seismometer calibration provided by the manufacturer. After work in the Lab and "homegrown" experiment, we have come up with calibration which was within ~5% of the manufacturers numbers.
Computing:
Finally was able to get an external modem working on my PC and was able to test the modem pool. Also, thanks to Stan Whitcomb and Gary Sanders for their help testing the modem accounts. The modem pool works for most things, but still has some problems resolving DNS names.
Requested quotes on service contracts as part of preparing the LHO Data and Computing FY 2000 budget. Reviewed software licenses and supplies to determine future needs.
The hacker from Italy has not been back since last week. There don't seem to be any foreign files or processes left behind by the hacker. So far, we have not suffered any adverse affects of being hacked.
If you have not changed your password on rainier, the LHO server, please do so ASAP. As a result of the hacker and trying to get everyone to change their passwords, we discovered a problem with Secure Shell 2.0. Apparently ssh 2.0 is not compatible with the nispasswd command. We think it may be the way ssh encrypts the password. We found that the old ssh 1.3 does work with the nispasswd.
Did the usual backups, ordered more supplies, added new user accounts, helped with several printer and PC problems and kept the GC accounting paper work up to date.
CDS
All 2k Interferometer DAQs and ADCUs are running (LVEA, left and mid stations). (Taiwan earthquake was seen clearly with LVEA seismometer)
Fitted AntiAliasing cards into interconnect chassis for LVEA rack 2x5, X mid station and Y mid station. Currently constructing EY AA interconnect, and LEMO AA interconnect for 2k PSL DAQ.
Frame builder testing with CPP frame library is continuing. Alex will perform testing next week at LHO. 4k IFO DAQ will be tested next week with Rolf using EY.
DAQ reflective memory network is being tested with bad packet elimination and remote VME reset capabilities switched on (both 2k and 4k networks).
Physics Environmental Monitoring:
Fred, Corey, Josh and I conducted checks of the seismometer using a pendulum. This resulted in getting numbers closer to what was on the data sheets provided by Guralp and allowed us to check 2 horizontal channels. We also discovered that the "breakout box" we used was wired incorrectly. This was repaired. We then set up to perform a calibration per the tech manual and found that our numbers were significantly off from the calibration data (this also happened on previous data runs). We found when we measured the calibration resistance as listed on the data sheets it was one third of the value possibly indicating 3 parallel calibration circuits. We performed another data run and when we completed the calculations with the new information we were able to come with in 3-6% of the values listed on the calibration sheets. I confirmed this with the Bruce Pauly of Digital Technology (Guralp vender) and we now understand the seismometers better. We now have seismometers and tilt meters in the LVEA and X Mid and currently logging data.
Pre-stabilized Laser
M. Guenther and I have been working on documentation and channel verification for the PSL subsystem. We have measured the frequency response of the PSL DAQ interface module that enables acquisition of twelve of the fourteen PSL "fast" channels. Once the DAQ interconnect chassis is installed (D. Barker is making modifications) we will verify that the signals appear as expected in the control room.
Optics
I have been working with Bill Kells on the optical levers again. We have been sorting out the optical lever DAQ system and determining the calibration factors for each of the optical levers. We are beginning to get a feel for their sensitivity in vacuum and in air. Hopefully we will have a few levers being monitored for a week or so before the spring seat replacement starts. Preliminary data looks hopeful.
We received four additional 4K ISC optic tables this week and moved them to their staging area. Rick Savage and I are modifying the 10 watt laser SOP to make it more suited to the current laser activities in the LVEA and VEAS. It will hit the DCC soon. We will need to explain the changes to reregister people who wish to be on the Registered Laser Personnel List.
Betsy and I put together a transport gismo to ship the LOS SUSs to the MID and END stations. Betsy has been assisting in seismic chores, getting things ready for seat replacement in the MID station as well as preparations for bake loads and COS preparations.
Suspensions and Optics: We continued to work on the steering mirror (SM06-1). We glued a wire standoff and a guide rod using the old fixture, curing at room temperature. We glued all the magnet-dumbbell combinations following the most updated procedure (curing at 100 deg C). The magnet-dumbbell combinations were also glued following the most updated procedure. The optic was balanced and the second wire standoff has been glued. This optic will be used to test OSEMS and investigate cross-coupling.
We balanced the optic on the granite table using a HeNe laser optical lever. Since a quad-sensor was not available yet, we had to damp the hanging optic in such a level that the HeNe beam reflected by the suspended optic and detected as a spot on a target was still enough to measure its height from the optical table. By clamping the suspension tower to the table and covering the whole suspension tower by aluminum foil to prevent the air flow from swinging the optic, we could make the beam spot moving around the neutral point not more than 25% (the spot diameter on the target was 10 mm and the spot had a yaw motion in -12.5 mm to +12.5 mm). It took about 30 min to damp the optic at this level. (Sany Yoshida)
Completed the alignment fixture to bond guide rods and wire standoffs to SOSs for Sany. (Jonathan Kern)
We are baking a LOS structure and RGA Tree components in the vacuum bakeout oven. We are also preparing for a test of the oven extension. (Tom Evans)
Beam tube bakeout: The X-2 beam tube is now at ambient temperature and the RGA and cal cart has been baked and are now in as the certification measurements are being made. Bake preparations for the X-1 module are under way. We have moved a large turbo to the Y arm end station in preparation for a leak test of the VE after detector installation. (Allen Sibley)
PSL: The Pre Mode Cleaner has been installed in the PSL. 8.24 watts of output power has been measured with only 9.33 Watts of input power. The beamsplitter cube after the laser may be losing about 1 Watt of light so it will probably be replaced. If this works, the ouput of the PMC should meet the spec. of 8.5 Watts. Further work includes going back and working on the frequency stabilization. (Joe Kovalik)
Juilien is helping Rolf and Jay to install SOS and DAQ systems. A quick manual to start CDS monitoring system in control room is written and posted next to the CDS Sun computers. (Juilien Svoboda)
LSC Modeling: I (Anthony Rizzi) am leading an effort to model the LSC using end-to-end model. As part of this effort, Hiro Yammomato is working with me here at LLO this week. We have modeled an single arm of the LSC using a box program whose base configuration was drawn by Bill Kells. We have obtained input from Peter Fretchil and Mike Zucker on parameters and planned tests for the 2km test in hanford. At present, we are investigating some important aspects of lock aquisition as well as probing the end-to-end model itself. Much is being learned.
GRASP: I am bringing Joel Tohline (Prof. from LSU) up to speed on various aspects of the GRASP program. Joel plans to be involved in our efforts to analyze seismic data with massively parralel computer system. LSU plans to buy a cluster of PC's that could be very helpful in processing templates before our LDAS computers arrive. He has offered use of them. Joel's schedule is now to come out every Wednsday afternoon. (Anthony Rizzi)
Control and Data Acquisition System: Data acquisition cabling from the Mass Storage Room to the LVEA is terminated and tested. 1X6 (SOS controls) has been successfully tested and is ready to be connected to the feedthrus at the tanks. Fabrication of 1X7 (LOS controls) is underway. We are missing the LOS Controllers. Worked out CDS installation plan for the next 4 weeks with Rolf and Jay. (Rus Wooley)
Facilities: Siemens Building and Technology Incorporated has made several unsuccessful attempts to connect the end stations building control system with the corner station. As soon as new modems that have been ordered are received they will return and make another try.
An agreement has been reached with the access road contractor to construct a pad for the LIGO sign at the intersection of Hwy 63. Work on this has stated and should be complete within a week.A meeting is to be held this coming Monday to accept the access road for LIGO's use. If all goes as planned the road should be open for traffic next week. (Gerry Stapfer)
(WBS 1.2, 1.3)
IAS Initial Alignment / ISC Design (K.Mason, M. MacInnis)
IO mode cleaner commisioning (Nergis, Rana, Haisheng, Peter F.)
The reflectivity of the AR coating of the MC flat mirrors was measured to be between 100 and 200 ppm (depends strongly on the angle of incidence).
Input/Output Optics -- Dave Reitze, UF
LLO 4k (Sany Yoshida)
We continued to work on the steering mirror (SM06-1). We glued a wire standoff and a guide rod using the old fixture, curing at room temperature. We glued all the magnet-dumbbell combinations following the most updated procedure (curing at 100 deg C). The magnet-dumbbell combinations were also glued following the most updated procedure. The optic was balanced and the second wire standoff has been glued. This optic will be used to test OSEMS and investigate cross-coupling.
We balanced the optic on the granite table using a HeNe laser optical lever. Since a quad-sensor was not available yet, we had to damp the hanging optic in such a level that the HeNe beam reflected by the suspended optic and detected as a spot on a target was still enough to measure its height from the optical table. By clamping the suspension tower to the table and covering the whole suspension tower by aluminum foil to prevent the air flow from swinging the optic, we could make the beam spot moving around the neutral point not more than 25% (the spot diameter on the target was 10 mm and the spot had a yaw motion in -12.5 mm to +12.5 mm). It took about 30 min to damp the optic at this level.
Mechanical Design (Dan Dickrell)
Core Optics Procurement and Metrology -- GariLynn Billingsley
Core Optics Coatings -- Helena Armandula
Core Optics Support -- Michael Smith
STEERING MIRRORS: 50 sets are awaiting assembly at CIT.
PO MIRRORS: Ken M. sent out a bid package for the 4K PO mirrors, and a purchase order for the 4K LHO and 4K LLO PO mirrors is expected to be let next week (9/30).
VACUUM WINDOW: A full set of COS vacuum windows is en route to LHO.
ARM CAVITY BAFFLE: Inner baffle assembly is being fabricated. Bids for outer support frame assembly have been received, and a purchase order will be placed next week (9/27). Paul K. is finalizing a few detail drawings, and is working on the top assembly drawings for LHO and LLO.
CONICAL BAFFLE: First article has been reworked, cleaned, and is being air-baked. Fabrication of the remaining production baffles is in process.
COS ALIGNMENT PROCEDURE: The optical elements of the COS autocollimator are in the process of being anti-reflection coated to eliminate excessive internal glare. New fixturing has been completed and tested for attaching the CCD cameras to the autocollimators. A holographic diffuser has been incorporated and tested for providing uniform illumination of the autocolliimator reticle, when illuminated with the 940 and 990nm diode laser sources. A mock-up of the COS alignment procedure for the FM, ETM telescope and APS telescope will be set up in the optics lab at CIT.
4K IO BAFFLE: Paul K. finalized the working drawings for the 4K IO baffle, and sent out a bid package. A purchase order for the 4K LHO and 4K LLO IO baffles is expected to be let next week (9/30).
INSTALLATION PLAN
| item | completion | install |
| Elliptical baffle 2KRM, HAM9 | done | done |
| Elliptical baffle 2KITMy, BSC8 | done | done |
| Beam dump FMYY, BSC8 | done | done |
| Beam dump FMYX, BSC8 | done | pending |
| Beam dump 4KITMHR3, BSC8 | done | pending |
| Beam dump 4KITMHR4, BSC8 | done | pending |
| Beam dump RMHR3, BSC4 | done | pending |
| Beam dump BSHR3P-2, BSC4 | done | pending |
| Beam dump ITMXAR1, BSC4 | done | partial |
| Beam dump ITMXAR4, BSC4 | done | partial |
| Beam dump ITMXAR4, BSC4 | done | partial |
| Beam dump ITMXAR4, BSC4 | done | partial |
| Beam dump ITMyAR1, BSC4 | done | partial |
| Beam dump ITMyAR4, BSC4 | done | partial |
| Elliptical baffle 2KITMx, BSC7 | done | pending |
| Beam dump FMXX, BSC7 | done | pending |
| Beam dump FMXY, BSC7 | done | pending |
| PO Tel, APS, HAM10 | done | pending |
| PO Tel, BS, HAM10 | 10/8 | ? |
| PO Tel, ITMy, HAM10 | 10/8 | ? |
| PO Tel, ITMx, HAM9 | 10/8 | ? |
| ETMy Tel | partial | ? |
| ETMx Tel | 10/4 | ? |
| Beam dump ETMy vac window | done | ? |
| Beam dump ETMx vac window | ? | ? |
| Arm Cavity Baffle, vertex | 10/15 | ? |
| Arm Cavity Baffle, end | 10/15 | ? |
| Conical baffle, vertex | 9/27 | ? |
| Conical baffle, mid station | 9/27 | ? |
| Vacuum windows | done | ? |
This week I have finished reorganising the DMT source code and copying it to cvs. I then successfully installed the new version of the gcc compilers and the dmt software (from the cvs repository) on the dmt machine at LHO. I am now completing the perl script to manage background monitor processes. Most of the time spent debugging diagnostics test code and solve synchronization problems between different CPUs. Made sure that tests can be repeated and test results are stored incrementally.
Physics Environmental Monitor (Matt Smith, David Shoemaker)
Suspension (Jay)
Timing System CDS: (Dale)
PSL (Rich)
From: Syd Meshkov <syd@ligo.caltech.edu>
No report this week.Reports, Proposals (Lindquist)
The Quarterly Report is being prepared. We are still waiting for a draft from Coyne/Whitcomb/Shoemaker pending resolution of scheduling issues. A copy of the previous Quarterly Report is available at Quarterly Report.
We will submit an Operations Work Plan for FY 2000 in October. I have asked task managers to submit budgets to Florence Kaufman by the end of this month and text by the middle of October. Again, early contributions will be appreciated.
Change Control/Contingency (Lindquist)
The following change request has
been submitted:
| CR-990018 | WBS 1.1.5 | Beam Tube Bake--Revised Estimate at Completion | W. Althouse |
Press for the latest Contingency Needs Projection
Everyone is reminded to provide a redlined copy of their current LIGO business card to Ed Jasnow so that we may plug it into the print shop for new ones.
Assisted the Quality Assurance Engineer ( B.Tyler) with packaging and shipping of four (4) metal shelves 17 5/8 "x21" and eight (8) L-Shape brackets to the LIGO Livingston Observatory, attention: T. Evans, account number P47440.
Assisted S. Elieson with the shipment of a Recycling Mirror Coated, Serial Number RM04 to the LIGO Livingston Observatory, attention: H. Armandula, account number P96937.
Assisted R. De Salvo by arranging Customs Clearance
for incoming Parts from Galli&Morelli of Italy being forwarded to the
Synchrotron Building.
Forwarded the General Services Administration (GSA) Voucher for Lease Vehicles with the billing date 9/21/99 to Hanford and Livingston Observatories.
Received disposition instruction from Caltech's Property Management Office to dispose of the following item for the reason indicated XEROX copier SN:010228953 not economical repairable.
From: Sarita Moore<moore_s@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: Kris Duncan <kris@ligo.caltech.edu>
| CR-990001 | WBS 1.3 | Return Unused Budget for Construction Related R&D to Contingency | P. Lindquist |
| CR-990017 | WBS 1.4.1 | Administrative Account Closeout | P. Lindquist |
| CR-990019 | WBS 1.2.1 | Detector Systems--Optic Tables Balance Weights | D. Coyne |
| CR-990020 | WBS 1.2.1 | Seismic Isolation System--Material and Subcontract Closeout | S. Whitcomb |
| CR-990021 | WBS 1.2.4 | Support Equipment--Additional Cleanrooms and Laminar Flow Benches | S. Whitcomb |
| CR-990022 | WBS 1.2 | Detector Staffing | S. Whitcomb |
| CR-990023 | WBS 1.3 | Beam Tube Enclosure--Hanford--Closeout | F. Asiri |
Completed monthly report of Operations for period ended August 31, 1999.
Spent a lot of time working on providing information regarding problems I had encountered with Oracle to various individuals working on correcting them. Good news is that corrections are being made. However, reports for August 99 for both Construction and Operations accounts should be viewed with caution since most of the corrections were not made until September. Problems to be aware of include:
I am STILL trying to work with WEBSTER. I have redone the July99, and completed the August99 'Allocation of Actual Costs' on the Construction accounts file Construction.xls (detail reports should/might be done next week).
Please note that it was brought to our attention via 'Administrative Alert' that "In WEBSTER, period totals (summaries) are correct, but detail data may be incorrect for July and August. since WEBSTER only shows burdened costs, detail data is incorrect for expenditures that include burdened costs. In cases where expenditures do not have burdened costs, expenditure details are correct for all time periods... This affects data only for July and August, not for the month of September..."
No report this week.
No report this week.TECHNICAL CONFIGURATION MANAGEMENT (Althouse)
Modeling
(BB) Made some clean-up in codes, e.g., "trans_displace_resolution" parameter is removed from "field_gen" module. Only "angle_resolution" will take care of the minimum resolution asked by the user for both rotation and shift effects of mirrors (since the latter is also effectively a rotation).
[Hiro Yamamoto]
(HY) Worked with A.Rizzi to understand the simulation of the lock acquisition
process
(HY) Worked with A.Rizzi to collect information about the 2k FP
(HY) Worked with A.Rizzi to start to model the framework of LSC of
the 2k FP
(HY) Discussed with Sany Yoshida about the thermal lensing effect of
EOM and Silica.
[Ed Maros]
(EFM) Removed error that caused core dump when selecting
Box from Main Menu.
(EFM) Helped Bruce to get Alfi compiled and start with
Alfi4 modifications.
(EFM) Resumed work on Alfi4
[Bruce Sears]
(BS) Alfi system:
Data Analysis System Development
(WM) I have been trying to characterize the recent 40m run taken in coincidence with TAMA. I have written scripts which bring over the archived data from CACR and run my analysis - which for now just calculates some statistics on the various channels and tabulates the in-lock sections. Because my connection to CACR is as fast as the rate at which we acquired data, this will take some time. However, I am planning to use Stuart's machine, which has a private but faster connection to CACR - this should speed things up by a factor of ~3.
[Stuart Anderson]
(SBA) Attended the annual HPSS User Forum to learn the current status and future plans for the proposed LIGO mass storage system. Provided support for the archiving the recent 40m data run into HPSS in "real-time".
----- Forwarded message from Larry Wallace -----
Met with Albert and Kent to go over hardware installation. Tom Evans is checking things out for cabling. SUN computers have been ordered and the PC's are to ship this week. Bill Tyler is checking on the order for the rack and is having the shelving items for the rack ship this week. The fibers are being ordered and will take a few days to make but they should ship the end of next week.
General Computing
Livingston: We have been working on network problems with our T1 provider. We have been intermittently on and off the net for the last few days due to the T1 line going up and down, but we now seem to be running and stable. LSU and BellSouth have been involved in resolving the issue.
We have ordered two replacement Sun monitors.
Hanford: Finally was able to get an external modem working on my PC and was able to test the modem pool. Also, thanks to Stan Whitcomb and Gary Sanders for their help testing the modem accounts. The modem pool works for most things, but still has some problems resolving DNS names.
Requested quotes on service contracts as part of preparing the LHO Data and Computing FY 2000 budget. Reviewed software licenses and supplies to determine future needs.
The hacker from Italy has not been back since last week. There don't seem to be any foreign files or processes left behind by the hacker. So far, we have not suffered any adverse affects of being hacked.
If you have not changed your password on rainier, the LHO server, please do so ASAP. As a result of the hacker and trying to get everyone to change their passwords, we discovered a problem with Secure Shell 2.0. Apparently ssh 2.0 is not compatible with the nispasswd command. We think it may be the way ssh encrypts the password. We found that the old ssh 1.3 does work with the nispasswd.
Did the usual backups, ordered more supplies, added new user accounts, helped with several printer and PC problems and kept the GC accounting paper work up to date.
CIT: Barbara began work on the Cost Book database for LIGO II. Roughed out some data entry forms and beginning to define the tables and relationships. Continued work on the Celebrations web pages and helped with database questions. The travel and lodging information from Vee has been added to both web sites. Purchased Time Target and installed production version on the DCC server. There is a new release in beta test. Prepared a cheat sheet and worked with Rita Torres so she can check the LSC Reports database and generate the reports when they arrive. Attended the Caltech Web Forum meeting. The forum is primarily for departments who contribute pages to the main Caltech web site. But it will be useful for us too. Most interesting is that they use Oracle, Tcl, and ??? (maybe ACS - some open source software) for their web database work; more information will be forthcoming on that.
Suresh setup couple of new user accounts. Modified some aliases. Made a data CD for a summer student (Dennis Petrovic). Installed Islandraw version 6 and samba (a PC NFS software) on new server. Working on to add a new print queue (duplex) for Millikan users on spooler. Provided regular support services to users.
Worked a number of procurement issues as well as contract renewals. Most of the contracts being worked on at this time deal with hardware maintenance. Reviewed financial plan for next year. Procurements cover networking equipment, printers, computers and associated periphrals. Worked a couple of issues at the 40M. Their run over the weekend went well which allows us to start working on migrating our network hardware over to the newer equipment. Investigating some of SUNS network tools which allow sharing of screens as well as some video conferencing. SUN has changed their format to allow certain PC video standards to be used which is something we are trying to look into. Worked a number of network issues. Working on a modem issue. Finally, have someone (Stan W.) that has been able to duplicate a problem that Gary S. has been having with the system. We hope to continue working on that issue today. Fixed a number of minor PC problems. Most were driver issues.
No report.
Irene Baldon
Please note that this covers only two days of the first week and three
days of the second week (I took one week vacation). It
took a considerable amount of time to organize my desk when I returned.
Worked on preparing the paper work for 18 new trips taken recently or
upcoming (18 Purchase Requisitions and 16 Advance
Requests). There are approximately an additional 9 new trips in various
stages pending completion of travel arrangements before
the paper work can be completed.
Completed 16 Expense Reports, some of which were extensive, involving
2 or more pages each. Many of these reports were
still not taped or completed by the Traveler, and required additional
time for completion. I would like to request that staples not
be used when attaching receipts to 8-1/2 x 11 white paper. Also worked
on a number of problem issues which required a good portion of my time.
There are 16 Expense Reports still to be done, including 3 that require
extensive work to complete. I’m holding 9 completed Expense Reports which
require a check from the Traveler before sending to Travel Audit to clear.
I continue to push for both Advance and Expense Checks already submitted.
"The System" is extremely slow in processing
these. I recently was informed that we will again be given T numbers
which enable us to track a particular trip. Performed normal recording
and filing associated with Travel and Reimbursement. Travel has yet to
be worked out in regards to ORACLE and things are still in a state of extreme
confusion. Things change many times from hour-to-hour. It is very difficult
to get things through or out of "The System."
Started travel preparations for the upcoming LIGO Celebration to be
held at LIGO/Livingston, LA, on Nov. 11th and 12th.
Vee and I have arranged for Conference Rates with two airlines (Delta
and United for domestic flights and Delta for
intercontinental flights). We have arranged for a block of 155 rooms
at a number of hotels in Baton Rouge, LA (75 at The
Radisson on Constitution Ave.; 40 at The Amerisuites on Bluebonnet
Blvd.; 25 at The Homewood suites on Corporate Blvd.;
and 15 at The Hampton Inn on Constitution Ave.). When all is in place,
travelers will be able to call (she will be getting an "800" number to
use during this Celebration) or e-mail Vee to book their trip using the
special rates that we will be obtaining. I will pass on more information
as I obtain it. In the meantime, Barbara Kratochwill has put the current
information on the WEB page.
Prepared the Travel/Vacation Itinerary for the Week of September 21, 1999.
Performed miscellaneous duties as requested by various members of the
LIGO Project here at Caltech, as well as from
members of the staffs of each of the two (2) sites. I continue to do
MIT’s travel to the sites for installation activities and assist
them wherever possible.
Dorothy Lloyd
Entered and approved numerous requisitions in Oracle which included
running periodic searches in Oracle to find PO number
assignments to newly entered requisitions. Performed "primary" and
"secondary" receiving on-line in Oracle, which authorizes
payment immediately upon receipt. [End Users should note that shipments
should be inspected immediately before submitting packing slips to me.
Once the information from the packing slip is entered into Oracle payment
will be made. The End User or I may never see an invoice.]
Continued to process heavy load of invoices for payment along with tracking and following up on various invoice problems using the old system. This system for approval continues with most of the orders that were entered in IFIS.
Notified various task managers of status of their subcontract funding levels and requested approval for supplementing funds.
Jim has continued to reconcile status reports as time permits, but has been concentrating mainly on LIGO database entry.
Elizabeth K. Wood
Updated the LIGO roster. If anyone or any information is missing, please let me know.
Created a small spreadsheet of the anticipated costs associated with the LIGOfest.
Talked to the ID Bureau about the missing ID cards for Hanford. We’re still trying to track them down.
Hired a temp to help Linda and Cleveland down in the DCC.
In between dealing with invitations for the LIGOfest, I did some personnel stuff, too.
Helped Veronica with wordsmithing some email messages she needed to send out to the Amaldi conference participants.
Reconciled charges on my P-card.
Continued working on the invitations and other arrangements for the
LIGOfest. Mailed out 360 invitations with a few more yet
to come. My thanks to Dave Beckett for participating in stuffing and
sticking sticky things on envelopes and to Cleveland Mak
for folding and delivering the stuffed and stuck envelopes. Thanks
to Barbara Kratochwill making ACCESS accessible.
Did payroll. What used to take about thirty minutes now takes closer
to four hours. Paperwork has increased too-manyfold.
And you think YOUR part is annoying. Your patience and cooperation
are appreciated.
For additional information about this report, contact sanders@ligo.caltech.edu