Weekly Report for Week Ending November 17, 1998



 Project Control Meeting Agenda   Highlights   Hanford Observatory     Livingston Observatory     Detector    Project Office    System Engineering    Administrative    Past Weekly Reports

The Project Control Meeting Agenda for Monday  November 23, 1998 will be:
 (Meeting time: 10:30 am Pacific Time)

  1. Announcements (5 minutes)
  2. Review of Action Items (10 minutes)
  3. Comments on Weekly Report (5 minutes)
  4. Field Change Orders/Contingency Liens/Change Requests (10 minutes)
  5. Review of ISSUES AND PROBLEMS by Subsystem/Activity (10 minutes each)
Special Items:


Special Announcements:


Weekly Report Highlights

Hanford Y1 beam tube bake current is on

Seismic stack installed in HAM7 at Hanford

Progress on remedial items with Hensel Phelps at Livingston
 
 Livingston mid-station gate valve, Y arm accepted

Initial alignment tested at Hanford

Hanford PSL now locked to reference cabvity under EPICS interface

Air bearings glide ahead
 


LIGO Hanford Observatory (LHO) Operations



 =========================================================
LIGO Hanford Observatory (LHO) Operations (F. Raab)
=========================================================

General Items:
--------------
(Fred Raab)

 Next Beam Tube Module heats up! Bakeout of the Hanford Y1 beam tube module was started at 17:30 pm PST today. At 19:30 pm (now), all systems behaving nominally. Tube
temperature is rising to 50 C tonight. - wea

Facilities:
-----------
(O. Matherny)

LHO New Construction

George Grant Construction Co. excavated for part of the footers for the
Staging building and prepared the area for the septic system. Parts of the
new roads and parking lot received the needed gravel base.

Old Item

LHO received permission from the State Health Department to use the potable
water RO system and discharge the brine in to the existing leach field.
 

Seismic Isolation Installation:
-------------------------------
(C. Gray, H. Radkins)

HAM 8 & 9 work

HAM 8 was closed up (after installation of Support Table, Support Tubes, and
Bellows) last week; diagonal portion of detector was pumped down and HAM 8 &
9 were leak tested over the weekend. Results were discouraging--it was
believed that 6 of 8 Bellows were leakers. These Bellows were then
re-installed. A second leak test once again showed quite a few leaks.
(It was determined that the Purge Air valves were the most likely candidate
for the leaks.) It now looks like just one of the Bellows is leaking--this
one will be replaced after HAM 7 work.

HAM 7 WORK

Installation of the Isolation Stacks, Optics Table and electrical cabling
began today. As of this moment is going smoothly. Once this work is done,
leveling of the Optics Table is next and then the doors will be put back on
HAM 7.

Later update -

The first seismic stack has been installed. The springs, seats, leg elements, optical table, and some cabling were installed in HAM7. This was nearly complete at close of business today (Thursday) with weights and clamps and closing the chamber set for tomorrow. - ghs

Optics & Lasers:
----------------
(D. Cook)

Most of this week was spent working with the IAS group at the X-End
station. It gives you a good feel for how long 2 1/2 miles is when you run
back and forth getting things setup. It is a great hands on learning
experience. The setup is a two part operation as I see it. Part one is the
setup of the reference line parallel to the beam tube and references to the
beam tube monuments. This is done by using an optical transit square and
laser autocollimator mounted on an electronic theodolite. This gave a
target laser beam to which the installation fixtures could steer a test
optic into it's position. The object was to locate the optic to within
3mm's both in the horizontal and vertical location, and within 10 arc
seconds of tilt. The air flow from the large soft wall clean room appears
that it may be creating some problems with the very sensitive and quick
response of the autocollimator. Some installation fixture changes will be
needed. The basic process is going smooth, but as most dry runs it produced
some items that need modifying. By week's end a lot will have been learned.

The LVEA particle counts this week are running better than an average of
class 6,000, with a lot of activity.
 

Computing Systems:
------------------
(C. Patton)

The permanent T1 line has been turned on and our router box has been
programmed for the new IP numbers. Twelve computers that were on the
old T1 line have been moved to the new T1 IP numbers. The DNS service
from Caltech has also been turned on. Our domain name is now "computer
name".ligo-wa.caltech.edu, e.g. our server is rainier.ligo-wa.caltech.edu.
The rest of the site computers will be moved to the new T1 line when I
return from vacation and holidays, the week of Nov. 30th.

Two P5-90s have arrived from Larry Wallace.  They will be equipped with
modems, one already is, and used in the LVEA or Mid or End stations to
allow access to the Caltech modem pool, for now, and when it is installed
to the LHO modem pool.

An ethernet connection to the General Computing network has been
installed in the LVEA Y section.  The Bakeout crew will be using it to
log their activities using the electronic web logging tool, elog.

Beam-Tube Bake Out:
-------------------
(M. Lubinski, M. Guenther, and W. Althouse)

See above - ghs


LIGO Livingston Observatory (LLO) Operations



 
 
Facility issues (Gerry Stapfer)

Hensel Phelps had been formally informed that several issues are
pending before our contract with them can be closed out. One of these issues dealt
with the completeness of the electrical installation. The HPC project
engineer and office manager met with their electrical subcontractor and after
an all day inspection at the site agreed that outstanding items as noted in
our QA report needed to be completed. We subsequently met with Parsons, HPC and LIGO and
agreed in principal on an approach to get all of the outstanding issues resolved and the contract
closed out.

We are ecountering some delays with the contractor responsible for installation of the laser
curtain. We had hoped to have this work and the cable tray installation underway by now, as the
cabinetry for the optics lab is scheduled to arrive next week and we would like to be able to
put it straight into the lab.

The networking room was reconfigured last weekend, with a few remaining problems that are being
still worked on, such as cable labelling and making sure all of the wall connectors are
functioning.

Vacuum Equipment (Allen Sibley)

After acceptance of the y arm last Thurs. the arm was vented by PSI, and
work on the GNB valves was begun. The work has progressed well with the
exception of fitting the flourel O-rings to the mid point valves. The
O-ring arrived from MIT in time, however the O-rings were not the correct
size. The mid station valves have been reassembled and LIGO will need to
determine when these new O-rings can be installed. All of the GNB valves
have been serviced and are in the process of the 50 cycle test. PSI has
started the bake on the vertex and the x arm manifold bake blankets are
being installed.

Educational Outreach.

Bonnie, Jonathan, and Mark attended the APS Plasma Physics Meeting's
Educational Outreach Day in New Orleans to set up a LIGO booth with posters telling about
LIGO and free stickers for the kids. We also got some ideas about how to do this better next time
(and a few counterexamples as well.) We took some pictures of our exhibit with New Orleans
school kids that we will include in the next LIGO newsletter.
 


WBS 1.2, 1.3    Detector Group


 
----------------------------------------------------
DETECTOR GROUP -- Whitcomb/Shoemaker

(WBS 1.2, 1.3)
----------------------------------------------------

40 m Interferometer (Nergis Mavalvala)
---------------------------------------

40m Prototype

The interferometer locks up fairly routinely for reasonable
stretches (several minutes at a time) after 8pm. We have
been measuring loop gains in all the servos to eliminate
possible pathologies there which may cause the interferometer
to lose lock. The issue of why it loses lock when the alignment
improves is still a mystery, but we're hoping a deeper look into
the control system and electronics will shed some light on this.

The optimal damping gains in the recycling mirror and beamsplitter
suspensions orientation controls were remeasured after we noticed
difficulties with locking with what were believed to be the best
gain values. The interferometer locks much better with the recently
measured values. Another mystery.

We attempted (again) to boost the low frequency gain in the lm
servo. Low frequency drift in the passive filter stage we added
was the problem, we will try to improve that shortly.
 

----------------------------------------------
Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
----------------------------------------------
 

Component fab/delivery status (MEZ)
-------------------------------------
item              status
----------------------------------------------------
IAS initial alignment tooling     delivered
WA2k&4k viewports      delivered
WA2k IO optical lever (MMT3)       delivered
WA2k COC optical lever optics    in fab, delivery 12/20
WA2k COC optlev supports (MMT3 type)    delivered
WA2k COC optlev supports (BSC type) out for quotes
WA2k COC optlev supports (TM type)  in final design
WA2k video/illuminators        delivered
WA2k IOT7 WFS table        all components in, delivery ~ 12/1
WA2k ISCT7,9,10          in layout, delivery 2-4/99 (scheduled)

ASC Initial Alignment  (K.Mason, M. McInnis)
----------------------------------------------
This week was spent at the Hanford facility running through our initial
alignment procedures with alignment fixturing and a LOS supplied by Janeen
R. The alignment test was done in the x-arm station, following procedures
for alignment of the 4k ETM.

We successfully ran through the complete alignment procedure, positioning
the dummy optic to its vertical and transverse position with a scale
mounted to the fixture. We read the axial position with a prism mounted to
the fixture, and set the angular orientation to within 1 arc sec to the
autocollimator.

Several issues were brought out which need to be resolved:

  1. We found a 10 arc sec error which appears to be either within the
instruments, requiring a careful calibration on an optic bench, or with the
parallelism of the autocollimator to the theodolite line of sight.

  2. Friction within the adjustment screws of the SUS alignment fixtures need
to be reduced to consistently attain precise adjustments and prevent galling.

In addition, we tested the autocollimators range by autocollimating to a
PNI optic with 10% reflectivity @ 635nm at a distance of 150 ft.
 

ISC control code development (MZ for Daw & Fritschel, on travel)
----------------------------------------------------------------
Daniel Sigg visited this week from LHO and helped us get our sw
development environment up and running, as well as get our GPS
timing system functioning.  We should now have everything in place
to test the supervisory control code and GDS/ISC
communication.

Lock acquisition (Ware)
-----------------------
It's been bugging the heck out of me for some time now that, given my
bright shiny new LIGO plant transfer functions obtained at the cost of
three cpu-weeks of computation, and which for the most part can be
reconciled with the theoretical derivations, it's still something
of a crapshoot whether any individual feedback controller used will
be stable and lock.  Why this set of poles and zeroes, and not this
slightly different set?

SMAC ought to always have had an open loop gain
(optics*pendulum*controller, not just optics) transfer function
option, with amplitude AND phase, since that is, in the end, the
result which makes the design of feedback controllers an engineering
task, and not black art.  So I've delved into the (largely
undocumented -- unless you consider the code itself the documentation)
FORTRAN and Matlab code to see whether this could be done, and if not,
why not.  It actually doesn't look that difficult, so after a few days
of study, I am about to attempt making the requisite changes to the
code.

ISC sensing table assembly (Zucker for Fritschel & Adhikari, on travel)
-----------------------------------------------------------------------
With all the parts in-house, the second beamline (MC reflection) is now
coming together.  Alignment and testing of the EO shutter with its
driver is underway.

-------------------------------------------
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
--------------------------------------------
 

Prestabilized Laser -- Peter King
--------------------------------------------

- The frequency shifter used in the PSL has been aligned and has a measured
single pass diffraction efficiency of 90%.

- The PSL is now locked to the reference cavity under the EPICS interface.
The laser remained locked overnight.  A quick in-the-loop frequency noise
measurement indicates that the performance is consistent with the PSL
requirement of 10 mHz/sqrt(Hz), if not 2-3 dB better.
- The cross-connect panel for the LLO 4k IFO has been wired and completed.

- New temperature stabilization hardware has been fabricated.  Installation
of the new temperature stabilization hardware on the LHO 2k IFO will take
place in early-to-mid December.
 
 

Task                  Current Completion Date
__________________________________________________

- LHO 2k IFO:

Frequency servo        11/30 or sooner.

Pre-modecleaner servo.   Complete

Temperature servo    12/31.

Intensity servo        11/31.

Beam handoff to IOO     12/31

Servo characterization      12/31.
 
 

Input/Output Optics -- Dave Reitze, UF
-----------------------------------------

No report received.
 

Core Optics Procurement and Metrology -- GariLynn Billingsley
-------------------------------------------------------------

Characterization of flat C continues.  Low frequency results from three
flat tests were grafted together with high frequency results from the
random sampling of FM2.  The cutoff was Z8 (a combination of spherical
aberration and power).  This composite picture of C was subtracted from
a measurement of a pathfinder optic and compared term by term to the
CSIRO measurement of that optic.  Power compared well, the mid spatial
frequency terms were a bit off and the high frequency terms were within
a thousandth of a wave of the CSIRO result.  We are now working with
other three flat test methods to add certainty to the lower frequency
characteristics of flat C.

Delivery
We can deliver measured optics at any time given two weeks notice.  We
understand that a RM and ITM will be needed at Hanford by mid December.
We will continue to use the precious time between to characterize flat C
and reduce the error bars on our measurement.
 
 

Core Optics Coatings -- Helena Armandula
--------------------------------------------------

REO Contract-COC's coatings: Waiting to receive the next 4ITM from CSIRO to
schedule the next coating run.
Characterizing coated and uncoated optics to be able to recognize coating
defects from polishing defects.
Received coated mirrors for M. Smith and Peter Fritschel.
 

Core Optics Support -- Michael Smith
------------------------------------

BEAM-DUMPS
The shop has almost completed the fabrication of the double cavity
beam-dump. Ara (works half-time for COS now) is finalizing the layout for
the SEI-mounted beam dump for GB RMHR3 in HAM3 and the LOS-mounted beam
dump for GB 2K BSHR3P. Craig C. is working on the triple hinge joint for
the cavity beam dump mount.

ARM CAVITY BAFFLES
Paul K. is in process of making detail shop drawings for the vertex arm
cavity baffles.

ETM and PO TELESCOPE
CC Development, Mike S., Ken M., and Jonathan K. conducted a final design
review on 11/12/98 of the completed working drawings for the ETM and PO
telescopes. Recommended corrections are being implemented by CC
Development. Completed sets of working drawings for both telescopes are
expected by 11/20/98. Preliminary results of the finite element analysis of
the PO telescope have been received. The lowest fundamental vibration
frequency is on the order of 30 Hz, which is acceptable. The FEA of the ETM
telescope in in process.

MOCK-UP
Work is on hold unit after the Thanksgiving holidays when Jonathan gets
back from Livingston.

PO MIRROR
Ken M. has sent out shop drawings to build a prototype PO mirror assembly.

CONICAL BAFFLE
Craig has completed shop drawings  of the cryopump baffle for the vertex
station.

MANUFACTURING
Jonathan and Mike S. have released specs for the ETM telescope and the ETM
Telescope lens elements.

COS FDR
Paul K. prepared updated integrated layout drawings. Mike S. has sent the
COS Final Design Document to the review committee. He is updating the
supporting documents, and completing the view graph presentation. The COS
FDR is scheduled for 11/25/98.

SCHEDULE

item                                    order placed    receive date

PO telescope mirrors                    11/12/98        3/12/99
PO telescope mirror coating             TBD
PO telescope assembly                   TBD
ETM telescope lenses                    11/18/98        1/18/99
ETM telescope assembly                  TBD
Faraday isolator                        11/13/98        2/18/99
Steering mirror mounts                  11/12/98        1/12/99
Periscope hardware                      10/26/98        11/26/98
Steering mirrors                        8/31/98         11/20/98
 

--------------------------
Isolation Group -- M. Fine
--------------------------

Seismic Design (Mike Fine)
--------------------------------------
1. Coarse Actuator Testing:
The full motions were tested last week.  Hytec began by making each
move request independently.  All six DoF's were tested with substantial
margins of safety added to the range of motions.  Independently, these
motions can be as much as twice as large as the required, but do not
exceed the bellows requirements.  Therefore, Hytec tested each DoF's
to twice its required range and did not experience any mechanical or
electrical failures.

2. Coarse Actuator Development:
Hytec made corrections to the transformations routines. The desired
actuations are now being made for all rotation and translation
combinations. Hytec identified a problem in the software for motions
that require a single actuator to move a small distance relative to the
remaining actuators and are currently addressing this problem and will
determine and implement a solution this week.  They are also designing
a more visual interface for the motion commands, that will allow the user
to command either relative or absolute position. The new interface
provides graphical gages that indicate angular and translational positions.

3. Air Bearing Testing:
Hytec successfully tested both the lift capability and full range of
motion and showed that the air bearings are performing as required.
Specialty Components has now been directed to proceed with the production
order for the air bearings.

4. Near-Term SEI Hardware Delivery Schedule:
1 HAM optical table and 1 HAM support table                 11/30/98
8 HAM Bellows (Livingston)                                 ~11/30/98
4 sets of HAM legs                                          12/4/98

Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)
-------------------------------------------------------------------
1. Alignment Dry Run:
Janeen is at LHO working on the dry run.

2. SUS Hardware Delivery:
SUS Structure Delivery Dates: [numbers in parentheses are quantities.]
LOS1(for ETM, ITM, MMT): 11/7(2), 11/19(1), 11/29(1), 12/06(1), 1/10(1),
                      1/17(2), 1/24(2), 1/31(2), 2/07(2), 2/14(2), 2/21(1)
LOS1(for RM): 11/19(1), 12/06(1), 12/13(1), 12/20(1)
LOS2(for BS): 1st artcle on 12/11, 12/13 (3)
LOS3(for FM): 12/13(3)
SUS Height Adapter Delivery Dates:
MMT3, RM: 11/14 (6)
BS, FM: 11/21 (5)
SUS Fixtures and Components Delivery Dates:
PAM Brackets: 11/5
Clamps: 11/13
BS Test Mass: 11/6
BS suspension blocks: 11/5
 
 

---------------------------------------------------------
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
---------------------------------------------------------
 

Global Diagnostics System (Daniel Sigg)
--------------------------------------

1. Work on the back-end of the diagnostics test tool proceeded.
Peter F. wrote a general purpose 2^n decimation algorithm
which includes an 42th-order FIR filter to avoid aliasing problems.
Ed D. is in the progress of wrapping up the Fourier tools
(power spectrum, cross-correlation, coherence, etc.). These
FFT tools will implement a heterodyne technique to zoom in to
an arbitrary frequency band. D.S. started writing the code
which stores diagnostics data in memory and saves/restores it to
disk. Looking into adopting the (new) LIGO lightweight data format
(XML based) as the native file format for diagnostics test
parameters, data and results.

2. Had some extensive talks about the future of the diagnostics
data monitoring tool (aka trigger tool, aka search tool). John Z.
agreed to lead the effort with help from Walid M. and Serap T.
The current thinking is to implement these data monitors on a
(multi) CPU shared memory system which gets the data from the CDS
network data server (aka frame builder) through a high speed link.
The system would consist of the following components:
  1) A shared memory data distribution component.
     a) Data producer API
     b) Data consumer API
     c) Distributed buffer management.
  2) Online data receiver process (copies data from NDS to
     shared memory)
  3) Trigger generation API (send trigger meta-data to the
     online database).
  4) Trigger application environment interfaces.
     a) for MatLab
     b) for root
  5) Signal processing library
  6) Process control/Error Handling (undefined)

3. An important consideration is to define a (first) set of
physically motivated monitoring tasks, so that this effort gets
coupled with the detector shake-down as early as possible.

4. Went to MIT to discuss the ISC/GDS interface and help installing
a VxWorks system which will make it possible to run the excitation
engine in one crate and the ISC supervisory/data transfer code in
an other (connected by a reflective memory ring). We were able to
install, compile and load the complete GDS front-end software.

5. Also discussed the details of implementing a swept sine test and
the Fourier analysis tools: length of data sets, settling times,
windowing/overlap, averaging, measurement times, etc. etc. We agreed
on the basic software organization and who is writing what.

6. No final conclusion was reached on the graphical user interface
for the diagnostics test tool. Commercially available packages seem
to be either too specific or require a fair amount of programming.
A decision was made to cleanly separate the test organizer code
from its user interface, so that we are not locked into a solution
which might turn out non-ideal.
 

Physics Environment Monitor (Alex Marin)
-------------------------------------------

More work was done for the final design of the cosmic muon monitor.
For the Livingston site, a ruggedized weather station has been chosen.
The Davis weather stations will be mounted at the end stations.
 
    A web site is under construction, which will contain all the PEM
    relevant information. At the present time, the deliver/order
    schedule can be found at:

    http://web.mit.edu/marin/www/PEM_Delivery.html
 
Shourov continue to work on simmultaneous seismic measurements at Hanford
and Livingston.
 
Matt S. is in Hanford this week His report follows:

>  PEM activities for this week include the determination of accelerometer
>  cable lengths to the new PEM racks in the LVEA.  These will be ordered next
>  week when I get back to Boston.
>  I have received the PZT shakers that I shipped here and have unpacked them
>  and put them into PEM storage.  The Livingston DAQ system was shipped to LA
>  from Hanford, The Display has not been shipped yet due to its shipping box
>  being misplaced.  I need to try to find another box to use.  The
>  Electro-magnetic shakers, power supplies and appropriate mounting hardware
>  was sent to Hytech and received. The interface plates were sent from the
>  vendor directly to Hytech.  These will need to be fit checked.  I have
>  discussed relocating the PEM RGAs to a more convenient location.  One
>  suggestion was to place them into the unused HAMS for the 2K and 4K.
 

Optical Contamination (Daqun Li)
--------------------------------

All the three contamination cavities are back on-line with light
illumination.  The initial ringdown and mode spacing data for both
cavities 1 (with viton) and 3 (with Faraday) are well consistent
with the previous data of those two cavities.  A few weeks is
needed to complete the qualification process of those two materials.
Ringdown and mode spacing data is still taking to qualify the empty
cavity (cavity 2).

Still working on the Loss Scanner to detect points of defects on
a 3" flat optic (T=1500 ppm) with the scatterometer under computer
automation.

-----------------------------------------
Control and Data System -- R. Bork
(WBS 1.2.2)
-------------------------------------------

Near Term Installation Activities:
=======================
- Nov. 30 thru Dec. 4:
     - Complete installation of IOO suspension controllers
     - Install GPS timing equipment in LVEA
     - Install rack internal wiring/initial electronics for IOO ASC/LSC
     - Contractor to install fiber optic cable at Livingston (provided cable
arrives as scheduled next week)
- Dec. 7 thru Dec. 11:
     - Install first DAQS equipment in LVEA (2k system + 1st PEM)
- Dec. 3 thru Dec. 17: Continued commissioning activities on PSL electronics
 

Data Acquisition
============
- Reflected memory boards for Sun workstations being returned to factory for
test.
- Work around using fast ethernet in place of VME to Sun reflected memory is
nearly complete; getting sustained rates of ~3.5 to 4MByte/sec total system
thruput with a single network attached. This can be scaled by adding multiple
fast ethernet links.
- Have been experiencing problem of running multiple of the new 24bit ADC
boards in a VME crate; turned out to be an error in the ADC manual for setting
jumpers, but it caused delays in getting software done.
- Began writing software to interface GEO's Triana software package to the
DAQS realtime network server.

Timing
======
- Driver software being written for the new binary clock GPS receivers.
- Received the first two GPS Receivers with the binary clock modification.
One is being tested at Cal tech, the other at Hanford. Three pairs of clock
fanout modules are completed, one for each receiver and one for further
development of the Sync Error circuit.
 

Suspension
================================
- 10 Satellite amplifiers and chassis are complete and ready for shipment to
Hanford. 8 will be installed as part of the 2K IOO suspension system on
Nov. 30.

- DAQ daughter cards have been received and will be stuffed and tested as
time permits.

IOO
================================
- Rack 2X6 cross connects are 95% complete and will be shipped to Hanford for
installation on Nov. 30.

ASC/LSC
================================
- Lori has a full working version of the ASC front end software running. This
version includes the ADCs, reflective memory, all filtering, which is
selectable, and operator displays for controls and monitoring. Right now
there appear to be no show stoppers for the LIGO ASC front end system. A version of
the LSC front end system will be started next week.

MC LSC
=================================
- A second MC Length Demod board is being assembled so we'll have a spare for
the IOO commissioning. A bias adjust and monitor are being added to the
final version of the photodiode. This will also have to be added to the
Demod board in the final version. The design of the MC Servo Amplifier is
progressing. We are expecting a first article by the end of December.

PSL
*********************
1.  Finished submission of all PSL electronics documentation to the DCC

2.  90 % complete on all remaining known orders for circuit board parts for
the remaining two PSL's.

3.  Worked with Peter King over the phone to get the frequency servo locked
and functional at Hanford.  One of the installed prototype frequency
reference cards had to be shipped back to Caltech for work.  Work was
completed and the board shipped back.  It is now functional and installed
and the servo has remained locked overnight at spec levels.

4.  Set up trip to Hanford for continued testing 3 Dec to 15 Dec.
 


WBS 1.4    Project Office



 

 1.4.1.2 Project Controls (Lindquist)


PROPERTY MANAGEMENT (Chargois)

>From: Ed Chargois <chargois_e@ligo.caltech.edu>

Liaison visit to the General Services Administration (GSA) Office and the Defense Re utilization Marketing Office (DRMO) throughout the San Diego area for the purpose of locating surplus government property to be used by the LIGO Project. Acct # 5N502.

Signed for a Street Sweeper (MFG: Elgin Ser# S5052D) Acquisition Cost $44,860 transportation.  Arrangements are being made to transport to the LIGO Livingston Observatory. Acct # 5D522.

Assisted the CDS with the shipping of a Electronic Board to the LIGO Hanford Observatory attn D.Barker, schedule delivery date 11-23-98.


DOCUMENT CONTROL CENTER (Turner)

>From: the DCC <dcc@ligo.caltech.edu>

COST SCHEDULE CONTROL SYSTEMS (Duncan, Rianda, Leonhardt, Akutagawa, Kaufman)

>From: Cindy Akutagawa <cindy@acrux.ligo.caltech.edu>

 I am working on my monthly reports.

>From: "Britt Leonhardt (T)" <brittl@FINANCE.caltech.edu>

I have been coordinating with Dorothy and Phyllis to iron out some vendor problems and accounting errors which allows us to pay these invoices in a timely manner.

[Estimated activity (these are partial weeks. Data was not available for full week.) -pel]
 

WE Date Incoming Invoices and Receivers Wire Transfers Large Contract Invoices New Purchase Ortders
10/08/98 248 2 9 155
10/15/98 225 0 4 157
10/22/98 247 0 1 58
10/29/98 182 1 4 42
11/6/98 141 2 20 91
11/12/98 
11/19/98
132 
118

2
11 
8
 63 
 14

>From: Kris Duncan <kris@ligo.caltech.edu>

Completed the input of earned value and estimate to complete status into COBRA.  Distributed final drafts of the CPR's and SPA graphs  to task managers on Wednesday, November 18, for their review.  Completed the October 1998 CSSR and SPA graphics for review in Monday's Project Control Meeting.  Also, initiated preparation of presentation materials for the meeting.

Prepared a reconciliation of the LIGO cost reports to the CIT financial reports.  Also, prepared a comparison of BAC's and EAC's from the September 1998 to October 1998 reporting periods.

Began investigation and evaluation of accounting software packages for Installation/Operations cost reporting.  I have received some demo files and will be analyzing them to fit our criteria.

Created and implemented new excel based spreadsheet for calculation of monthly EAC for both the Facilities and the Detector.  Decreasing the amount of manual calculation that is done monthly to determine EAC when a status of "no change" is submitted.

Finished reviewing of Hytec's MS Project schedule.  All changes to dates, durations, and relationships of note have been incorporated into the current Open Plan Schedule for the Detector.

Finished producing the last first draft of the schedules and distributed to the appropriate task managers.
 

>From: Florence Kaufman <fkaufman@ligo.caltech.edu>

No report this week.


SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

>From: irena@ligo.caltech.edu (Irena Petrac)

>From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

Carrier Building Systems and Services has been notified that they have been selected as the mechanical maintenance contractor for the Livingston Laboratory. The contract is being prepared and is expected to be sent to them for signature on Thursday, November 19.

Modification No. 13 is being issued to the CBI contract in the amount of just over $97,000 to cover several change order requests.

A Technical Review Board meeting will be held on Thursday, November 19 to discuss the LIGO position on fluporel O-rings for the midpoint gate valves at Livingston.  There are several technical and contractual issues with PSI requiring resolution.

Representatives of Hensel Phelps toured the Livingston site on Thursday, November 19, with some of their subcontractors to try to correct some of the deficiencies discovered in the buildings.  LIGO personnel will request a plan from Hensel Phelps to correct these defects.

The exchange of correspondence among LIGO, LSU, and the State of Louisiana regarding the Livingston access road is being forwarded to the NSF for informational purposes by Sandy Pool.

The State of Washington Department of Revenue has requested that LIGO submit forms to register as a business in the state.  These forms have been forwarded to Sandy Pool for handling.


1.4.2.1 Quality Assurance (Tyler)

>From: "William H. Tyler" <tyler_w@ligo.caltech.edu>

Nothing significant to report this period.
 


WBS 1.4.3    Systems Engineering / Data Analysis and Computing



 
 1.4.3  Systems Engineering

1.4.3.1  Systems Engineering & Integration (AL, BB, CC, JK, DC)

Reliability:

* LIGO Service Center Task #: 100096.11:     2.0 Hrs
    Nothing significant to report.

* Met with Jay Heefner and Dale Quimette.  Design status of CDS ASC/LSC
  remains unchanged. Reliability effort will remain suspended until
  sufficient design information becomes available.

ELEVATED PLATFORMS:
Preliminary effort was made to find an elevated platform to allow access to
the BSC chamber. A pass through version is required for working in chamber.

SEISMIC BALANCE WEIGHTS
First 10# weight was submitted to & approved by LIGO last week. Production
was started and hopefully machining is finished on all 10,000# of weights.
Passivation should be finished on the first 1000# and this lot should be
shipped to our Northern California vendor, for bake out, by Monday 11/23/98.
Balance to be shipped in 2000# lots every other week, starting in two weeks.

X & Y-BEAM SPOOL BAFFLES(COS COC BAFFLE)
Detail part changes have been completed but shop drawing effort has suffered
due to other priorities. Barring any new major interruption, details should
be finished by Tuesday 11/24/98.

1.4.3.3 Modeling & Data Analysis (KB/HY/AL)

Kent Blackburn:

* Made two more revisions to the documentation for the GenericAPI.

* Began writing the requirements document for the ManagerAPI.

* Integrated new staff (Xiao Hu) into the LDAS. Xiao will be our
  database programmer and has already started working with me on
  getting DB2 on our system.
 
* Met with Roy Williams to discuss purchasing a DB2 license/software
  for one of the LDAS servers.
 
* Met with Dave Hackenberg of Fore Systems to discuss potential solutions
  for the LDAS network. An interesting feature identified is a Gigabit
  uplink in the 2810 switch that could feed the Beowulf with its OS.

Phil Ehrens:

* Designed developed and implemented a self-documentation
  method for Tcl/Tk scripts.  The output format is HTML.
  Features include a table-of contents linked to individual
  procedures, and colored syntax highlighting of the Tcl
  code blocks.  Look and feel is highly consistent with
  the LDAS GUI help system file format.

* Removed widget dependency from the "openLog" procedure
  in the genericAPI.tcl script based on concerns expressed by
  Albert Lazzarini regarding the robustness of the procedure.

* Began to install system software into the new standard
  installation directory hierarchy using Ed Maros's build
  maintenance system.

David Farnham:

* I have met with Walid to discuss the FCL API.  I am now working on
  defining the functions which the FCL API should implement.
 
* I have been running benchmarks on the Beowulf cluster (mpbench and
  other parallel code which I have come across) in order to test the
  stability of the new kernel (2.1.127) and to measure the performance of
  the cluster.  So far the new kernel appears to be stable -- there have
  been no problems during a ~48 hour test (running parallel code).

* M27 has been upgraded to RedHat 5.2.  I have also installed the
  Tripwire (v1.3) security package.

* I have added a couple more test programs to the Generic API.

Xiao Hu:

* Read documentation on LDAS provided by Kent

* Read documentation on XML

* Installed / Tested Demo DB2 verions on LDAS NT machine

Bruce Sears:

* Studying and reworking the E-log system to make it more portable and
  maintainable in preparation for installation at the Hanford facility.
 

Adlib : multi-mode implementation (BB)

* Large Angular reflections from mirrors introduced.

* Mirror transversal displacements introduced.

* Beam-shift class is ready but we decided to keep it waiting outside e2e
  for the time-being in order to keep the code simpler by avoiding one or
  two presumably weak effects.

* Some more improvement in computational speed could be achieved by cleaning
  the code.

Adlib : Mechianics (HY, GC, SM)

* Giancarlo Cella has sent us a note summarizing his work. It is available
  in /home/e2e/Software/docs/e2e/mechanics/.

* Somuya sent in a status report. He has started implementing his model of
  a suspended mirror in Matlab, and he will send us the code. When
  delivered, that code will be ported to e2e environment. This module will
  be used (1) for a fixed configuration - a simple suspension mirror -
  simulation and (2) for the validation of Cella's generic model. Somuya's
  dynamic formulation will be included in Cella's code where appropreate.

* The interface modification of e2e for Cella's mechanics module is still
  going on.

Alfi: (EM)
* Continued working on getting new version.

Admin: (EM)
* Compiled and installed several software packages

* Trying to figure out how to configure a cvs server and get it installed
  on spica.

Misc: (SK, HY)
* Dr. Klimenko of UFL is visiting Caltech from 11/17 to 21. He presented
  his idea of implememting fields, and the comparison with modal model was
  discussed and some simulation runs will be used to understand the
  difference.

* During the stay in Japan, Hiro visited SuperKamiokande site and gave a
  talk about LIGO status. He met Prof. Totsuka of ICRR and explained LIGO
  status and LSC. He finished the installation of the FFT program on TAMA
  machine and explained the physics and usage of the program to TAMA
  scientists.

1.4.4.2  General Computing (LW/TE)

MIT:
Nothing to Report

Livingston:
Modem pool should be online this week. Other network issues appear to
have been resolved. Changes for the DNS tables to allow for direct e-mail
services to the Observatory should be done by next week.

Hanford:
The permanent T1 line has been turned on.  Twelve computers have moved to
the permanent line.  The rest of the computers will be moved when Christine
returns the week of Nov 30th.

General Computing will have ethernet connections in the LVEA.  This will
allow the Bakeout crew and Detector Installation crews to use the electronic
logging tool, elog.

Two P5-90 will be used in the LVEA as GC computers for elog and downloading
documents.

CIT:
Installed the web application for reserving a document number in
order to do some parallel testing.  The application is failing because of
privileges.

Prepared a spreadsheet that is an electronic view of the DCC (all
directories with PDF files, all Access database files, and all the
WebBase web pages).

Updated WebDocs and installed November newsletter on the web site.

Continue work on getting software pkgs. installed on the new GC server.
The licensed pkgs. are taking considerable time.

Held number of meetings with the LDAS network planning is still going on with
multiple action items on getting more information on equipment as well as the
future plans of the WAN in the areas of the Observatories. The quotes from
FORE and SUN have arrived.

We have received and installed multiple workstations and computer related
items. We now have a two digital camaras that people can check out for use
in project documentation. Currently, one camara resides with Larry W. and
the other with Elizabeth W.

Samantha working on docs and some minor s/w upgrades to the modem pool.

Performed some minor software upgrades to some of the networking equipment.

Working on the final procurements that are to be placed against the 5N510
account so we will be able to close that account in the near future.
 


WBS 1.4.4.1    Administrative Group


 Dorothy Lloyd

 Continued processing heavy load of purchase requisitions, POs, change orders, check request, etc. as well as extremely heavy load of invoices.

 Followed up and tracked problems with invoice payments.

 Entered AP30 reports into the database.

 Continued to monitor and support the temporary help.

Elizabeth K. Wood

 Got a temp to help Linda Turner out with a mass mailing in the DCC. I believe he starts tomorrow (Friday) morning.

 Made arrangements to move Barbara K’s phone over to Millikan and install a new extension in room 364 for the day when we have a visitor sitting there.

 Sold many LIGO Livingston t-shirts after the PAC meeting this week.

 Handled many personnel matters including personnel requisitions and paycheck problems.

 Tried to find out from the bookstore about ordering calendars.

 Purchased a substantial supply of black and yellow ink cartridges for the color plotter and color printer in room 18 (and elsewhere).

 Communicated with Ben Ortega about visa issues.

 Did payroll.

 Covered for Irene while she was ill.

Rita Torres

Attending a writing class. Unavailable for report.

Irene Baldon

Released from the hospital Wednesday. Should be back with us Monday or Tuesday.
 


For additional information about this report, contact sanders@ligo.caltech.edu