Weekly Report for Week Ending April 28, 1998



Project Control Meeting Agenda    Facilities    Detector    Project Office    System Engineering    Administrative    Hanford Observatory    Past Weekly Reports

The Project Control Meeting Agenda for Monday  May 4, 1998 will be:
 (Meeting time: 10:30 am Pacific Time)

  1. Announcements (5 minutes)
  2. Review of Action Items (10 minutes)
  3. Comments on Weekly Report (5 minutes)
  4. Field Change Orders/Contingency Liens/Change Requests (10 minutes)
  5. Review of ISSUES AND PROBLEMS by Subsystem (10 minutes each)
Special Items:


Special Announcements:  The March issue of the LIGO Newsletter is now posted at:

http://www.ligo.caltech.edu/LIGO_web/9803news/9803main.html


WBS 1.1    Facilities Group



 
From: "gerry" <gerry@ligo.caltech.edu>
Date: Thu, 30 Apr 1998 09:20:34 -0500

WBS 1.1.1 Vacuum Equipment(Worden)
 
    1. Gate Valves:
    In preparation for the first LVEA bake, PSI has bagged three
    valves connected to the left beam manifold and found no
    more problems here.
    PSI is waiting for a written report/plan to deal with the leaky
    bellows.
 
    2. One bake oven load remains to be processed to complete the
    MIT chambers.
 
    3. All LA chambers have shipped. Only GNB valves remain
    to be shipped.
 
    4. Installation activities:(Kyle Ryan)

    X-arm end station:

    GNB determined that the 44" VE gate valve
    leak was the result of a damaged lead screw
    bellows.  They have one on order.

    X-arm mid station:

    PSI inspected the interior of the 2500 L/s ion
    pump and found that the gap between one of the
    two high voltage bus bars and ground was too
    tight (only one of the two pumps which comprise
    the "2500 L/s ion pump" had been functional).
    They increased this gap and it appears to have
    fixed the problem.

    Corner Station:

    PSI replaced the vent line bellows on the left
    80K pump (long).  No welding was performed.  The
    local roots pump PSI was utilizing to rough the
    left BT manifold exhausted oil.  Only one pipe
    section of the header was effected.  It was clean-
    ed and the pump will be repaired.  The left BT
    manifold is now pumped down and leak checked.
    Most of the bake blankets have been installed.

    Y-arm mid station:

    PSI is preparing for the "100 hour back to air"
    commissioning.

    Y-arm end station:

    PSI modified the 80K pump level control valve by
    changing the needle and seat sizes.
 

Livingston Status (Allen Sibley)
 

1) Rec'd the req from Ed Jasnow for LN2 for LA. Bids are due in 5/11. PSI
requires LN2 on 6/8. This will be very close and I will continue to
monitor.

2) Cleaning of the LVEA floor has been completed and Dave Evers has
accepted the responsibility for maintaing the area.

3) The overhead door in the Rt. end is still broken. No one seems to know
what happened to it. If this is not resolved by soon we will be impacting
PSI. The part that is needed is here according to H-P but no one is here
working on it. I will contact H-P to get this moving. It will take a day to
install and  we may have a problem with PSI's access to the VEA to install
the BSC. PSI is ready to move it into VEA and may claim that their
installation schedule is being impacted.

4) I have informed Dave Evers that LIGO will clean the area outside the
cleaning area with brooms only and that that will be the end of LIGO
responsibility for keeping the area clean.

5) We had several meetings with SJB regarding the survey of the LVEA and
arm-1 end station. We think we now have closure and have a meeting
scheduled with Albert and Larry to finalize the results.
 
 

1.1.2  Beam Tube (L. Jones)

     a. Tube section fabrication status, Magnolia Beach shop
     (running totals):
                Leak     Leak
             Formed  Tested  Failures Cleaned    Shipped

     as of 4/21:   395    370    0  370   316
     as of 4/28:   400    379    0  378   332
 
     The final tube section for LIGO has been formed and is
     progressing through the shop. Shop fabrication should
     be complete in two weeks; demobilization follows.
 
         b. Tube section installation status (Livingston site):
         (running totals):
                      Inside Leak   Leak Final
           Welded Repairs Tested Failures Aligned

         as of 4/21*:   312    20   310     0     0
         as of 4/28*:   328    20   326     0     0
 
         * Includes gate valves as the finish "tube sections"'
         Installation will be complete when weld, leak test,
         and alignment all reach 404.
 
        Turbopumping the X arm continues, with minor problems
        causing pump shutdowns. CBI has been requested to take a
        wipe sample to check for oil contamination each time a
        vacuum pump line has been disconnected, following the
        recent discovery of oil in a Roots roughing pump exhaust
        line at Hanford.
 
        CBI has started coring the holes in the concrete enclosures
        for direct GPS access on the beam tube supports. Of 34
        needed on the X arm, 16 have been cored to date.
 
        CBI has issued a request for direction regarding SJB's move
        of the interface mark on BT/VE1 and CBI's questioning of
        the BT/VE4 mark. A meeting will be held on 4/30 to discuss
        SJB performance and our response to CBI's request.
 
        BDF air flow performance since 4/21:
        Particulates (0.5u)/cu ft: 16 (max., any day)
        Dew Point, degrees F: 1-8
        Temperature, degrees F: 48-51
 
        Of the 326 tube sections installed, 286 have now been covered
        with enclosure sections.
 
    c. Planned meetings:
 
                6/2/98: monthly project status review, Livingston site
 
                7/1/98: Completion Review, Livingston site (performed
                early due to manpower availability)
 

Hanford Construction (Otto Matherny)

   Levernier

      Consolidated Punch List

      Total punch list items remaining- 58
      Total Corrected-                 45
      Total Signed off-                45

  
   OTHER ITEMS
 
      Received the 90% design on the new support building.

      No change on the water system.

      No change on the telephone PBX.

      No change on the maintenance sub contract.

 
Livingston Construction (Gerry Stapfer)

The site  has received 9 inches of  rain during the past two days. The
access road is flooded but (more or less) passable.
 

HENSEL PHELPS

--Working on outstanding notice to comply and punch out items.
BERNHARD MECHANICAL CONTRACTORS-installing AHU ducting in the warehouse
building.  Connecting sewer line to the sewage plant at the trailer site.
 

WOODROW  WILSON

--Installing B unit doors and hardware along Arm 2.
--Removing the nitrogen pad base plates at the Arm 1 End Station.
    --Grouting , patching bug holes and caulking around the installed BTE's
along Arm 1.
    Total Enclosures Cast   2390
    Total Enclosures Approved  2215
    Total Enclosures Installed 1862
 

Issues:

HVAC at arm-2 end station continuous to shut down at night and needs to be
re-started every morning. We are monitoring the DEMCO power to ascertain
whether the problem is at DEMCO or with Trane.
Some over head doors and cranes are intermittent and often inoperative. The
Door and Crane subcontractors are working on this issue.
Parsons is working the issue of the wrongly installed cooling coils.

 


WBS 1.2, 1.3    Detector Group


Date: Thu, 30 Apr 1998 18:03:41 -0400
From: David Shoemaker <dhs@ligo.mit.edu>
----------------------------------------------------
DETECTOR GROUP -- Whitcomb/Shoemaker

(WBS 1.2, 1.3)
----------------------------------------------------
-----------------------------------------------
Implementation Group  -- Mark Coles/Fred Raab
-----------------------------------------------

40m (Jennifer Logan)
--------------------

Last weekend's earthquake has misaligned the East End mass to an extent
where we have to vent in order to realign it.  This vent is planned for
the end of the week to allow Bil to finish some wavefront sensor
working that is being done on the simple Michelson.

As a first step, the differential mode in yaw of the Simple Michelson
has been controlled by the wave front sensors.  Today we hope to
implement control of both pitch and yaw.  Walid is now starting work on
software for the wavefront sensing which will be a great help in
implementing the system.

As part of testing one of the wavefront sensor heads it became evident
that we were seeing fringes at the symmetric port despite the fact that
the only interferometer component aligned at the time was the recycling
mirror.  We tested components outside the vacuum system and failed to
find a culprit for the parasitic interferometer and so when we vent
this week we shall take the opportunity to look inside the system for
the cause.

Dick has been continuing his work on designing and testing an aluminum
substrate for the Pockel cells and I have been looking at the Lithium
Niobate cell that was sent to us by New Focus for testing.  However given
that work at the 40m at 514nm will be scaling back towards the end of the
year and that our current cell shows no signs of degrading so far and
we have spares, we will be scaling back this effort.
 

----------------------------------------------
Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
----------------------------------------------

Initial alignment (Zucker, Mason)
------------------------------------
Completed IAS final design review 4/30.  The most significant actions
concerned coordination and time phasing of the suspension installation
among SUS, COS and ISC tasks, and trying as much of it as possible in
advance to get the dance steps down.  Very few actions concerned the
IAS equipment design.  We have received preliminary approval to proceed
with procurement and fabrication.  Thanks to the committee and
observers for many helpful comments.

LSC lock acquisition (Ware)
------------------------------
Learned more about the original design of SMAC and controllers, in the
process of studying discrepancies between Bode plots and SMAC results.
Implemented a State indicator in SMAC which delineates what state the
system is in at a given time.  Started to look at deriving phase
information from SMAC variables (not done in original model!).  Met
with Dave Redding to discuss completion of documentation of SMAC
modeling.  Discussed various details with Lisa.

In other words, another step up on the learning curve this week.

ISC Design/Testing (Mavalvala)
--------------------------------
LSC Detection Mode Controls:
The LSC common-mode design is complete enough that documentation
is underway. Small design tweaks are still in the works as the
anti-aliasing filter and test mass resonance notch filter designs
are developed and tested by Dale O.

We tested some time-domain simulations on the common-mode servo
model in collaboration with Gabriela G. at PSU. Except for the
very simplest stripped down loop, the integrations failed to
converge, again attributable to numerical instabilities.

ASC Controls:
With Gabriela G. we revisited the wavefront sensor control model
to determine the status of the ASC controls design and update the
models for the Final Design.

LSC Photodetectors (Zucker for Csatorday)
-----------------------------------------
The first production LSC main photodetector module is now
undergoing linearity and response tests in the optics lab.
Looking good, Dale!

LSC digital loop test @ PNI (Fritschel, Daw)
--------------------------------------------
o Ed D discovered that the glitches seen in the output of the Pentek
DAC were due to timing errors in the system; he tracked this down
further to an intermittent  increase in the time taken by the Baja
processor to respond to the Pentek's ADC interrupt. This in turn was
caused by a network process running on the Baja that seemed to have a
too high a priority. Suspending this network process resulted in
glitch-free operation. The problem now is to figure out how to keep the
network task running (so we can communicate with the processor), but at
a low enough priority so that it doesn't interfere with the Pentek
interrupts.

o We also working on the code to implement the servo filtering
functions for the Michelson loop, and learning lots of fun stuff about
digital filters in the process.
 

-------------------------------------------
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
--------------------------------------------

10 W Laser Contract -- Jordan Camp
------------------------------------

Nothing to report.
 

Prestabilized Laser -- Peter King
--------------------------------------------

- R. Abbott has been working on the VMEbus intensity stabilization servo,
as the previous version of the card did not provide enough gain to suppress
the intensity noise to the required level.

    Each stage of the salvaged card has been tested and more or less
behaves as predicted.  However when used to suppress the intensity noise,
there is still not enough gain beyond ~1 kHz.  At frequencies greater than
~7 kHz and less than 12 kHz, noise is added to the system.  With what would
appear to be ample phase margin (greater than 40 degrees and as high as 60
degrees), the behaviour of the servo is not understood at present.
 

Input/Output Optics -- Dave Reitze, UF
-----------------------------------------

IOO construction

We are still collecting quotes/orders for the IOO commercial parts.
Quotes have been requested from about 10 vendors for such things as
posts, mirror mounts, fork clamps, lens-holders, dog clamps, etc.

Mode-matching Measurement

Rana made measurments of capacitance of the bullseye photodiode -
good uniformity from segment to segment. Installed DAQ board with
software + LABView 4.0. Acquired connectors, cables, etc. Modified Head
Board box in the machine shop. Am beginning DSP programming today.

High Power Testing

We measured the stray B-field of a Faraday rotator of 12 mm clear aperture
manufactured by  EOT (Electro-optics Technology).  Previously we had
measured 8 mm. The measured B-field does not show substantial difference
from the case of the 8 mm clear
aperture Faraday rotator (manufactured by EOT) that we measured
previously. The maximum difference was observed at z~25 cm r<5 cm, where z
is the coordinate along the optical path and r is perpendicular to it. At
this location the B-field measured for the 12 mm aperture Faraday rotator
is higher than that of the 8 mm aperture Faraday rotator by ~25%. This
B-field is, however, still lower than the B-field level that we have
estimated to cause SOS displacement that is two to five orders of
magnitude lower than the open loop SOS displacement. Thus it can be
concluded that the 12 mm aperture Faraday rotator can be employed in the
2K and 4K LIGO.
 

Core Optics Procurement and Metrology -- GariLynn Billingsley
-------------------------------------------------------------

The first group of 5 substrates arrived at REO for coating, 9 more follow
this week.  The Contract for coating of the 40 LIGO optics has been
approved by NSF.  We expect the first delivery May 15th.

Brian Loucks is working again (after a brief hiatus while we switched IR
interferometer vendors) on tooling to support the interferometer and optic
under test.  Since the new configuration is very similar to the one at
NIST, delivery times are anticipated to be short.
 

Core Optics Support -- Michael Smith
------------------------------------

PO TELESCOPE:
D. Rose has completed the tolerance requirements for the 1) parabolic PO
telescope mirrors
and 2)refractive ETM PO telescope. Requests for final quotes have been sent
out for both sets of telescope elements.
K. Mailand is finalizing the details of the parabolic PO telescope mirror
mounts, housing, and support structures.

BEAM-DUMPS:
A. Badalian is working on the design of the beam-dumps.

COS PARTS LIST:
M. Smith has created a preliminary data base using a systematic naming
convention to describe top assembly, subassembly, and component for the COS
parts. The list can be sorted by category to obtain information about field
replaceable items, repairable subassemblies, and stocked items. The list
can be totalled to determine the total number of individual components
which must be ordered. The list provided data to track the order date,
received date, assembly date, and ship-to-site date.
 

--------------------------
Isolation Group (Mike Fine)
---------------------------
 

Seismic Design (Mike Fine)
--------------------------------------

1. Assembly Hardware:
Hytec has completed all the alignment of the prototype BSC up to the pier
adapter
plates. The procedure that was developed earlier has been proven workable.
Hyec is
making the necessary changes to the procedure, and will then adapt the BSC
process
to the HAM. Phase II hardware will ship to Hanford this week. We are
expecting the
>hardware to arrive at Hanford today. The order for the additional HAM rail
assemblies with Vertex has been placed. Orders for the Phase III assembly
hardware
for the HAM have been placed. In order to expedite the fabrication, the
orderd are
broken up such taht the bellows clamp will be fabricated by Jona in Los
Alamos, and
the remainder of the hardware, by Noor Mfg in Albuquerque. Delivery times
are 3-4
weeks for this hardware.

2. Coarse Actuator Component Testing:
The test fixturing for the actuator components have arrived at Hytec and is
being
configured. Hytec anticipates to test the flexure stage for the XY actuator
system
next week. The dummy Z stages and X/Y stages are being fit-checked at Hytec
this week
and, if all goes well, will be shipped to Hanford next week.

3. Air Bearing Assembly:
The prototype air bearing was tested earlier this week at Specialty
Component. The test
of both flate and spherical bearings was conducted under 3500 lb (BSC
load); with 150
psi air supply, the air gap of ~.0002" was achieved without any evidence of
vibration.
The flow meter was not avaialable to measure the air flow but SC will
obtain a meter
and measure the flow next week. They will also test the frictional
coefficient of
the surfaces.

Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)
-------------------------------------------------------------------

1. LOS Fabrication:
Bill Tyler and Mike F visited Brookfield this Tuesday. Brookfield has
completed the 1st article height adapter and are awaiting the rest of the
info on the compound angle definitions to complete the final machining of the
1st article welded structure. For the production lot, they have all the
components
machined and weld-prepped, ready to be sent to welder for assembly soon as
they
receive go-ahead from us.

2. LOS Fixtures:
We have received shipment of the clamps, dumbell standoffs, side standoffs
and guide rods from Schober's. More shipments are coming.

---------------------------------------------------------
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
---------------------------------------------------------

Global Diagnostics System
(Rolf Bork, Paul Govereau, Mark Pratt, David Shoemaker, Daniel Sigg)
--------------------------------------------------------------------

Software development for GDS continues this week.  MP continues work
on the excitation system, DS on the scheduler and PG on c++ compiling
under vxWorks.  Recent developments include installation of the GDS
heartbeat on the PNI reflected memory network.

Received a new Baja4700E at LHO. After solving several installation
hassles related to driver version conflicts it is finally up an running.

Had a meeting with CDS and LDAS to discuss LIGO time representation
and distribution. In short: time will be expressed as seconds
starting Sunday, Jan. 6, 1980, 00:00:00UTC (GPS zero). However,
any time format of type month/day etc. will be strictly UTC to avoid
misinterpretation (for instance the IRIG-B signals).
 

Physics Environment Monitor (Alex Marin)
-------------------------------------------
We received almost all the parts of the DAQ and PC for the PEM cart to be
used for the 1st SEI article test. We are working on the assembly of the
hardware and then we will start to write some software for the NI-DAQ
system, which will have up to 8 channels with setable gains, which can
acquire (new) simmultaneously data at minimum 10kHz (depends on the
number of channels used).
 

Optical Contamination (Daqun Li)
---------------------

Continued to take ringdown and mode spacing data from two cavities;

Continued to bakeout the third contamination cavity (inner chamber and
spacier)
and gather components for setting up the third cavity;
 

Non-Optical Contamination (Matt Smith)
--------------------------------------

Matt is traveling to Hanford to start setting up for the SEI vacuum testing.

-----------------------------------------
Control and Data System -- R. Bork
(WBS 1.2.2)
-------------------------------------------

Vacuum Controls
================

- Hanford LVEA systems made ready for PSI tests.
- PID control loop testing of Cryogenic pump regeneration being performed at
Left Mid Station via network.
- Hanford VC processors now connected on ATM network.

Control Area / Networking- Hanford
==================================
- Single mode fibre installation between buildings complete. All ATM
systems up and running in mid and end stations. Ethernet networks have been
installed in all VEAs except Right Mid (waiting bakeout completion).
- Tried multi-mode video over 2km run, could not detect carrier
signal.(Thought
we'd try it, but we will need the single mode/ multi-mode convertors)

- Initial design of internal nework/telephone layout for mid and end
stations in draft form.

Data Acquisition
==================
- Docs distributed for FDR on May 8.
- Working on IPC header files for Reflective Memory layout.
- Testing new ICS110B (24 bit) ADC cards.

Suspensions
=============
- SOS and LOS controllers in final PC artwork stage.
- Design review to be held mid/end May.

IOO
======
- Working documentation for design review in mid May.

ASC
=======
- Testing use of DSP for servo loops, particularly multi-DSP in parallel to
close servos and to provide data to DAQS.
 


WBS 1.4    Project Office



 
Date: Thu, 30 Apr 1998 17:31:36 -0700
From: Linda Turner <turner@ligo.caltech.edu>

1.4.1.2 Project Controls (Lindquist)

CHANGE CONTROL (Lindquist)

The following change requests have been submitted:
 
CR-980007        WBS 1.1.5 Beam Tube Bake, Adjust Budgets to reflect
                 experience
CR-980011 Rev A  WBS 1.1.5 Beam Tube Bake, Electrical Power
CR-980012        WBS 1.1.5 Beam Tube Bake, Leak Detector, Redundant Valves
CR-980015        WBS 1.1.1 Miscellaneous Vacuum Equipment Mods to reflect
                 changes to the PSI payment milestones
CR-980016        WBS 1.1.4 On-site Telephones, Hanford

REPORTS, WORK PLANS, PROPOSALS (Lindquist)

A final draft of the Quarterly Status Report for the period ending February
1998 has been placed on the network as

     ~phil/monthly/February98/m980088-A.pdf

NSF TELECON (Lindquist)

Stan Whitcomb, Irena Petrac, Ed Jasnow, and I held a teleconference with
NSF DGA personnel on April 28, 1998.  Stan presented three new contracts:

Specialty Components - Air Bearings
Allied - Long Lead Items for Stack Leg Elements
REO - Optical Coating

NSF indicated that they were satisfied with the materials as presented with
only a few minor corrections to be provided, and promised a quick response.

The next NSF Teleconference is tentatively scheduled for May 12, 1998.

OFF CAMPUS OVERHEAD RATES (Lindquist)

Federal Accounting has established special "fund" accounts for Hanford
and Livingston Operations charges that will force the application of the
off-campus overhead rate starting October 1, 1997 for the sites.  To do
this we will be switching account numbers as described in the following
message from Barbara Comfort:

The new  5PXXX  accounts, set-up to allow the off-campus overhead rate
of 21.5% to be charged, have all been activated as of today (April 29,
1998).  Please inform your people of the new numbers and have them make
the necessary purchase order and payroll changes.  Listed below are both
the new and the old account numbers:
 
                                         OLD         NEW
HANFORD, WA
 
Observatory                   5P502       5P550
Site Office                        5P521       5P551
Facilities                          5P522       5P552
Vacuum Equipment         5P523       5P553
Optics                              5P524       5P554
Electronics                       5P525       5P555
Data/Computing               5P526       5P556
Administrative                  5P527        5P557
Interferometer                  5P528        5P558

LIVINGSTON, LA

Observatory                    5P503       5P560
Site Office                         5P531       5P561
Facilities                           5P532       5P562
Vacuum Equipment          5P533       5P563
Optics                               5P534       5P564
Electronics                        5P535       5P565
Data/Computing                5P536       5P566
Administrative                    5P537       5P567
Interferometer                    5P538       5P568

We are also reviewing Construction accounts to identify potential off-
campus labor charges (and others) that are candidates to be switched
to a "fund" account with the off-campus overhead rate (for FY 1998).
 

PROPERTY MANAGEMENT (Chargois)

Assisted the Optical Engineer with the shipping of Group 2 Optic Lens
serial numbers ETM03,ETM04,FM03,FM04 and RM02 to the REO c/o Dale Ness 1855
S. 57th Court Boulder,CO.
expected arrival date 4/29/98 conformation received. Acct# 5F514

Assisted the Optical Engineer with the shipping of one (1) Optic Len to
NIST c/o Chris Evans
Route 24 & Clopper Rd. Gaitherburg, MD.  Schedule arrival date 4/30/98.
Acct # 5F514

Assisted the Optical Engineer with the shipment to Lightwave Electronic c/o
Frank Provenza/Tom Kane 1161 San Antonio Rd.  Mountain View CA, schedule
arrival date 4/30/98. Acct# 5F514

Conformation received concerning the transporting of the lower half of the
HAM mockup,  HAM Bellow
serial numbers 003 and 004, One (1) box clean and special baked and one (1)
box containing a Foam rubber Mat.

Submitted the final(claim) documents to American Transfer and Storage to
recover missing items or Monetary compersation for (5) 5 draw File
Cabinet($300.ea), (4) 4 draw File Cabinet ($180.ea),  (23) 2 draw File
Cabinet ($100.ea), 48 Chairs ($220.ea) and Conference Tables ($500. ea)this
estimate equate to $15080.
 

DOCUMENT CONTROL CENTER (Turner)

From: Linda Turner <turner@ligo.caltech.edu>

STATISTICS.   A total of 8 documents have been electronically
submitted to the DCC.  They were reviewed and have been
transferred on-line.  Also, total of 184 documents were added to the
DCC database.  The following figures represent these new additions
by category.

C = 102    D = 44     E = 6     G = 7     L = 13     M = 1    P = 0    T = 11

A total of 39 packages were received and distributed.  An additional 20
packages were sent out.  The DCC processed 58 incoming faxes and
the project transmitted 46 faxes.

Transparencies from the LSC, PAC4, and GWIC 2 were scanned and
passed to Barbara for transfer to the web.

RELOCATION.  The move from 056 to 046 was completed.  Though 046
is a smaller room, the layout provides much easier access.
 

COST SCHEDULE CONTROL SYSTEMS (Akutagawa, Duncan, Rianda, Patlan)

From: Cindy Akutagawa <cindy@acrux.ligo.caltech.edu>

I have been working on the TAS reports and hope to have them distributed by
Monday.  I received the MIT twonk report for March 1998, am waiting for the
MIT invoice.

From: Kristin Duncan <kris@acrux.ligo.caltech.edu>

Incorporated the following Change Requests into the April 1998 Performance
Measurement Baseline (PMB):
CR-980008     WBS 1.1.1       $ 164,241
CR-980009     WBS 1.1.1       $ 472,020
CR-980010     WBS 1.1.2       $  59,574
CR-980013     WBS 1.1.4       $ 272,430
CR-980014     WBS 1.1.4       $ 139,645

Completed and distributed the Responsibility Assignment Matrix (RAM) with
status as of March 1998.

Revised the schedule value of milestones for Hensel Phelps, Levernier, and
Woodrow Wilson contracts for the April 1998 CSSR.  Initiated revising the
schedule milestone values for the PSI contract (work packages 5A522 and
5A532).

Transferred and investigated alternative methods of transferring earned
value status from OPP to Cobra3, achieving partial success.
Worked with GariLynn Billingsley to produce a Core Optics Delivery schedule
for a presentation.

Produced and distributed schedule and cost update worksheets for the April
1998 CSSR for the Detector and Facilities groups.  Began receiving and
inputting the  updates received so far for the month of April.

Continued work on streamlining the schedule report process.  This included
working on developing an electronically transmittable schedule, linking the
different schedule layouts in a more logical configuration, and simplifying
the methods used to produce reports.
 

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena (Irena Petrac)

Butler: Change Order No.7, adding M. Ganther and R. Sass, and
increasing the bill ing rate for F. Mann, was released to Purchasing.

Telos: Change Order No.19, incorporating funds for FY98 support
requirement, was released to Purchasing. Novation Agreement,
transitioning LIGO/T elos Contract to NYMA, effective Change Order
No.19, was released to Purchasing.

March Metalfab/SEI Non-vacuum Hardware: NSF approval was received.
Purchase Order was released to Purchasing.

Specialty Components/SEI Air Bearings: Verbal NSF approval was
received. Purchase Order was released to Purchasing.

Allied/SEI Leg Elements: Verbal NSF approval for Change Order (CO) No.2
was received. CO was released to Purchasing.

Veeco/Fizeau Interferometer: NSF approval was received. Purchase Order
was released to Purchasing.

REO/Production Coating/Detector Optics: Verbal NSF approval for
Change Order (CO) No.6 was received. CO was released to Purchasing.

University of Florida/IO Construction and Installation Support: NSF
approval for  Change Order (CO) No.4 was received. CO was released to
Purchasing.

University of Oregon/NO-cost extension/1 month: Change Order No.3 is
in Project Office for signature.

RFQ for LOS Fixtures etc: RFQ was released. Offers are due in 2 weeks.

From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

A selection was made for the electrical contractor to perform the beam tube
bakeout in Hanford.  The selected contractor was Sun River Electric of
Kennewick, WA.  This will be a time and materials contract for $400,000. It
is expected that the approval package for this contract will be sent to the
NSF early next week, with discussions held during the teleconference
scheduled for May 12.

Discussions continue with Hensel Phelps concerning the issue of additional
costs for cleaning of ducts in the LVEA.  Hensel Phelps has submitted a
proposal for settlement of this issue, which is being reviewed.

Specifications for the new building at Hanford have been received, and an
invitation for bid is being prepared.
 

TECHNICAL CONFIGURATION MANAGEMENT (Althouse)

Nothing special to report this week.
 

1.4.2.1 Quality Assurance (Tyler)

From: "William H. Tyler" <tyler_w@ligo.caltech.edu>

LIGO QA (R. Vincent) witnessed 20 open/close cycle gate valve test at GNB.
Mr. Vincent also witnessed a final leak test of another gate valve. Both
test activities were completed successfully. Early this week, Mr. Vincent
was advised by GNB that they were suspending work on the remaining gate
valves while they investigated an actuator bellows leak problem which
appeared to be due to a design error. John Worden has provided a more
detailed description of this problem and the potential impacts to LIGO to
modify/rework the GNB gate valves in a separate e-mail message.

LIGO QA accompanied M. Fine to visit the air bearing vendor to observe
tests of a prototype under load and to survey this vendor's QA
methods/processes. Although a small two person operation, this vendor's
products are produced with a lot of attention to workmanship "quality" and
delivering a "quality product". I would rate this vendor as "approved" for
LIGO fabrication. Their major weakness is the fact that they are only a two
man shop (limited "redundancy" or "backup" expert workforce). Other vendors
visited on this trip were Pegasus Manufacturing (internal damped coil
springs, KTI (coil spring EB welded end caps) and Brookfield Machine
(support structures).


WBS 1.4.3    Systems Engineering



 
Date: Thu, 30 Apr 1998 19:12:42 -0700
From: lazz@ligo.caltech.edu (Albert Lazzarini)
 

1.4.3  Systems Engineering

1.4.3.1  Systems Engineering & Integration (AL, BB, CC, JK, DC)

__Integration Planning:

Cable Tray Specification

Bill Baldwin has written a draft specification for the cable tray
installation in the LHO Corner Station and put it out for review at
this week's integration meeting.  Once the general approach and the
requirements have been agreed on then the specification will be
extended to the Mid and End stations and a bid package will be put
together.

__Analyses:

Lazzarini is working on a refined Mathematica model to track LIGO
outgassing estimates.

Lazzarini has met several times with facilities folks to
resolve/understand alignment issues at Livingston. Latest
teleconference appears to have put the issues to bed: the site
alignment will be within required bounds (i.e., 90deg. arms; 46.00 m
distances to corner station interfaces); only remaining issue is a 4 mm
discrepancy (transverse) between location of the BT/VE interface forthe
Y arm End station (BT/VE4). We can live with either the SJB location or
the CBI location.

__Reliability:

Feedback was received from S. Whitcomb on the initial draft of the COC
section of the LIGO Maintenance Plan. PEM MP section is still under
review. DAQ MP section was given to R. Bork for review.

J. Worden was contacted with regards to VE maintenance issues. J.
Worden said that a review is taking place in mid-May with the
contractor in which documentation would be provided addressing these
issues. The VE MP section will be outlined with the details filled in
after the mid-May review.

__Integrated Layout/Drawings:

CDI DRAWING RELEASE

    Drawings have been upgraded to A change revision for Initial
    Release.  Drawings will be sent to DCC starting Monday, 5/4/98,
and complete by Friday, 5/8/98.

MIT LEVER LAYOUT

    This project is now on temporary hold due to the possible
    change to the Louvre Baffles in spools numbers BE-5 & BE-6. No
date of completion is projected.

WASHINGTON OPTOMECHANICAL ILDs

    The Mid Station xref's are set up waiting for input from the
    various groups (IOO, ISC,COS). When time permits, will also set
up End Stations.

PSL/IOO XREF LAYOUTS FOR ILDs

    This is not started yet due to current priorities. Will start
    assembling the Optical Enclosure (PSL/IOO table) package near
the first or middle of next month, (May), and hopefully receive input
on the PSL and the IOO layouts.

Worked with MIT on the new PEM Sensor layer for the Washington Corner
Equipment Arrangement Integrated Layout Drawing (D970310). A new
version of D970310 will be filed by Tuesday 5/5.

Continued work on LOS2 Large Optic Suspension production drawings.
Currently working on the structural weldment.

Assisted with modal analysis for the PSL Pre Mode Cleaner.

__Mock-ups:

HAM LOWER HALF MOCK UP

    The Ham half mock up arrived in Hanford, on Wednesday 4/29/98.

ELEVATED PLATFORM MOCK UPS

    Have received a couple of replies & am expecting additional
    product information from a few companies on platforms with
larger work surfaces then the one unit that we purchased. Other
projects have been injected ahead of this project but, will try to make
a decision on purchase plan by Wednesday of next week (5/6/98).

HAM 84" ACCESS & 14" ("E") NOZZLE GUARDS W/COVERS

    Have finished the drawings except for a few dimensions which
    Larry Jones supplied, this week. Will try to finish the
drawings by next Tuesday, 5/5/98.  month.

1.4.3.3 Modeling & Data Analysis (KB/HY/AL)

TEMxx Modal Implementation :

Generic and smart version (a.la.A266) of the mode decompostion matrix
for the rotation and displacement have been implemented. Formulation of
tracing the base of the mode base, characterized by waste size and
focal point, has been done.

Garching workshop :

Hiro atteneded the Garching workshop "LSC Workshop on Software Tools
for AIC". Attendees were from LIGO, GEO, TAMA and ACIGA. Unfortunately,
no one attened from VIRGO (no reply to invitation mails from the GEO
organizer).  Each group explained ( including demonstrations by some )
their software tools, discussed the future directions of tools,
including

* Standarlization

* Validations

* Physics

* Shared efforts

* Development of time domain models

At the workshop, Twiddle and End to End model were demo-ed and received
good attention of people.  GEO group has twiddle-like software,
originally written by Jun Mizuno, and these softwares were compared for
the Dual Recycling configuration transfer function, and agreed well.

A webpage will be prepared which lists all the simulation tools
available.

Alfi :

Robust memory handling is implemented to make Alfi more stable.

Data Analysis and Modeling:

KB met with Bruce Sears to discuss security policies as they apply to
TCL/TK plug-ins (tclets). Bruce has agreed to look into what it means
to modify default security policies and to generate new security
policies associated with tclets as they are planned for LIGO's data
analysis.

KB attended the LSC ASIS sub-group meeting that was held this week to
finish up discussions of the priorities in each of the coordinators'
categories. KB reported on priorities associated with Noise Models to
be used by the group in proto-typing and developing data analysis
algorithms. The highest priority is to get an acceptance/approval for
the estimated noise curves generated using parameters taken from
sub-system review docs and make these curves available for the LSC
community through a webpage. These curves are currently being generated
using the C++ Noise Class Library developed last summer by KB's SURF
project. KB has updated parameters in these models to reflect David
Shoemaker's current thinking of the performance of the suspension. KB
also needs to update some of the models to these classes(seismic
angular excitations and gravity gradient).

KB installed the second alpha release of TCL/TK 8.1 this week to be
able to install a new release of BLT (a collection of high level
widgets for x-y plots, histograms and other useful data display
extensions to TCL/TK. The BLT package works great under this alpha
release of 8.1.

KB downloaded a version of the sockets++ C++ class library this week
and began debugging the code. This was hampered by the poor
configuration of C and C++ compilers on our Sun computer. After making
several modifications of the code, KB was able to compile the source
(but only using gcc from Sirius) and run many of the test programs. For
the most part the socket classes seem to be working on the SUNs.
However, KB also worked to port the code to LINUX this week. The code
was modified and bugs fixed so that the same code builds on both Sirius
and Linux, but the test programs on the Linux box are in general not
working. KB is in the process of debugging this code under Linux. Even
though it is not possible to report success with the sockets++ class
library yet, this is a major step forward from the earlier attempts by
both KB and Walid Majid to work with this package which would not
compile or would core dump on start up.

After waiting a week after receiving the monitor for the new Alpha LDAS
workstation, KB contacted the vendor and then CIT receiving to locate
the CPU unit. It turns out the unit set over in receiving for one week
after Dot told them to contact KB and receiving called the wrong number
and left a message waiting for a reply. The unit should arrive this
week in West Bridge.

Anderson worked on LSC/ASIS related organizational tasks to get the
periodic source search research plan put together.

He also worked on latest ATM problem which looks like it is actually an
AIX bug not an HPSS bug.

1.4.4.2  General Computing (LW/TE)

Motivated by some of the PAC meeting discussions, Sanders and Lazzarini
subsequently discussed the relative merits of moving LIGO PCs from
Microsoft OS to linux. Gary volunteered to be a "guinea pig" to see
whether this option can support the critically necessary LIGO Lab
general computing functions (i.e., email, web-surfing, calendar
browsing and word processing).

MIT:

1. Preparing for the move to the new building. Trying for a June 22nd
time frame for the move.

2. We had a meeting with the networking people at MIT (April 28th)to
try and get a better setup than the basic offering. Dave S. and Tom E.
are heading that up.  They have been dealing with Steve Goldman. From
the meeting we are going back to get more information to justify our
needs for a faster network and hope to present that in the near
future.

Hanford:

Nothing to report

Livingston:

1. The PC's have finally arrived and are being installed by
Techmasters. Julian and Allen S. have a map of the addresses for the
machines.

2. Mark Coles has turned in a list of computer names which will be
mapped to IP addresses in the next couple of weeks.

CIT:

1. Multiple computer moves at Bridge. So far no major problems with the
moves but the multiple little items have taken up time.

2. Finally, we were able to do a full backup on kater. We should be
finished with the full backup of sirius this week.  We have three tape
drives that have gone bad. All three are under warranty and will be
getting sent back with in the week. Two of the drives we will try to
trade-in because of the 2-4 week period before the fixed drives are
returned.

3. Multiple file restorations. I have received a few e-mails from
people saying that they now believe in the importance of backups.

4. We have been working on modifying the DCC setups to allow Linda T.
to have more control over the system.

5. Worked on fixes for netscape and Acrobat. Netscape4 is now on-line
we should have it on the menu in the near future.

6. Multiple accounts added and modified. We are now to a point in-which
most of the CIT users have been moved over to sirius (a few exceptions)
and all we have left are the users not located at CIT. Surresh S. (new
sys. admin.) will be working on those accounts over the next few
months.

7. For the web site: (Barbara K.)

  - turned a PDF version of the travel authorization form into a
  web-based form using Adobe Exchange Forms Author.  The form works
like a charm on PCs.  We are trying to get the UNIX version to work.

  - developed a transparencies page for PAC4.

  - made a variety of changes to the conferences page for Dave
  Shoemaker.

8. Barbara K. worked through George Stokes' programs to map out his
logic in assigning a new document number.  Began working on a web-based
form to reserve a new DCC document number.

9. We have had the fibers tested from the basement of Bridge Annex to
the Second floor of Bridge and found that nearly all had bad
connections. The company that installed the fiber will be out to
replace the connections and perform some more tests in the near future.
We will also have the fiber lines that are currently being used by the
second floor tested after the known bad lines are fixed.
 


WBS 1.4.4.1    Administrative Group


Date: Thu, 30 Apr 1998 14:20:57 -0700
From: Elizabeth Wood <ewood@ligo.caltech.edu>

Elizabeth K. Wood

Arranged for a temp to help Dorothy Lloyd get out from
under her load.

Made arrangements for the on-going upgrade of Rita's
new office.

Met with L. S. Finn to discuss the LRC and updating the
LRC emailing list.

Held the fort while Irene and Gary were not here.
 

Dorothy Lloyd:

Entered AP30 reports into database and contract invoice
summary sheets.  Processed numerous PRs, POs, Change
Orders, Check Request, etc. Processed as many invoices for
payment and followed up on problems with invoice payments.
Provided clerical support were needed.
 

Irene Baldon:

I was on vacation April 24th and 27th and sick leave April
29th,
thus my report covers only 2 working days.

Arranged and processed the paper work for 3 trips and 8
trips that still have paper work to be completed. Worked
on the ever present backlog of Expense Reports.

Performed miscellaneous duties as requested by various
members of
the LIGO Project here at Caltech as well as members of the
staff of each of the two (2) sites.

Prepared and distributed the Weekly Travel/Vacation
Itinerary Report for LIGO Staff and Visitors.

Processed Staff Payroll, incorporating various recent
changes, new hires and the processing of Vacation/Sick
Leave accounting.
 

Rita Torres

Continued organizing office in 357WB. Filed away Technical
Papers and such.

For I. Petrac did change order No. 6 to Research
Electro-Optics; this was sent for NSF approval. Verified
addresses in preparation for RFQ IP-294, Lg. Optic Susp.
Alignment Fixtures, Support Beam, Lift Table & Lift Truck.
Did change order No. 3 to Lightwave, change order No. 7 to
Butler Services Group and Butler Procurement
Justification.

For W. Althouse & E. Jasnow did final edits to Source
Selection Memo.

For W. Tyler and Laser Safety area did edits to procedure
for Valve Seal Replacement.

For P. Lindquist did edits to Budget pages in Advanced R&D
proposal.

Distributed: PC265792 with March Metalfab, change order
No. 1 to Veeco  Corp. Also distributed CDS DAQ FDR
documents.
 


LIGO Hanford Observatory (LHO) Operations



 
Date: Thu, 30 Apr 1998 15:33:36 -0700
From: Fred Raab <raab_f@ligo.caltech.edu>

=========================================================
LIGO Hanford Observatory (LHO) Operations (F. Raab)
=========================================================
 

Lab setup:
----------

Delivery of the optic tables for the Optics Lab have been set back
1 week as TMC did not ship per schedule. They shipped out 4/29. LHO
clean room, and clean part handling, storage procedures are being
worked on by R. Savage, K. Ryan and D Cook for the LVEA, Optic Lab
and Vacuum Prep. Areas. Outlines for the laser "Standard Operating
Procedures" For the LVEA and LVA,s are being developed by R.
Savage and D Cook. Added ideas from any of the participating groups is
always appreciated, especially along the lines of safety interlocks,
enclosures or special needs such as remote operations etc.
Support equipment continues to flow.
 

HAM First Article Test:
-----------------------

David Hall (contractor) began work on Mon. (4/27).

HAM Pier Centering Jig observed to be a bit flexible; a different method
for locating the HAM Drill Template has been employed and the results
have been within tolerances.

The Redhead Anchor Bolts delivered to the site were too short; a Hilti
Insert/Stud anchoring system will be used instead.  Kyle Ryan will help
with drilling of the holes.  The Anchor Bolt Holes on the Drill Template
will be modified to accommodate the Hilti inserts.

Procedure for removing large doors on the HAM is also being worked out
(John Worden).

The dowel pin holes on the HAM Pier were found to be too small;  we will
be getting equipment to ream out the holes to the correct diameter.

Toyota Forklift Battery Charging Station is going to situated in the
First Article Test Area.

HAM Mock-up arrived 4/28.  The Piers for the Mock-up will be anchored.

Rust Remover has been used on 8 of the piers--more will be ordered.
 

Beam-Tube Bake Out:
-------------------
(M. Lubinski, M. Guenther, K. Stiff and W. Althouse)
 

1. Electrical Support Services subcontract:

The Proposal Evaluation Team has submitted their report and recommendation
to Gary Sanders, and it has been signed off.  An Electrical Contractor has
been selected. Bill Althouse and Mark Lubinski will meet with Sun River to
begin negotiations with them prior to contract awarding.

2. Power system components:

All Panelboards have been delivered

2. Heater blankets and heater blanket controllers:

Blanket control panel and cords continued to arrive this week.

3. Cryopumps:

The prototype pumping stand was made and fit checks were done. Some
modifications are required and will be done this week. The first Cryopump
compressor has arrived on site.

4. RGA measurement systems:

Acceptance testing of the RGA measurement systems will take place in
Albuquerque, NM on 5/7 and 5/8. M. Lubinski and R. Weiss will represent
LIGO.

Calibration Cart:

The Calibration Gas Assembly acceptance testing is complete and the unit
was being readied for shipment this week.

5. Data Acquisition and Temperature Control System:

The data system is being assembled in-house at LHO. 17 I/O boxes are
complete and all parts are on hand for assembling the remaining boxes.
Data cable construction should begin next week. Software development was
put aside temporarily to push the assembly task forward, and should
resume this week.
 


For additional information about this report, contact sanders@ligo.caltech.edu