This page has pointers to documents & information pertinent to the development of the
Advanced LIGO Suspensions Project Development.
Adobe's AcroBat Reader version 4.0 is required to read some of the documents. You can
download a copy for virtually any platform.
SUPPORT DATA
Janeen Hazel Romie's LIGO Suspension Web Page
ADVANCED LIGO SUSPENSIONS - Calum Torrie
PLANNING DATA
Suspensions
Project Schedule Version 5 - Complete SUS Program plan. Forecast completed project of
08/17/09. Progress Highlight through 06.13.03.
Suspensions
Project Schedule Preliminary Design - SUS PD plan. Forecast completed project of
1/12/06. Progress Highlight through 06.13.03.
PROGRESS DATA
Suspensions Project Schedule Progress as of 02.28.03 - Forecast completed project of 10/23/07 . Currently showing 14.0% complete. Progress Highlight through 03.14.03.
Suspensions Project Schedule Progress Preliminary Design as of 02.28.03 - Forecast completed project of 05/27/04. Progress Highlight through 03.14.03.
Suspensions Project Schedule Progress as of 03.14.03 - Forecast completed project of 10/23/07 . Currently showing 14.7% complete. Progress Highlight through 03.28.03.
Suspensions Project Schedule Progress Preliminary Design as of 03.14.03 - Forecast completed project of 06/11/04. Progress Highlight through 03.28.03.
Suspensions Project Schedule Progress as of 03.28.03 - Forecast completed project of 11/05/07 . Currently showing 15.0% complete. Progress Highlight through 04.18.03.
Suspensions Project Schedule Progress Preliminary Design as of 03.28.03 - Forecast completed project of 06/25/04. Progress Highlight through 04.18.03.
Suspensions Project Schedule Progress as of 04.18.03 - Forecast completed project of 11/26/07 . Currently showing 15.5% complete. Progress Highlight through 05.02.03.
Suspensions Project Schedule Progress Preliminary Design as of 04.18.03 - Forecast completed project of 07/19/04. Progress Highlight through 05.02.03.
Suspensions Project Schedule Progress as of 05.02.03 - Forecast completed project of 12/12/07 . Currently showing 15.9% complete. Progress Highlight through 05.16.03.
Suspensions Project Schedule Progress Preliminary Design as of 05.02.03 - Forecast completed project of 08/02/04. Progress Highlight through 05.16.03.
Suspensions
Project Schedule Progress as of 05.16.03 - Forecast completed project of 08/17/09 .
Currently showing 16.2%
complete. Progress Highlight
through 06.13.03.
Suspensions
Project Schedule Progress Preliminary Design as of 05.16.03 - Forecast completed project of
01/12/06.
Progress Highlight
through 06.13.03.