![[LIGO logo]](http://www.ligo.caltech.edu/LIGO_web/icons/ligo_logo.gif)
Laser Interferometer Gravitational-Wave Observatory
LIGO Caltech 40 meter prototype Upgrade
WEEKLY REPORTS ARCHIVE
May 27, 2004
- Osamu, Bryan, Seiji and Alan have been working to confirm and
check the observation that the "sidebands on sidebands"
applied by two EOMs in series cause a large contamination of the
arm signals (CARM and DARM) onto the short dof double-demod signals
(PRC, SEC, MICH), severely complicating lock acquisition and control
of the Advanced LIGO optical configuration.
This is documented in a set of
ppt slides from Osamu,
his
SPIE paper,
and a
detailed analysis by Bryan Barr.
- Bryan was able to get reasonably good separation between
the arm and short degrees of freedom by careful choice of demod phases,
at the expense of large offsets and exceedingly tight demod phase
tolerances. Not a practical solution.
- Fortunately, a practical solution is easy to implement:
a Mach-Zehnder interferometer on the PSL table,
with one EOM in one arm and another in the other.
This requires a control system to lock the M-Z via internal modulation
(two beamsplitters, an RFPD and demod board,
servo filter, pzt mirror actuator),
all of which are being acquired now.
A very preliminary draft design by Osamu, Bryan, Seiji and Steve is
here.
It includes an analysis of the frequency and intensity noise
introduced by the M-Z; we think it will be negligible.
We hope to assemble the system in the next week or 2.
- Osamu will re-measure the PSL frequency noise and intensity noise,
before and after implementing the M-Z.
- The PSL, mode cleaner, and FPMI interferometer
all continue to lock well and stably.
All oplevs and QPDs are centered and the spots come back
to where they were before, between locks
(we don't leave the FPMI locked routinely).
- Jay reports that the LSC rack cross-connect wiring changes
for the double-demod boards are done,
all the modules are in hand, and code for the new lsc auxiliary crate 2
will go in next week.
- Rolf is ready to put the new front end LSC software in next week.
Rob is working on a first draft of the InputMatrix40m code.
- Rob is also thinking about machine-learning methods
for finding the ideal demod phases for double-demod length sensing.
- Ben has been working on the LSC/ASC RF distribution drawings.
These drawings are
intertwined with Jay's LSC drawings, and usher in a new wiring for the 1x2
rack. This rewiring will be accomplished by Tuesday, along with the
cabling of the cross-connects to the modules. This will make the hardware
be in place in time for the software's arrival.
- Osamu found a problem with an LSC PD Interface board.
Ben took it back to the
shop for troubleshooting. He fixed it and it now works fine. There was a
bad logic chip that disabled the 1st two PDs.
- Bob has installed heliac cables for all long RF runs.
- Osamu continues to work on the frequency stability servo,
implementing some changes that he has planned for a long time.
- Flavio and Peter King have been working on the ISS
for the 40m PSL, implementing changes to the servo filter
and the current shunt actuator that were developed
on the LASTI PSL;
the block diagram is
here. Preliminary results look very nice.
The changes to the current shunt caused the power of the PSL
to drop from 10.8 W to 10.4 W.
- The readout board for the TRY QPD is not working; Ben will
look at it.
- Ben Olsen and Steve have been diagnosing problems
with the STACIS seismic isolators.
There is one bad controller (of 4),
and at least 3, maybe 4, bad isolators (out of 12).
At least one shows evidence that the PZT stacks are burnt out.
They will continue to diagnose the problems,
before we start sending pieces of the system
back to TMC for repair.
- Steve had two Tropel optical spectrum analyzers
converted from green light to 1064; they are now back
and ready for use.
A third Tropel is in continual use monitoring the
light transmitted through the mode cleaner.
- Fumiko has implemented a simple servo filter for the
oplev P/Y servos, and has taken transfer functions at
different gain settings. She finds that the pitch pendulum Q
can be reduced from > 10 to < 0.9 before oscillation sets in.
The continues to optimize and document the system.
- Shihori continues to work on developing a procedure for
diagonalizing the suspensions' output matrix.
- Monica Varvella of Orsay has spent the last few weeks
here at Caltech learning how to run e2e, build models,
understand the Han2K and SimLIGO models,
and thinking about the modifications required
for AdvLIGO and the 40m.
She will also work on modeling the Mach-Zehnder,
as a simple and useful exercise.
She leaves tomorrow, but will return for the month of July.
- Bob is busy with many bake jobs for Janeen and the
triple pendulum MC crew, and for Larry Jones.
- Bob is baking out and scanning the new squeaky-clean
bake oven, in the hopes of achieving the AdvLIGO cleanliness specs.
May 20, 2004
- Osamu and Bryan have uncovered what we believe to be a fundamental
design problem in the Advanced LIGO length sensing scheme which the
40meter has been working towards testing.
The design calls for two pairs of RF sidebands, f1 and f2 (for AdvLIGO
this might be 9 & 180 MHz; for the 40m, it's 33 & 166).
The CARM and DARM degrees of freedom are sensed at f1 and f2,
respectively, while the short dofs (PRC, MICH, SEC) are sensed at
f2-f1, f2+f1, or both ("double demod"). The idea is that the short dof
sensing is derived only from the sidebands and is undisturbed by the
arm-amplified carrier phase shifts.
We have modeled this scheme using Twiddle and Finesse, and it agrees
with the matrix presented by Peter Fritchel in an LSC meeting back in
2000 or so.
We have implemented these two pairs of sidebands at the 40m using two
EOMs in series. This produces "sidebands on sidebands", ie, local
oscillators at f2-f1 and f2+f1. These were apparently neglected in all the modeling.
They exist, and they can beat with the carrier at f2-f1 and f2+f1.
This is not a negligible effect; to the contrary, it completely swamps
the signals for the short dofs.
Osamu has confirmed this using a modified FINESSE model.
Osamu's results are
here.
- It turns out that Bryan was unable to lock the Glasgow 10m RSE
interferometer for exactly this reason.
Bryan's summary of the Glasgow work is
here.
- We are considering several possible solutions to this problem:
- eliminate the sidebands on sidebands by placing the two EOMs
in parallel, using a Mach-Zender
- eliminate the sidebands on sidebands by employing 2 more EOMs
to kill f2-f1 and f2+f1
- Generate f1 and f2 but not f2-f1 or f2+f1 by sending an appropriately
tailored RF signal into one broad-band EOM
- find a different combination of demod phases and other signal processing
to allow us to extract clean signals for PRC, MICH, SEC
with the existing EOM configuration (it is not clear that this will
be successful, but we will try).
- some more radical solution which might require changes to the
interferometer or the length sensing optics and electronics.
- Dave Tanner & Dave Reitze have experience with complex modulation
of broadband EOMs, and they say that we can indeed reduce the
sidebands on sidebands by, maybe 10 dB. We need more like 20 dB suppression,
as well as a system to monitor and actively kill the sidebands.
- Bryan and Osamu have started looking into the finesse model in a bit more depth to see if we can reduce the effect of the arm cavities by tweaking the demod phasing and other such tricks. It looks as if it might be possible if we're not too fussy about offsets (at least initially) but needs some more in depth examination. If it is possible then the diagonalisation of the central part will not be as good and the problem of lock acquisition will still be just as bad due to large signals in the central part signals around the arm cav carrier resonances - only cancels at the operating point as far as I can see. We need to look at this a bit more but it is unlikely to change the conclusion that we need to use a Mach Zender.
- The best course for now seems to be to use a Mach-Zender interferometer because it has no sidebands of sidebands from beginning. Frequency noise by a doppler shift will be considerable, but it should be of the same order as one produced by the other mirrors.
- To control the MZ, Osamu asked Jay to get a PZT driver like PMC which has a fast response up to ~100kHz. Internal modulation using 33MHz should work well to get signal to control the MZ. We will probably put a pick off BS for parallels EOMs just after PMC, so MZ won't change the path length.
- Osamu is writing a proceeding paper on the 40m program for SPIE. The effect of the sidebands of sidebands is already included. A draft can be found
here.
- Rolf has prepared new LSC software for the 40m dual-recycling configuration. Some more work is required before it can be installed; Rolf will return to this after his 2 week sojourn to LLO.
New MEDM screens and the EPICS sequencer are in progress.
- For lock acq, this code expects to include InputMatrix40m.c; the development of this code is the subject of much active thinking by Rob and everyone else in our group.
- Ben has delivered two 33MHz Wavefront Sensors to the lab, and is getting two boxes for them from the machine shop.
These complete the PD requirements, and join the other recently delivered QPD, double demod PDs, and 66MHz LSC PDs at the lab.
- Don has been installing the cross connects for the rewiring of our LSC rack to accommodate the double-demod signals.
- Ben has traced and characterized the PSL fast channel DAQ readback paths.
To the design, they are being treated properly by the interface card. The next step is to see if the gain that was dictated by the design is appropriate for the signal levels that we have here.
May 13, 2004
- We did not hold a 40m weekly meeting this week; AJW is out of town.
This is an incomplete weekly report.
- Osamu and Bryan have discovered that the length sensing
modeling done with both Finesse and Twiddle share a common bug:
they don't simulate the sidebands placed on the sidebands
by the two EOMs operating at 33 and 166 MHz. These
sidebands will change the error signals dramatically.
Under intense study.
- All core suspended optics are now well aligned, including the two
recycling mirrors.
- Osamu and Steve have used a Tropel optical spectrum analyzer to
look at the light tranmitted through the mode cleaner, and then out
the asym port. The 33MHz and 166MHz sidebands can be seen clearly at
both locations, with expected magnitudes.
- The double-demod (DD) signal at the sym port has about 10mV with
maximum modulation index and 15% transmission of SP EOS. The double
demod signals generated by 133, 199MHz demod boards are going to
whitening filters and they can be seen by dataviewer.
- We expect to see an offset in the DD signal due to
imperfect demod phases (from Seiji's and Osamu's calculations) but it
is not seen at all. Osamu and Bryan tried to change the phase of
133MHz and 199MHz local oscillators (using different cable lengths;
the digital controls are not yet available) to see offset change, but
saw no offset. This may be due to the Finesse bug referred to above.
Under study.
- Jay has completed drawing up the mods to the length sensing and
control (LSC) wiring to accommodate the double-demod LSC
photodiodes. He has compiled a list of wiring changes, and work on
these is commencing.
- Rolf, Jay, Ben and Alan met to discuss the LSC software required
for dual-recycling lock acquisition. New software is in progress and
should be ready for initial testing early next week.
- From Rolf, on his new LSC code: Added another Linux kernel module
to do linked list DMA on the new VME P4 processor boards. This allowed
me to port the present LSC software over. The LSC code under Linux on
the new CPU board runs in 28usec (Pentium 3 code at sites runs in
49usec). This LSC code is now being modified for the 40m lab (12 input
photodiodes, 8 DOF, and dither locking).
- Alex got the new CPUs
to boot Linux over the network (diskless node). Therefore, we no
longer require direct connection of a disk drive.
- While Rolf's initial intention was to change over the 40m lab DAQ
system to be consistent with the sites at the same time (makes LSC
code easier), he is opting to defer that until later.
- Bob has been working on the RF cabling for the LSC
photodiodes. All RF signals at 133, 166, and 199 MHz, and also long 33
MHz runs, will be carried by heliax cables. Bob has installed some of
these and is ordering the heliax for the remainder; in the meantime,
he has installed temporary coax cables.
- Ben is acquiring two WFS photodiodes for the 40m arms.
He brought two boxes to the machine shop they should be back soon.
- Ben continues to chase down problems with the PSL fast channel
DAQ readback. A connector on the back of the Generic DAQ Interface card
was out of position, and has been fixed. This accounts for some signals
not lining up with their software names. Now the next step is to do a
survey of the incoming signals, to see if they are being treated properly
by the interface card.
- Bob cleaned and baked a load of small parts for Janeen.
- Bob bonded and baked (first bake) 10 Hybrid OSEMs, and cleaned
and started their hot bake.
- Bob started wrapping the new oven with heating tape and he will
switch the SRS RGA from oven B to the new oven.
May 7, 2004
- Bryan Barr has arrived from Glasgow,
and Monica Varvella from the Orsay VIRGO group.
They will focus on dual recycling lock acquisition strategies
at the 40m and, via e2e simulation, AdvLIGO.
Please welcome them!
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
- Osamu locked the power recycling cavity (PRC)
along with MICH, for the first time.
He used SP 33I for PRC and AP 166Q for MICH.
This is a good check that the length control path to the
power recycling mirror is working correctly.
- Osamu is working on establishing signals with the
double-demod (DD) photodiode, at 133 and 199 MHz.
The signals are very small. He believes that
the DD PD amp should be modified by notching out
the 33 MHz, which otherwise swamps the DD signals.
Jay will look into this.
- Osamu is measuring the 166 MHz at the AP using an optical
spectrum analyzer.
- Seiji, in Japan, is developing methods to set the
double-demod phases correctly for the PRC, MICH, and SRC signals.
- Rob continues to study and understand the lsc front end code,
and is talking with Rolf about how he can help develop it.
- PSL (Miyakawa, Vass, Ward):
- Osamu found a 10 kHz oscillation on the
frequency stability servo (FSS) error signal,
and traced it to a back-reflection of 30-40% of the light
from the AOM.
He adjusted the 1/4 wave plate near the AOM,
and eliminated the back-reflection and the 10kHz oscillation.
- Osamu then found a 100 kHz oscillation
on the FSS error signal, and traced it to a bad op-amp
which was put on the FSS card to cancel the PMC pole
(after we moved the FSS pickoff to be after the PMC).
He and Ben replaced the opamp, and the 100 kHz is gone.
- Osamu then found a 58 kHz oscillation
on the FSS error signal, traced to a resonance of the PZT
on the new NPRO. The FSS card has a notch at 71 kHz;
with the new NPRO, this needs to be moved by changing a capacitor.
Osamu and Ben will do that soon.
- There remains a 500 kHz oscillation
on the FSS error signal, whose origin is unknown;
it may come from the RFPD amplifier.
But, it's small and has a small effect on the performance
of the FSS.
- Osamu thinks that the FSS PZT loop filter has one more
pole at 10kHz than it should. He will confirm with Rich Abbott,
then remove the extra pole.
- After all this FSS work, the PSL is very stable and performing
as well as ever. The mode cleaner is locking robustly,
and staying in lock for many hours at a time.
- Osamu will remeasure the FSS OLTF and use the MC to re-measure
the PSL noise, and compare with what we had 6 months ago.
- We intend to adjust the PSL slow loop temperature change
in the EPICS state code.
- Optical sensing (Kawazoe, Sakata, Ward):
- Fumiko has installed digital filters on all the
oplev servos, and is taking noise spectra with the servos off and on.
She sees some significant in-loop noise reduction in the 0.5-1.0 Hz range,
but sees little or no change in the OSEM P/Y noise spectra.
She's also taking swept-sine transfer functions with
one or 2 optics. She's finding several problems, and is not sure
whether the problems are with FOTON or something else.
Under investigation.
- Steve is ordering replacement mirrors for two
tropel optical spectrum analyzers
that were left over from the old green-light 40m days.
- Steve & Bob set up a video camera to view
the area around the MC2 chamber.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran):
- The group is reviewing Jay's
drawings for mods to the LSC rack
to accomodate the new double-demod signals.
- Steve has ordered RF splitters for
distributing the RF local oscillators to our
long list of LSC demod boards.
- Steve, Bob, and Rob set up remote controls
for the picomotors that dial in beam blocks
in front of the four test masses.
All 4 beam blocks are visible on the video cameras
viewing the test masses.
- Ben, Jay and Rolf looked at our inability to read out the fast
PSL channels correctly into DAQS. They traced it to an ICS110b ADC
that was not in synch. They rebooted that crate and it appears
to work ok now. Ben will go through the channels
to see what gains they need on the DAQ interface board
to keep them in range.
- Rolf says that he will have time in the next couple of weeks
to get our new LSC code working.
He will run it in a new Pentium IV vme Cpu.
Since he doesn't have a VxWorks BSP for this board,
he will try to run it on realtime linux.
- Rolf also plans to upgrade our DAQS system
like he did at the sites, including a new frame builder
and better handling of channels at different read rates.
- Undergrad Ben Olson is taking transfer functions
of all 12 STACIS systems and is finding that most of them
are working well. He's trying to isolate and diagnose the problems.
-
EPICS code to shutter
the PSL during vacuum transitions will be implemented soon.
- Mohana and Shihori continue to work on setting
alarm limits on all EPICS channels in the EPICS alarm handler.
-
Facility (Vass) and South Annex Bake Ovens (Taylor):
- Bob is vacuum-prepping OSEM clamps and LASTI MC parts for Janeen.
- Bob is installing thermocouples on his new
super-clean bake oven. He's working with Larry Jones on
getting the noise down on RGA scans, etc.
April 30, 2004
- The 40m lab welcomes two visitors on Monday:
Bryan Barr from Ken Strain's group in Glasgow,
and Monica Varvella from the Orsay VIRGO group.
They will focus on dual recycling lock acquisition strategies
at the 40m and, via e2e simulation, AdvLIGO.
Please welcome them!
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
- Work on the PSL, and on the LSC electronics,
has trumped any experimental progress in
dual-recycling lock acquisition this week.
- Seiji has written a technical note documenting his
proposed dual-recycling lock acquisition sequence, which features
dither-locking of MICH as a first step.
This document is now under review by the 40m group.
- Rob has been studying the lsc front end code all week,
and is starting to feel comfortable with modifying and maintaining it.
- PSL (Miyakawa, Vass, Ward):
- Osamu has been struggling with the frequency stability
servo (FSS) all week. Our new NPRO (SN 238) is much noisier
than the old one (SN 332), forcing the FSS to work hard.
- He re-aligned the entire FSS optical path,
but still the FSS was not staying in lock robustly.
- He found some design flaws in the FSS board, starting from
rev D (our board says "rev C" on it, but it looks like it's rev E or F).
He has fixed these on our board, and is working with Rich Abbott
to generate a new rev (drawing to DCC) for this board.
- He found saturation in the PC loop for the FSS,
and changed some gains to fix it.
- He sees ~ 10 kHz oscillation and saturation in the PZT loop
for the FSS. He changed the dynamic range by a factor 3,
which greatly reduced, but did not eliminate this problem.
- He noted that the FSS EPICS gain sliders don't do what
they're supposed to do. It seems to be an EPICS database problem;
Ben and Osamu will diagnose and fix it.
- After all these changes, the FSS is now performing much better,
and the FRC and MC lock stably for hours.
It's still not perfect: the 10 kHz oscillation still
appears sometimes.
- But just now (Thursday afternoon) Osamu found the source
of the oscillation: the AOM QWP was out of adjustment,
and much of the light that was supposed to go to the
FRC was returning to the laser, introducing noise
and optical feedback. He has fixed this, the 10 kHz oscillation
is gone, and the FSS appears to be as stable as ever.
- Osamu will remeasure the FSS OLTF and use the MC to re-measure
the PSL noise, and compare with what we had 6 months ago.
- We would like to get the old NPRO (SN 332) refurbished
and made available as a hot spare in the 40m lab.
- Jay reports that Flavio and Peter King will want to
look for a 2.5 MHz peak in the ISS current shunt actuator
response function, that has been seen in the LASTI PSL.
- We intend to adjust the PSL slow loop temperature change
in the EPICS state code.
- Optical sensing (Kawazoe, Sakata, Ward):
- Fumiko continues to study and understand
the oplev servo filters employed at the sites,
and how to modify them for the 40m. She will talk to oplev servo experts.
- Bob and Steve are installing the remaining ccd video cameras
on beamlines, and cables to the video switch.
They checked all cameras using the laser beam and/or flashlights.
Mods to the video switch programming and the EPICS screens
will be done by Lisa.
- Steve will attempt to adjust the camera views so that the
beam flags (in front of the 4 test masses) can be seen.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran):
- Ben got the three RFPDs for double-demod from Todd;
they are tested and ready for installation. The 66 MHz RFPD for SPOB
will be ready by the end of the week.
- The large fluctuations in the MOPA output power,
reported by the EOT photodiode in the MOPA box,
are now believed to be due to improper grounding
of the photodiode signal to the ADC (VMIC 3123).
Ben fixed this, and will do the same for the NPRO power monitor.
- Ben is working on a switchbox to control all the
picomotor beam flags from the control room.
- Jay reports that
drawings and database changes for signal recycling have been started
and should be complete by Monday.
These are mods required for our existing
length sensing (LSC) rack, to accomodate more RFPD signals.
It looks like it will be a substantial piece of work,
and an additional aux crate is required.
We will pursue this work with the highest priority,
followed by a serious search for 60 Hz pickup.
- Bob installed heliac cable for the LSC RFPDs in the POB and AP
beamlines.
- Ben has been in email contact with Vern regarding the RFPD redesign.
Things seem to be coming along, and when Vern's design is
reviewed, Ben can continue on the production.
- Ben will check that perennial problems
associated with rebooting (XYCOM boards not set right,
EOS state not right, polarities for mechanical shutter toggles
set right) are now being automatically done right.
- Steve and Ben Olson are diagnosing the STACIS problems
prior to a visit to the 40m lab by TMC reps on Monday.
-
EPICS code to shutter
the PSL during vacuum transitions will be implemented soon.
- Mohana and Shihori continue to work on setting
alarm limits on all EPICS channels in the EPICS alarm handler.
-
Facility (Vass) and South Annex Bake Ovens (Taylor):
- Bob is in the middle of the first of a long list of
bake jobs for Janeen, for the AdvLIGO MC triple pendulum suspension.
- Bob is assembling and vacuum-prepping LIGO I osems for Janeen
and for the 40m.
April 23, 2004
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
- Work towards implementing a full LSC system for locking
the dual-recycling interferometer is progressing rapidly; see below.
- The mode cleaner servo is performing less robustly.
Osamu thinks that the demod phase has somehow changed
(maybe when RF cabling was done in that rack
a couple of weeks ago), and will re-tune the demod phase
with different-length cables.
- Rob continues to study the deep complexities of the
front-end LSC code, with the aim of modifying it for
dual recycling.
- Seiji is writing a technical note summarizing
his studies of dual-recycling lock acquisition,
in which he concludes that dither-locking MICH
can provide a robust path towards lock of the full IFO.
- PSL (Miyakawa, Vass, Ward):
- Our MOPA continued to misbehave in new and strange ways.
Ever since Steve & Osamu turned down the current on the NPRO
(to reduce the overheating), the MOPA power monitor
has been fluctuating *upward* from 11 watts up to 13 or 14 watts.
When that happens, the mode cleaner falls out of lock.
- Steve and Rob obtained an NPRO heat sink from the shop
(ordered by Peter King weeks ago) and installed it on the NPRO
in our MOPA laser. They also removed the cover from the NPRO.
The TEC temperature monitor fell to 1 volt,
the MOPA power stopped fluctuating, and the mode cleaner
held lock for hours. Late last night,
there was some more MOPA power fluctuation,
but it hasn't happened since.
- In the next few days, we will close the MOPA cover
(it is now propped open a few inches)
and declare victory on the heating problem.
- However, there are still problems with the FSS.
There appears to be a big oscillation (3MHz) in the FSS fast PZT loop
which is limiting the gain and causing the mode cleaner to fall out of lock.
Osamu burned the card out while testing it,
by plugging it into a bad extened board.
Ben fixed the FSS board this morning, brought over
a new extender board, and checked that the FSS board works ok.
But it still has the big oscillation.
Osamu thinks it is an electronics problem that can be fixed.
But he's also checking and tuning up the optical path
to the reference cavity.
- Osamu and Rob found that the EPICS sliders for the FSS common gain
and fast gain do not work as they should.
They will enlist Ben to help find and fix the problem.
- We intend to adjust the PSL slow loop temperature change
in the EPICS state code.
- Optical sensing (Kawazoe, Sakata, Ward):
- Fumiko continues to work on implementing an oplev servo filter
based on what she found at the sites (modified with FOTON
to be more appropriate for our 5" optics).
- Shihori is documenting her commissioning of the
electro-optic shutters.
- Steve will attempt to adjust the camera views so that the
beam flags (in front of the 4 test masses) can be seen.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran):
- Ben has been accumulating the remaining hardware
needed for length sensing for dual recycling, including:
two more double-demod RFPDs, another 33 MHz RFPD,
a third LSCPD interface board,
a fourth whitening board, and a fourth anti-aliasing board.
- Jay is working on mods to the LSC rack drawings
to get the wiring for these additional boards.
- Ben continues to work on the redesign of
the RFPD amplifier for fast RF and low power.
- The RFM network went down on Wednesday at around 6am
for unknown reasons. Rob spent much of the day trying to get it back up
(by rebooting the vme cpus) with no success.
Jay determined that the problem was that the c1epics
linux cpu which connects EPICS with the front-end servos
was not performing its task. He restarted the task
and everything else could be brought up by the end of the day.
Thanks, Jay; this is going into the procedures manual!
- Ben will check that perennial problems
associated with rebooting (XYCOM boards not set right,
EOS state not right, polarities for mechanical shutter toggles
set right) are now being automatically done right.
- Steve has had no luck locating our STACIS servo extender board,
and TMC wants $1K for a new one.
We'll see if we can borrow one, and/or attempt to optimize
the servo gains without it.
- Steve located some old picomotor controls
which work with our picomotor-driven in-vacuum beam flags,
and he and Bob have run cables so that all beam flags
can be controlled from the control room.
Ben modified a switch so that it worked with this system.
- A controller for a uniblitz shutter that was non-functional
out of the box will be fixed by the manufacturer at no charge.
- Bob ordered heliac cables and connectors
for the long fast RF runs, and they are on their way.
-
EPICS code to shutter
the PSL during vacuum transitions will be implemented soon.
- We plan to do a careful search for 60 Hz pickup
in our LSC crate, which is anomalously large.
- Mohana and Shihori continue to work on setting
alarm limits on all EPICS channels in the EPICS alarm handler.
-
Facility (Vass) and South Annex Bake Ovens (Taylor):
- Bob plans to deliver 8 LIGO-I OSEMs to Janeen
(and spares for the 40m) by the middle of next week.
- Bob is finished plumbing up new "clean" oven C,
and is pumping on the RGA line.
- Bob has decommission "dirty" oven D and surplused it.
It is now removed from his lab.
- Bob is exploring building a new very large bake oven for AdvLIGO.
April 16, 2004
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
- Osamu is preparing to lock the PRC with
double-demodulation (DD) at the SP.
A DD RFPD is in place, the DD will be done with
a pair of IQ Demod boards, and the LO RF signals
are in place (at 166+33 and 166-33 MHz).
We need to do some wiring of the LSC rack
to get the signals into the LSC system,
and are now looking into the needed software changes, if any.
- Jay, Osamu, and Rob are going over the requirements
for LSC hardware and software for the full dual-recycling
lock acquisition, and Rolf knows that we're thinking about it.
- Rolf and Alex are thinking about implementing a general-purpose
"math block" in the digital controls software,
which we could use for dither-locking the PRC.
- Locking of the Fabry-Perot-Michelson (FPMI)
is currently hampered by a (new) problem with the PSL
(see below). It can be done, but there is apparently
a problem making the transition between locking of
XARM/YARM and CARM/DARM that is not understood and is
under investigation.
- PSL (Miyakawa, Vass, Ward):
- The PSL is starting to misbehave again, in a new way.
The frequency reference cavity (FRC) error signal is oscillating
in a funny way, suggesting saturation.
Osamu suspects the FSS fast (PZT) loop.
Under investigation.
- Steve & Osamu decreased the PSL NPRO #238 power output
from 712mW to 504mW by adjusting the
doide current potentiometer from 2A to 1.7A.
DTEC fell from 1.7 v to 1.25 v (that was the point;
the PSL trips off when DTEC exceeds 2 v),
and the MOPA power fell from 12.1 W to 11.0 W.
The PSL has been performing stably since then.
We think we're out of the woods with regard to heating,
but we still await an NPRO heat sink from the shop.
That will hopefully arrive and be installed next week,
at which time we will fully close the MOPA cover
and hope that the heat (DTEC voltage) doesn't rise
unacceptably.
- We intend to adjust the PSL slow loop temperature change
in the EPICS state code.
- Optical sensing (Kawazoe, Sakata, Ward):
- Fumiko has tried to implement an oplev servo filter
based on what she found at the sites (modified with FOTON
to be more appropriate for our 5" optics). She was unable
to see a reduction in P/Y noise (as measured by the OSEMs).
She will pursue this work systematically.
- Rob has finished laying out the POB beamline,
and is hooking up the electro-optics: a ccd camera,
an RFPD, and a QPD.
- We now have 12 QPDs installed and being read out:
IPPOS, IPANG, IOPOS, IOANG, MCR, MCT, TRX, TRY, POX, POY, AP, SP.
We need one more, POB, and an additional readout channel.
Ben has delivered the QPD itself; we have to either
instrument a new readout channel or borrow POY's.
- Shihori has aligned all the QPDs except for POB,
and TRX and TRY. She will do those next.
- We now have 3 electro-optic shutters (EOS):
at MCR, SP, AP. The MCR one has been working for many months.
Shihori and Osamu got the SP one working, and Shihori measured
the transmittance vs HV; a nice cosine curve.
She will document it.
There are problems with the one at the AP, which may be due to
bugs in the controller. Under investigation.
- We now have 4 mechanical shutters under EPICS control
(PSL, MCR, AP, SP) and 4 under manual control
(MCT, POB, POX, POY). One shutter is not functioning
and has been returned for repair/replacement.
-
EPICS code to shutter
the PSL during vacuum transitions will be implemented soon.
- Osamu, Steve, Rob and Shihori have cleaned up
all the optical tables, removing all excess optical components
for storage, and ensuring that all beamlines are fully
instrumented and laid out as in the drawings.
- The PSL table is now grounded to the
vacuum enclosure, as are all other optical tables.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran):
- We now have Marconi signal generators for all
required frequencies (29.5 MHz for MCR, and 33, 166, 133, and 199
for the main interferometer, all phase-locked to multiples of 33 MHz).
- Ben brought over
LSC RF distribution boxes for the
133, and 199; not needed for 166, only one IQ demod board needs it.
There are heliac cables for the 33 and 166 to the LSC rack,
and Bob ran some temporary RG405 for the 133 and 199;
more heliac cable is on order.
- At Osamu's request, Ben removed (and jumpered across)
the output attentuators at the end of the
RF AM stabilizers that go to the EOMs.
Osamu measured the maximum modulation depth
for 166 MHz to be 0.3; more than enough,
and easily turned down to 0.1 with the EPICS slider.
The 33 MHz is probably much deeper, but will also be
turned down to 0.1.
- The 166 MHz and 133,199 MHz RFPDs show oscillation at 500 kHz.
This is a known problem for RFPDs with low light level,
with a known fix, and Ben will implement it.
- Ben cured the long-standing problem of the varying
monitoring readout of a couple of Thorlabs photodiodes
on the PSL (PMC transmitted DCPD and FSS transmitted DCPD),
by tying the "Guard" pin to the signal "Lo" pin
(discovered after reading the 96 page manual
for the 3123 ADC).
He will now investigate the PSL DAQ channels,
some of which have been railed forever.
- Ben continues to work on the redesign of the RFPD board,
with Vern Sandberg.
They are working to incorporate a few new features that would be nice to
have. Ben plan to give Dennis a schedule of development by the end of
this week.
- Ben is updating the system wiring schematics for the 40m Auxiliary
rack, in order to reflect the as-built condition.
- We plan to do a careful search for 60 Hz pickup
in our LSC crate, which is anomalously large.
- Mohana and Shihori continue to work on setting
alarm limits on all EPICS channels in the EPICS alarm handler.
- Ben Olson continues to diagnose problems with
the STACIS seismic isolators. Two of the 3 isolators
in the south end are working well, the NE isolator
is behaving badly. Under investigation.
Steve will locate the STACIS servo extender board
or order a new one.
- Dual-recycling lock acquisition (Kawamura, Miyakawa):
Seiji and Osamu have settled on two lock acquisition
sequences (using double demod) that they think
will work robustly.
Seiji's involves dither-locking MICH
then locking the PRC and then SRC with double demodulation
at the SP and PO, respectively.
Osamu's replaces the first step with an alternative
scheme for MICH.
We will work towards implementing these schemes.
This is a perfect thing
to test with e2e... new visitors are arriving in May
who may want to work on this.
-
Facility (Vass) and South Annex Bake Ovens (Taylor):
- Steve is cleaning up the 40m lab,
moving excess optics and equipment to cabinets
in the east arm,
and getting rid of surplus equipment such as old
40m racks full of obsolete electronics.
- Bob tied down the monitors in the control room
for earthquake safety.
- Bob is plumbing up new "clean" oven C.
- Bob will decommission "dirty" oven D,
will surplus it, and will recommission old oven C as a new
"dirty" oven D.
- Bob is exploring building a new very large bake oven for AdvLIGO.
- Bob is building OSEM diodes
for Janeen (AdvLIGO MC triple) and for the 40m.
April 9, 2004
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
- Osamu and Rob locked the Michelson (l-) using the
166 MHz RFPD at the AP. They are now working on locking the PRC (l+)
using double demodulation at the SP.
- Rob and Osamu are studying Matt Evans' thesis and
InputMatrix code, in order to generalize it for dual recycling.
- Fumiko and Osamu have analyzed the MC transmitted beam
using the Tropel optical spectrum analyzer. They measure
a transmitted modulation depth of 0.13 for the 33 MHz sidebands
and 0.06 for the 166 MHz sidebands, with all EPICS sliders
set to maximum. they will work on increasing the modulation depth
for the 166 MHz.
- PSL (Miyakawa, Vass, Ward):
- Osamu re-aligned the beam from the (new) NPRO to the power amplifier.
The power out of the MOPA is now up to 12.1 watts, and intensity
fluctuations are now much reduced.
He also re-aligned the beam into the frequency reference cavity
and the PMC. The PSL is now performing very well!
- We are still operating with our MOPA cover off
to keep the NPRO from heating up.
- Steve has ordered a heat sink on the new NPRO
and will install it as soon as it arrives.
- We intend to adjust the PSL slow loop temperature change
in the EPICS state code.
- Optical sensing (Kawazoe, Sakata):
- After tuning up the PSL, Osamu
re-optimized the mode cleaner wavefront sensor
beamline and digital alignment control system; it is now
working well.
- Shihori and Osamu have installed and aligned electro-optic
shutters on the AP, SP, and MCR beamlines. The trigger photodiodes
were wired from the auxilliary rack; this proved to be dangerous,
and a couple of photodiodes have been fried. We are now running
power to these trigger photodiodes using matched power supplies;
SP and MCR beamlines have these, and a third will be installed
soon on the AP beamline.
- Shihori and Osamu have checked out 12 of 13 beamline QPDs,
from photodetector through the entire electronics chain to EPICS displays.
All are working well. One more QPD is required for the POB beamline.
Ben is acquiring it (and a spare).
- Rob is almost finished laying out and aligning the POB beamline.
He awaits a QPD and a CCD camera.
- Osamu and Rob have installed and tested
mechanical shutters on the SP, AP, MCR, POX, POY, MCT,
and PSL input beamlines.
EPICS control of the SP, AP, MCR shutters have been tested;
EPICS control of
the PSL shutter will be tested soon. EPICS code to shutter
the PSL during vacuum transitions will be implemented soon.
Mechanical shutters for the other beamlines are controlled manually
(as opposed to EPICS).
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran):
- Jay has generated a block diagram and requirements
for the LSC as it relates to signal recycling.
There will be 11 LSC RFPDs feeding I&Q demod boards;
a 22x8 input matrix; and an 8x8 output matrix
(including a path from CM -> MC).
- Ben continues to check out some varying
monitoring readout of a couple (at least) of PSL channels
(PMC transmitted DCPD and FSS transmitted DCPD)
and now believes that the signals are
being pulled down by a weak short to some other signal(s).
He has a spare 3123 which he will test during the next
PSL down time.
- Ben helped Rob repair a particularly stubborn oscillation on one of
the RFPDs. Adding the 1.5K resistor didn't do any
good, so he tried the Inductor-Resistor fix, and it worked very well.
- Ben received two signal generators (IFR 2024's)
that he ordered
for the LSC double demodulation, and has
brought them to the 40m. Bob Taylor has made shelves to mount them
between 1Y2-24, and 1Y2-28. This should make minimal impact on the
existing rack drawings.
- Todd has delivered the four I&Q Demod boards that are needed
for double demodulation, and Ben brought those over today.
We now have 13 I&Q Demod boards, and much work is required
to wire them up for use. Ben will take the lead.
- Bob has installed heliac cable for some long cable runs
from RFPDs to I&Q demod boards, and
will order and install heliac cable for all remaining long RF runs.
- Ben is planning a redesign of the LSC RFPDs for higher frequency
operation.
- We plan to do a careful search for 60 Hz pickup
in our LSC crate, which is anomalously large.
- Mohana and Shihori continue to work on setting
alarm limits on all EPICS channels in the EPICS alarm handler.
- Digital suspension controllers (Sakata, B. Abbott, Heefner):
- The EPICS readback of the coils for ETMX were
reading anomalously large values, although the optic was
being damped just fine.
Ben compared the database for ETMX with the one for
ETMY, and found that the ETMX database was wrong
(not known how or why) and that a recent reboot
(not known when) caused the problem to surface and
come to Osamu's attention.
Ben fixed the database, rebooted, and all appears to be well.
- Safety (all):
A
40m lab safety document T040092 has been completed
and submitted to DCC.
-
South Annex Bake Ovens (Taylor):
- Bob continues work on new oven C.
- Bob is building 40 or 50 OSEM diode boards
for Janeen and for the 40m.
April 2, 2004
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
With the PSL problems under control (sort-of),
Osamu and Rob
re-established the Fabry-Perot Michelson interferometer
(with misaligned PRM and SRM) and are re-measuring the noise spectrum.
They are commissioning the new POB beamline.
Rob is increasing the gain on the SP RFPD .
Shihori is aligning and commissioning all 12 QPDs on
the output beamlines.
We are making plans to complete our LSC and Lock Acquisition
system in preparation for locking the dual recycled IFO.
- PSL:
- We are currently running with
our replacement PSL NPRO (SN 238),
installed 3/11/04,
and our old MOPA power supply.
The MOPA cover is propped open about an inch
to allow it to cool.
As far as we can tell, no cooling water is running to the NPRO
through the needle valve; it appears to be stuck.
In this configuration, the laser is running stably, and
the NPRO DTEC voltage is ~ 1.6 volts.
If the MOPA cover is not propped open,
the DTEC voltage rises to 2 volts, and the NPRO trips off.
- Steve looked at a history of the DTEC voltage for the
last 800 days. About 150 days ago, it rose from 0.6 volts
and hovered just below 2 volts while our old NPRO (SN 332)
appeared to be dying. It crept closer to 2 v when we replaced it
with NPRO SN 238, and the NPRO started tripping off.
This indicates a long-standing cooling problem;
we are guessing that we were flowing water cooling
to the NPRO till the needle valve jammed 150 days ago,
and have only now noticed it.
- We don't have a heat sink on the new NPRO;
we have ordered and will install one.
Apparently, the sites all have heat sinks on their NPRO,
and either have holes punched in their MOPA cover,
or have the MOPA cover propped open.
We have also ordered and will install a replacement
water valve for the NPRO.
We are in communication with Lightwave, but the rep there
doesn't think that our problem is due to cooling...!
- Intensity fluctuations out of the MOPA
are 10 times larger with the new NPRO.
We need to optimize the alignment from NPRO
to power amplifier, to maximize power and minimize intensity
fluctuations.
And, we need to finish commissioning of the ISS!
- The HV on the frequency reference cavity ion pump
has had no failures ever since the 24 v power cable
to the ion pump HV was replaced.
- We intend to adjust the PSL slow loop temperature change
in the EPICS state code.
- Optical sensing (Kawazoe, Sakata):
- Shihori is working with Bob to wire up last EOS,
in the AP1 beamline.
- Rob noticed that the trigger PD for the EOS
in the SP beamline was burned out; we have ordered a replacement.
- Fumiko recentered the ITMY oplev.
She is writing up her studies of oplev noise.
She will move on to commission the oplev servos, next.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran):
- Jay has begun generating a block diagram and requirements
for the LSC as it relates to signal recycling.
There will be 11 LSC RFPDs feeding I&Q demod boards;
a 22x8 input matrix; and an 8x8 output matrix
(including a path from CM -> MC).
- Jay and Ben are ordering parts for more high frequency RFPDs
and I&Q demod boards and more IFR RF generators.
- Ben will start work on the design of
high frequency (low power) RFPD boards, for double demodulation.
- Bob is running heliac cables to all the high frequency
RFPDs on the optical tables.
- Ben is getting two more QPDs; one for installation
on the new PO beamline, and a spare.
- We plan to do a careful search for 60 Hz pickup
in our LSC crate, which is anomalously large.
- Mohana and Shihori continue to work on setting
alarm limits on all EPICS channels in the EPICS alarm handler.
- Jay and/or Mohana will implement EPICS code to automatically
close the mechanical shutters in the event of a vacuum transition.
- Ben continues to check out some varying
monitoring readout of a couple (at least) of PSL channels
(PMC transmitted DCPD and FSS transmitted DCPD)
and believes it is due to a bad 3123 ADC.
- Undergrad Ben Olson is measuring the transfer functions
for the STACIS isolators. He has measured the three at ETMY;
two work well, providing 22 dB of attenuation at 10 Hz;
one is oscillating. He will learn how to adjust the gains
on the loops. The STACIS controllers that are supposed to
communicate with our EPICS system have many problems...
- Digital suspension controllers (Sakata, B. Abbott, Heefner):
- Shihori has completed her writeup of the
DSC input matrix diagonalization procedure and results
and is submitting it to the DCC.
- She is now preparing to diagonalize the
input matrix of the last two suspensions (PRM and SRM)
and is preparing the procedure for diagonalizing the
output matrices.
- Dual-recycling lock acquisition (Kawamura, Miyakawa):
- Seiji and Osamu continue to use Finesse to explore
how the signals for the short DOFs (PRC, SRC, MICH)
change during lock acquisition, in order to develop
an efficient lock acquisition procedure.
They are making good progress, and are optimistic.
Seiji thinks that dither-locking MICH (l-) will work well,
allowing us to aquire lock in the other two short
degrees of freedom (PRC l+ and SRC ls) more robustly.
Osamu is gearing up to test this.
- Safety (all):
A follow-up safety audit was held last Monday March 29.
All action items were addressed and closed.
A
40m lab safety document is nearing completion.
Many thanks to the safety audit team for their careful
inspection and advice!
-
South Annex Bake Ovens (Taylor):
- Bob is wiring up the temperature controller
for new oven C.
- Bob did some bake jobs for Larry Jones' galling tests.
- Bob is building 40 or 50 OSEM diode boards
for Janeen and for the 40m.
Mar 26, 2004
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
There's been a break in commissioning work while
repairing the PSL (see below). Now that the PSL is back up
and all systems are working, we will
re-establish the Fabry-Perot Michelson interferometer
(with misaligned PRM and SRM) and remeasure the noise.
- PSL:
- Our replacement PSL NPRO (SN 238),
installed 3/11/04 to replace
our old NPRO (SN 332) which was dying after many thousands
of hours of service,
started to misbehave 4 days after installation.
The power drops to zero for around 10 minutes,
then comes back up, and repeats every hour or 2.
- The problem was initially associated with a 580 kHz oscillation
seen on the FSS card.
Rich Abbott said that this oscillation was also seen on an LLO laser.
Jay and Osamu killed the oscillation with a capacitor on the FSS
card, but the power problem persisted.
- The problem did not appear when the stand-alone NPRO
power supply was used, only when our MOPA power supply was used.
Jay and Peter King swapped MOPA power supplies, but the
power problem persisted.
- We frantically searched for another spare NPRO;
neither Peter nor LHO have any to spare.
- The problem is also associated with raised temperature reported
by the NPRO thermoelectric controller (TEC).
Yesterday (Wednesday), Steve turned on the water cooling
for the NPRO. As of today, the power problem has not reappeared,
and the FSS, PMC, and MC remained locked throughout the night.
We have switched back to the old MOPA power supply,
are keeping the cooling on, and are declaring success.
- The HV on the frequency reference cavity ion pump
occasionally falls to 0. Steve and Bob replaced the 24 v power cable
to the ion pump HV, and the problem has not reappeared.
- These problems uncovered another problem: the PSL slow loop
(which changes the temperature of the reference cavity
when the FSS PZT signal drifts) changes the temperature by too much.
Osamu will adjust this in the EPICS state code.
- Optical sensing (Kawazoe, Sakata):
- Shihori and Fumiko are preparing to install the last EOS,
in the AP1 beamline.
- Ben is getting two more QPDs; one for installation
on the new PO beamline, and a spare.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran):
- Jay has delivered an RFPD tuned for duoble demodulation
(peaks at 133 and 199 MHz, notch at 166 MHz).
- Jay delivered two 2-omega IQdemod boards (for SPOB),
and IQdemod boards for 133 and 199 MHz. Osamu will install
and debug these in the LSC system.
- Mohana and Shihori are establishing the
alarm limits on all EPICS channels in the EPICS alarm handler.
- Jay and/or Mohana will implement EPICS code to automatically
close the mechanical shutters in the event of a vacuum transition.
- Ben is checking out some varying
monitoring readout of a couple (at least) of PSL channels
(PMC transmitted DCPD and FSS transmitted DCPD)
and believes it is due to a bad 3123 ADC. He will look for
a replacement.
- Digital suspension controllers (Sakata, B. Abbott, Heefner):
- Shihori has completed her writeup of the
DSC input matrix diagonalization procedure and results;
it will be released soon.
- Safety (all):
Following through on the remaining
action items from the safety inspection of 1/13/04:
- All crane operators (Steve, Bob, Osamu, Rob)
were trained and certified on Tuesday.
- All 40 Meter personnel attended the lab safety briefing
(led by Steve) on Thursday. AJW updated an evolving
document
summarizing all the material covered in the safety briefing.
- A follow-up safety audit will be held next Monday March 29.
-
South Annex Bake Ovens (Taylor):
- Bob has recieved a new temperature controller, and 20" oven body,
for the new oven C. He's working on wiring up the temperature controller.
Mar 19, 2004
- The 40m Technical Advisory Committee met
on Thursday during the LSC meeting in LLO.
Osamu presented the status of the project, as well as
Seiji's and Osamu's results on
strategies for locking the dual-recycled Michelson.
Powerpoint slides are
here
(8 MB).
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
There's been a break in commissioning work while
repairing the PSL (see below) and while Osamu is
at LLO for the LSC meeting.
- PSL:
- Late last week, Rob and Osamu installed a replacement
NPRO (SN 238) in our MOPA laser; our NPRO
was showing signs of dying.
They aligned it, and tuned up the MOPA by maximizing
the output power. They got up to 12.5 watts output.
- Osamu was then able to lock the frequency stability servo,
after readjusting the servo gains.
He moved on to the mode cleaner, but ran out of time
in optimizing the servo before he had to leave for the LSC meeting.
- Four days after installing the new NPRO, it has been
showing signs of misbehavior: the power drops to zero for
around 10 minutes, then comes back up, and repeats every hour or 2.
Osamu will diagnose the problem when he returns from the LSC.
- The HV on the frequency reference cavity ion pump
occasionally falls to 0. This is not being monitored
by EPICS; Steve noticed it when looking at the controller.
Fortunately, the FRC holds vacuum pretty well even when the
pump isn't working. Steve and Rob think the problem is with
the 24v cable to the HV supply, and Bob will make a replacement.
- Optical sensing (Kawazoe, Sakata):
- Shihori and Fumiko are preparing to install the last EOS,
in the SP beamline.
- Shihori is preparing to install the remaining QPD,
on the new PO beamline, and to cable up and test the MCT QPD.
- Fumiko is writing up her oplev calibration and noise studies.
She is starting to implement and test the oplev servos,
and is studying the appropriate filtering.
- Jay and/or Mohana will implement EPICS code to automatically
close the mechanical shutters in the event of a vacuum transition.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran):
- Mohana and Shihori are establishing the
alarm limits on all
EPICS channels in the EPICS alarm handler.
- The monitoring readout of a couple (at least) of PSL channels
(PMC transmitted DCPD and FSS transmitted DCPD)
has been misbehaving badly for many months.
This does not effect the servos.
The cause is somewhere in the electronics rack,
and Ben continues to investigate it.
- Digital suspension controllers (Sakata, B. Abbott, Heefner):
- Shihori has measured the damping Q's for the side OSEMS on
all of our suspended optics. The poor damping of
ITMX side osem servo is clearly observed.
Shee will now study the dependence of the Q on the gain,
for all OSEM damping servos.
- Dual-recycling lock acquisition (Kawamura, Miyakawa):
- Seiji and Osamu continue to use Finesse to explore
how the signals for the short DOFs (PRC, SRC, MICH)
change during lock acquisition, in order to develop
an efficient lock acquisition procedure.
They think they have a path for locking the PRC (l+)
degree of freedom; the other two (SRC or ls, and MICH or l-)
are proving to be more problematical.
Osamu presented these results at the
Advanced Optical Configurations group meeting
at the LSC meeting in LLO.
- Safety (all):
Following through on the remaining
action items from the safety inspection of 1/13/04:
- The custodian went through the basic LIGO laser training.
The Safety Office has requested that they not switch
custodians on us so often.
- All 13 emergency lights in the lab have been tested.
Two were not functioning right (the two that were supposedly
fixed last month); they have now been fixed properly, and tested.
- All the fire alarms (including the one newly installed
in the South Annex clean room) and extinguishers
will be tested on Friday.
- All rack kill switches have been modified to provide
a continuous ground path.
- All optical tables are being grounded to the vacuum envelope.
Not sure whether we should also ground the racks to the vacuum envelope.
- Bob is setting up lockout / tagout systems for
all the relevant vacuum equipment. The racks and power breakers are done.
- All crane operators (Steve, Bob, Osamu, Rob)
will be trained and certified next Tuesday.
Signs listing all certified crane operators,
with safety reminders, are now posted on all three crane controllers.
- All 40 Meter personnel will undergo the lab safety briefing
(led by Steve) next Thursday. AJW wrote up an evolving
document
summarizing all the material covered in the safety briefing.
- A follow-up safety inspection has been scheduled for March 29.
-
South Annex Bake Ovens (Taylor):
- Bob continues to work on rebuilding oven E and building new oven C.
Parts are coming in on schedule.
He's now working on the temperature controllers and RGA filaments
for the new ovens.
Mar 12, 2004
- The 40m Technical Advisory Committee will meet
next Tuesday during the LSC meeting in LLO.
Osamu will present the status of the project.
We hope that there will be time in the AIC working group
agenda to present Seiji's and Osamu's results on
strategies for locking the dual-recycled Michelson.
- Commissioning (Miyakawa, Vass, Ward, Kawamura):
- Late last week,
Rob increased the gain on the POX RFPD
to compensate for the relatively much larger
60 Hz noise that appeared when we installed
and mis-aligned the power recycling mirror.
The x-arm is locking robustly, with much-reduced
relative 60 Hz noise.
- Increasing the gain on the POY RFPD
induced an oscillation; Ben has fixed this
with the addition of a resistor.
- Seiji, Osamu and Rob tried an experiment
in which they modified the damping of the
ITMX, ITMY, BS optics (comprising the
Michelson) to give them lots of DC gain
and a UGF at 4 Hz,
in effect "tying" them to the optical tables
on the seismic stacks.
The hope was that, if there isn't much relative motion
between the tables, such a scheme could make it easier
to obtain lock in the short dual-recycled Michelson.
They compared the Michelson error signal
and transmitted light power before and after
changing the suspended optic damping,
and so no significant change.
They conclude that there is too much
relative motion between the tables to make this
a useful approach.
-
On Saturday, the PSL frequency stabilization servo (FSS)
lost lock, and we haven't been able to regain
robust lock since. After carefully studying the data
and performing a variety of
checks of the MOPA using the PMC,
Osamu, Steve and Rob found no evidence of
problems with the FSS, PMC, reference cavity, slow or fast frequency
actuation, chiller, cooling water, coolant piping, or the power
amplifier. Reviewing the data, it appears that the inability to lock
the FSS since last Saturday is due to the failure of the TEC or some
other element of the NPRO. The TEC temperature is now back to normal,
but the NPRO is not; it appears to have suffered permanent damage.
It appears that the 40m NPRO is in its death
throes, after 18,000 hours of faithful service.
We have now obtained a spare 126 NPRO (SN 238)
from Peter King's lab (many thanks, Peter!), and
Osamu and Rob installed it
into the Lightwave box. They're busy aligning and tuning the output beam.
We will return our NPRO (SN 332) to Lightwave for repair.
- As part of the diagnosis of the PSL problem,
Rob, steve and Osamu shut down all electronics and computers in the lab
and brought everything back up successfully.
Rob is documenting the detailed procedure for doing this.
- Optical sensing (Kawazoe, Sakata):
- Shihori and Fumiko have installed an
electro-optic shutter (EOS) on the SP beamline,
and checked out its operation under EPICS control.
They had some problem with the trigger photodiode,
and a spare one will be installed soon.
They are preparing to install the last EOS,
in the SP beamline.
- Shihori has checked out the installed beamline QPDs,
and will install the last two (of 12) soon.
- Fumiko is taking noise spectra of the five oplevs
that are currently in service (the ones for the SRM and PRM
aren't working because the optics are misaligned).
She will start implementing and testing the oplev servos.
- Bob has cabled up all the beamline mechanical shutters
One is installed on the PSL output beam;
three others will soon be installed in the
MCR, SP, and AP beamlines.
Ben and Jay have made them work under EPICS control,
although there are some questions about the wiring logic
for fail-safe shuttering under loss of power or EPICS cpu reboots.
- Jay and/or Mohana will implement EPICS code to automatically
close the mechanical shutters in the event of a vacuum transition.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran)
- Rob modified the POY RF photodiode to increase the gain,
but it was oscillating.
After Ben installed a shunt resistor to ground as advocated
a while ago by Mike Zucker, the oscillations have stopped.
- Ben fixed a flaky LEMO cable reading out the PRM side OSEM.
- Bob installed some heliac cable for the
33 MHz RF signal from the PSL rack to the LSC rack.
The 166 MHz signal is already carried by heliac cable.
- The kill switches for all the electronics racks have all been modified
so that the ground conductor remains connected when power is
disconnected.
- The monitoring readout of a couple (at least) of PSL channels
(PMC transmitted DCPD and FSS transmitted DCPD)
has been misbehaving badly for many months.
This does not effect the servos.
The cause is somewhere in the electronics rack,
and Ben continues to investigate it.
- Mohana and Shihori are reviewing the long list
of EPICS channels in the EPICS alarm handler,
to establish good alarm limits on all channels.
- Digital suspension controllers (Sakata, B. Abbott, Heefner)
- The DSC system has functioned with no problems this week!
- Shihori has diagonalized the input matrix for the
ETMX suspension, and has re-measured all the cross-couplings
for all the other suspensions now that the vent is over
(except for the PRM and SRM, which are still misaligned).
She has observed some significant
changes in the cross-couplings in ITMX. We suspect that the side OSEM
in ITMX is not working well. Under investigation.
- Safety (all):
We are documenting a response to
all of the action items from the safety inspection of 1/13/04,
which have all been addressed.
-
South Annex Bake Ovens (Taylor):
- Bob is ordering temperature controllers and RGA filaments
for the new oven he's building,
Mar 5, 2004
- Commissioning (Miyakawa, Vass, Ward):
- We closed up after a successful 4 week vent to install
the two suspended recycling mirrors, PRM and SRM.
We pumped down last Thursday with no problems,
and now are at 9e-6 torr with the maglev turbopump alone.
- By Thursday evening, the mode cleaner was locked,
and by Friday AM the FPMI was locked.
Minimal re-alignment was necessary; the mirrors did not move
much because of the pump down.
- All error signals are now much weaker,
because only 7% of the light gets through the
mis-aligned PRM; and the asymmetric port has an
8% transmitting mis-aligned SRM.
As a result, the 60 Hz noise is now relatively much larger,
and is a real problem for locking.
- Osamu hunted for the 60 Hz noise source.
It's in the analog LSC crate, and it only goes away
when all cables are unplugged and modules pulled out.
- The band-aid solution is to increase the gains on
the RFPDs sensing the FPMI degrees of freedom
at the POX, POY, and SP ports.
- Rob increased the gain on the POX RFPD, but couldn't do the POY;
Ben is looking at it. Meanwhile, with this mod,
the x-arm is locking robustly, with much-reduced
relative 60 Hz noise.
- Osamu is now modifying the whitening filter gains
and re-tuning the LSC servo filters, to optimize the
control with these lower light levels.
- We will then want to recalibrate the FPMI
and get a new calibrated noise curve.
- This past Tuesday, the HV cable(s) to the
PZT steering mirror(s) at the end of the PSL table were bumped,
and the mirror(s) moved (not sure which one, or both).
Before understanding what happened, Osamu re-aligned
the MC to the input PSL beam;
as a result, the beam to the main IFO was different.
Fortunately, we have QPDs monitoring the beam position / angle
at the PSL and at the MC -> IFO hand-off.
Osamu has now used these to re-establish the correct beam pointing
at the PSL, and has brought the MC and and main IFO alignment
back to where it was.
- Optical sensing (Kawazoe, Sakata):
- All 7 oplevs are working well after pumpdown.
- Shihori is checking out the installed beamline QPDs,
and will install the last few (of 12).
Then she'll calibrate them all.
- Fumiko did some more measurements to
determine how well the oplevs sense the
suspended optic pitch and yaw, above the noise.
We remain unsure about how useful the oplev
servos would be for us,
whether we should bother to commission them,
and over what frequency range they should act.
- Because of the large amount of light reflected from the
PRM to the SP when it is aligned, we need to finally
install and commission the electro-optic shutter (EOS)
at the SP and AP ports. Fumiko and Shihori
are working on this, and Bob is helping with the wiring.
- Bob is checking all the wiring for the
remote control of the mechanical shutters for the
PSL, SP, AP, MCR beamlines.
We still need to complete the EPICS control software
for these.
- All camera views are established
for all 7 core optics and all 8 output beams,
and all signals are going into the video switch.
We still need a few more camera power supplies
to make use of all cameras. Steve has them on order.
- All chamber illuminators are working
and under EPICS control.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran)
- The monitoring readout of a couple (at least) of PSL channels
(PMC transmitted DCPD and FSS transmitted DCPD)
has been misbehaving badly for many months.
This does not effect the servos.
The cause is somewhere in the electronics rack,
and Rob and Ben are searching for the problem.
- Jay reports that
the PD needed for double demodulation has been tuned up and is ready
for installation.The response has a notch at 166MHZ and peaks at 133
and 199MHz. The is ~30dB of suppression of the 166MHz. Better
suppression will require a re-layout/redesign of the board.
- Mohana and Shihori are reviewing the long list
of EPICS channels in the EPICS alarm handler,
to establish good alarm limits on all channels.
- Steve and Bob spent some time cleaning up the PSL
cable plant.
- We continue to think about the necessary
mods to the LSC software to implement lock acquisition code.
- Digital suspension controllers (Sakata, B. Abbott, Heefner)
- On Wednesday, the DSC sensor ADCs (ICS 110b's)
started to channel hop, and all the
vertex suspension watchdogs tripped off.
We rebooted the DSCs, and several suspensions came back,
but not all. The DSC filtering computer
c1suslinuxpc2, which services MC1, MC2, MC3 and SRM,
wouldn't re-start; when manually restarted,
it segfaulted (as if it was getting corrupted data
from the sensors). Jay found a bad cable from the PRM side
OSEM sensor; Ben fixed it; Alex restarted the DSC system.
By the end of the day, all the DSC system
is back up with all suspensions damping nicely.
- Shihori is diagonalizing the input matrices for the
ETMX, PRM and SRM suspensions.
- Safety (all):
We still need to document a satisfactory response to
all of the action items from the safety inspection of 1/13/04.
All the action items have been addressed, we just need
to assemble documentation.
Steve gave a safety lecture to new undergrad student Ben Olson
who is looking at the STACIS system.
-
South Annex Bake Ovens (Taylor):
- Bob continues to work with Larry and Dennis
on rebuilding ovens C and F,
aimed at achieving AdvLIGO cleanliness specs.
He has placed orders for all parts for oven C.
- Bob is building hybrid OSEMs or Janeen,
as well as spare OSEMs for the 40m suspensions.
Feb 27, 2004
- Installation (Miyakawa, Vass, Ward):
- We are closing up after a 4 week vent to install
the two suspended recycling mirrors, PRM and SRM.
- The installation went very smoothly and successfully.
The installation crew (Steve, Osamu, Rob)
installed both new suspended optics,
got them damping well in the middle of the OSEM ranges,
balanced the chamber optical table,
established good alignment of all optics,
centered the beams on the in-vac PZT steering mirrors
with the PZTs in the middle of their mechanical and electrical range,
established all output beams (AP, SP, PO, POX, POY, initial pointing),
observed aligned spots and michelson fringes at the AP and SP beams,
established all oplev beamlines,
installed glass dishes to isolate the OSEM cables
from the chamber walls and checked for any contact,
established good camera views of all optics,
checked everything, and took lots of pictures.
A complete list of tasks is
here.
Terrific job, installation crew!
-
On Wednesday, all access connectors and doors were replaced,
and pumping on the annuli commenced.
On Thursday, pumpdown commenced and has been proceeding smoothly.
As of Thursday 5pm, the maglev turbopump is pumping
on the main volume at about 3e-5 torr.
We should be ready to recommission the interferometer on Monday.
- Optical sensing (Kawazoe, Sakata):
-
All 7 oplevs are working well. The two new ones (for SRM and PRM)
were set up by Rob. They require several in-vac mirrors each,
and the resulting beams on the QPDs are dim, but adequate
for sensing.
- Fumiko has completed her calibration of the first 5 oplev
qpds, and is measuring the pitch and yaw motion spectra
in units of radians/rtHz, and rms motion in radians.
- Fumiko is determining what changes are required
to Mike ACad optical layout drawings in light of the
recent installation work.
- Shihori will be working with Fumiko to commission
the electro-optic shutters for the AP and SP beamlines.
- Shihori will commission and calibrate all 12
beamline QPD monitors.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran)
- Jay reports that
the 2 Omega I&Q demod board for SPOB is fabricated and in test.
- Jay has a working "double resonant" photodetector circuit
for testing, but it is clear that a new design is required
to make it work well.
- Mohana has completed implementing a long list
of EPICS channels into the EPICS alarm handler.
She and Shihori will establish good alarm limits on all channels.
- We continue to think about the necessary
mods to the LSC software to implement lock acquisition code.
- Digital suspension controllers (Sakata, B. Abbott, Heefner)
- Several more problems with corrupted entries in the
SUS AUX databases were found, and Jay fixed them.
It's hard to check everything; problems will be fixed
as they reveal themselves.
We're not sure how or why these databases got corrupted,
but care will be taken to ensure it doesn't happen again.
- Ben fixed a flaky cable on carrying the BS LL OSEM SENSOR
into the ISC patch panel.
- Shihori is working on a final draft document describing her
diagonalization of the suspension controller input (OSEM) matrix.
She will diagonalize the input matrices for the
ETMX, PRM and SRM suspensions next week.
She is also developing her plan for diagonalization of the
output (coil) matrix.
- Dual-recycling lock acquisition (Kawamura):
- Seiji was in Aspen last week and gave a talk on
dual recycling at the 40m.
After highlighting the progress at the 40m,
he described the challenge of finding a clean path
to lock acquisition of the dual-recycled Michelson
with the current readout scheme.
He got lots of interesting suggestions,
and quickly tried many of them with Finesse;
none worked well. The path to lock acquisition
will be a challenging one!
We hope that expert members of the e2e team will contribute.
- Safety (all):
We hope to complete a satisfactory response to
all of the action items from the safety inspection of 1/13/04,
next week. Meanwhile, all crane work at the 40m in the last
two weeks (there was a lot of it)
was performed by operators wearing steel-toed safety shoes.
-
South Annex Bake Ovens (Taylor):
- Bob continues to work on rebuilding ovens C and F,
aimed at achieving AdvLIGO cleanliness specs.
- Bob expects all ovens to be back up and running by the end of March.
Feb 20, 2004
- Installation (Miyakawa, Vass, Ward):
- We are vented for the installation of
the two suspended recycling mirrors, PRM and SRM.
- Steve used the de-ionizing N2 gun to attempt to clean the dust
off of the PRM, but it didn't do much.
Then he tried the CO2 snow gun; it got some of the dust off,
not all. Steve talked with Stan, Helena and Betsy; apparently,
the sites have the same problem, and they live with it. So will we;
we will NOT attempt to drag-wipe the optics to get the remaining dust off.
- The installation crew installed the signal recycling mirror
last week, and the power recycling mirror this week.
They are both positioned within 1 mm (or so) of specifications.
- The OSEM pigtail bracket had to be moved in order
for the pigtails to reach it. Steve moved it without any problems.
- In-vac mirrors for the oplevs have been placed on the
BS optical table, and the table was leveled using counterweights.
- Both newly installed suspended optics
are now damping well, with all OSEMs nicely centered
both electronically and mechanically.
- The two in-vac PZT steering mirrors were adjusted so that
they are in the center of their dynamic range, both mechanically
and electronically.
The settings are being auto-burted.
- Alignment of all five vertex suspended optics is in progress,
and the SP, AP, and PO beams are being established.
Currently, the main beam is flashing through the mode cleaner,
through the faraday isolator and MMT, through the PRM,
beam-splitter, to ITMX, and back through to the asymmetric port.
Work is in progress to re-establish the symmetric port beam.
- We had been using the PRM oplev to monitor the BS table,
and last week we observed a significant drift of this signal.
Rob traced this to a bad oplev laser mount, and this has been
fixed. The PRM and SRM oplev systems are now being
aligned onto the newly-installed optics.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran)
- Jay reports that
the 2 Omega I&Q demod board for SPOB is fabricated and in test.
It should be available by Monday.
- Jay reports that
work on the "double resonant" photodetector continues.
- We continue to think about the necessary
mods to the LSC software to implement lock acquisition code.
- Jay suggests that we run the high frequency (33, 166, 199) MHz
LSC RFPD signals to the I&Q demod boards using heliac cable.
Bob will get the cable and connectors.
- Alex Ivanov has developed an x-y display of digital signals
using a modified dataviewer. Osamu and Seiji find the display
of error-signal versus transmitted power to be a powerful
diagnostic tool.
- Mohana continues to work on the EPICS alarm handler
to make it useful.
- Caltech undergrad Ben Olsen is beginning to look at
the STACIS system, to resolve problems with it.
- Digital suspension controllers (Sakata, B. Abbott, Heefner)
- There was an earthquake last Saturday, 4.3 in central CA.
All suspensions got shaken.
Watchdogs tripped off for ETMX and ETMY, but for none of the others.
This has been seen before.
Jay looked at it, but couldn't figure out why the watchdogs
for the vertex optics weren't working. Finally, he rebooted the
AUX cpu that runs the vertex watchdogs, and then verified
that they are now working correctly. This remains a mystery.
- After rebooting the AUX cpu,
some of the optics were not damping well, and some OSEMs
were not being read out.
Jay discovered and cleared up a few problems with database records
caused by inadvertant replacement of files in the target area.
We will be implementing procedures to minimize the risk of this
happening in the future.
- Shihori has completed a second draft document describing her
diagonalization of the
suspension controller input (OSEM) matrix.
She is also developing her plan for diagonalization of the
output (coil) matrix.
- Dual-recycling lock acquisition (Kawamura):
- Seiji is in Aspen this week and will give a talk
on dual recycling at the 40m.
- Safety (all):
Almost all of the action items from the safety inspection of 1/13/04
have been followed up on, and a response report is being prepared.
Now that the two suspended optics are no longer on the
South Annex flow bench, work on installing a fire alarm
in the South Annex will be scheduled.
-
South Annex Bake Ovens (Taylor):
- Bob is cleaning and baking a reworked SOS suspension
for our BS, which has a notch cut out of it
to allow the POB beam to exit without clipping.
- Bob rebuilt oven F, and is now doing an RGA scan to assess
its cleanliness.
- Bob is doing bake jobs for Larry Jones in support of HEPI and AdvLIGO.
- Bob continues to work with Larry Jones and Dennis Coyne
on the design of new 12" bake ovens for the lab,
aimed at achieving AdvLIGO cleanliness specs.
Feb 13, 2004
- Installation (Miyakawa, Vass, Ward):
- We are vented for the installation of
the two suspended recycling mirrors.
- The installation crew replaced a Brewster prism mirror
on the SP beamline with a 2" mirror, and re-established the SP beam
through to the photodetector.
- Steve set up a ccd camera on the SP for installation / monitoring.
- The installation crew placed two in-vac mirrors
to steer a pickoff beam (from BS to ITMY) onto the optical table
near ITMY, and established this PO beam on that optical table.
- The installation crew carefully measured the distances
between the ITMs and the BS.
Osamu and Rob carefully calculated the optical path length
for the power and signal recycling cavities and the Schnupp asymmetry
to an accuracy of 1 mm (Seiji established the tolerance on this
to be within a few mm of the design values for the two recycling
cavities, and several cm for the asymmetry).
- Steve used the di-inonizing N2 gun on the SRM.
Then, the installation crew moved the SRM suspension and installed it
in the chamber, positioning it precisely within 1 mm.
- They connected the cables, and it damped well, immediately.
Well, the side damping was a bit noisy until the OSEM was adjusted
and the table balanced; then all 5 OSEMs damped the optic nicely.
- The table was balanced using counterweights,
and the OSEMs were adjusted to read around 1 V each (the middle
of their range). Visual inspection of the magnets in the OSEMs
remains to be done.
- Osamu and Rob noticed discrepancies between their two calculations,
and when it was resolved, it was realized that the SRM was placed
2 mm off from design. The suspension was moved by that amount.
- After a bit more table balancing, PSL flashes were seen
in the initial point beams, in reflections from ITMX back to the
symmetric and asymmetric ports, and at ETMX.
After some touch-ups, the reflections from ITMX and the SRM
were made to overlap with each other, and the incoming beam,
at the symmetric port. Additional alignment of suspended optics
and output beams are in progress.
- Plan to install the suspended power recycling mirror on Friday.
- Electronics (B. Abbott, Heefner, Taylor, Mageswaran)
- Jay reports that
The 2 omega I&Q demod board needed for SPOB
should be stuffed and tested by 2/13/04.
- Jay reports that
work on a "double resonant" photodetector is proceeding.
Right now we can get a PD that has peaks at roughly 133 and 199MHz
with a notch at 166MHz.
A PD should be ready for installation and test by 2/20.
- The signal from the PSL frequency reference cavity transmitted
light photodiode is fluctuating wildly.
The problem appears to be downstream of the photodiode,
eg, in the cable to the 3113 ADC, the ADC, or beyond.
Under investigation.
- The PRM oplev signals are fluctuating; under investigation.
We have requested a spare oplev QPD from the controls group,
and we have spare oplev lasers.
This oplev is currently monitoring the levelness of the BS chamber
optical table, NOT the PRM, which has not yet been installed.
- Ben notes that the Minco temperature controller
on the PSL frequency reference cavity is oscillating.
He and Bob will look at the filtering in that controller.
- Mohana installed a first draft of the EPICS alarm handler.
Much work is needed to make it useful.
- Caltech undergrad Ben Olsen is beginning to look at
the STACIS system, to resolve problems with it.
- Digital suspension controllers (Sakata, B. Abbott, Heefner)
- The DSC watchdogs to not do their thing.
When the rms motion exceeds the set limit,
they should disable the coils; they do not.
Under investigation.
- Shihori has completed a first draft document describing her
diagonalization of the
suspension controller input (OSEM) matrix.
She is also planning her diagonalization of the
output (coil) matrix.
- Dual-recycling lock acquisition (Kawamura):
- Seiji continues to use Finesse to explore
how the signals for the short DOFs (PRC, SRC, MICH)
change during lock acquisition, in order to develop
an efficient lock acquisition procedure.
He spoke at some length with Hartmut Grote of GEO
about how they lock their dual-recycled IFO.
He is trying some of the techniques they use,
but it is not clear that they will be helpful to us.
- Seiji will be in Aspen next week and will give a talk
on dual recycling at the 40m.
-
South Annex Bake Ovens (Taylor):
- Bob is cleaning and baking a reworked SOS suspension
for our BS, which has a notch cut out of it
to allow the POB beam to exit without clipping.
- Bob is doing bake jobs for Larry Jones in support of HEPI and AdvLIGO.
- Bob continues to work with Larry Jones and Dennis Coyne
on the design of new 12" bake ovens for the lab,
aimed at achieving AdvLIGO cleanliness specs.
Feb 6, 2004
- Commissioning (Miyakawa, Kawamura, Sakata):
- We are vented for the installation of
the two suspended recycling mirrors.
- We are carefully monitoring all oplev and OSEM signals as we
work. Everything appears to be pretty stable.
- The PSL beam (low power) is flashing through the
mode cleaner, to the ITMs and back to the SP and AP ports.
This beam is being used to align all optics.
- Steve, Osamu and Robert
replaced an in-vac prism mirror with a regular 2" mirror,
and will use the prism mirror to correct for the
astigmatism in the SP beam in air, where it can be more easily aligned.
- Then they installed two mirrors to bring the
beam from BS -> ITMY out to a nearby optical table.
- The distances between vertex suspended optics
are being measured with a ruler. We aim to install
the power- and signal-recycling mirror suspensions
with a tolerance of a couple of mm with respect to the ITMs.
- Next is to install the PRM and SRM suspended optics
and oplev beamlines, and align everything.
- We decided to not center the beam better
on ITMX. It is a bout 1cm from the center of the optic.
Since it's not really a problem, and would be a big chore
to correct, we decided not to bother.
- After we pump down, we will re-establish the
Fabry-Perot Michelson (FPMI), with misaligned power- and
signal-recycling mirrors.
Our original plan was to first commission a LIGO-1-like
power-recycled FPMI. But we decided that we would not
learn anything valuable from that exercise, and that it would
be more efficient to go straight to a
dual-recycled Michelson (without Fabry-Perot arms, at first).
Opinions on this are welcome.
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- The 2 Omega I&Q demod boards needed for
the SPOB signal should be ready within the week.
- Mohana is working on the EPICS alarms and vacuum interlock.
- AJW, Jay and Alex have been looking at the
LSC front end code (Rolf) and lock acquisition code (Matt),
and are discussing the mods needed for the
dual-recycling experiment.
- A considerable amount of additional electronics
(LSC RFPD's, double-demod boards, and associated wiring)
still need to be specified, designed, and built.
- The STACIS system still is down, awaiting some attention.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Shihori is documenting her
diagonalization of the
suspension controller input (OSEM) matrix.
She is also planning her diagonalization of the
output (coil) matrix.
- Simulations:
- Seiji has released a note on
Signal Extraction Matrix of the 40m Detuned RSE Prototype,
T040010-00-R.pdf.
This note explores different variations on
the 5x5 signal extraction matrix for Detuned RSE:
comparison of differential demodulation and double demodulation,
dependence of each DOF on demod phases,
allocation of ports for optimal signals,
comparison of different PO ports, and cavity length tolerances.
- Seiji continues to use Finesse to explore
how the signals for the short DOFs (PRC, SRC, MICH)
change during lock acquisition, in order to develop
an efficient lock acquisition procedure.
- Safety (all):
Following up on the action items from the safety inspection of 1/13/04:
- Bob ordered steel-toed safety boot covers for
crane operation, but they're too small, so they will
be returned for larger sizes.
- Steve installed drip trays under the vacuum roughing pumps.
-
South Annex Bake Ovens (Taylor):
- Bob continues to work with Larry Jones and Dennis Coyne
on the design of a new 12" bake oven for the lab,
aimed at achieving AdvLIGO cleanliness specs.
Jan 30, 2004
- Commissioning (Miyakawa, Kawamura, Sakata):
- We vented on Wednesday, for the installation of
the two suspended recycling mirrors,
with no problems or incidents.
- As noted below, we had many problems with the
suspension controllers on Monday.
By Wed morning, things had been stable for more than
24 hours. All oplev, OSEM, PZT, etc signals
and servo settings were recorded before the vent.
- During the vent, the drifts in the oplev and osem readings
were carefully monitored. There was considerable motion
in the oplev signals, much less on the OSEMS: consistent
with the motion being due to the table motion (in yaw, mainly)
as the seismic stacks respond to the vent.
There is clearly a daily drift in the oplev readings,
correlated with temperature, but it isn't very big (~ 0.2 volts,
while deviations of ~ 1 volt are tolerable for maintaining
alignment).
After the vent, the P/Y biases on the OSEMS were changed
to recover the pre-vent oplev readings.
- Osamu completed the mode-matching into the IFO
last week, by maximizing the ratio of the x-arm transmitted power
to input power. He needed to make only one turn of the
MMT adjustment screw, which means the original MMT
alignment and adjustment was done very well (thanks, Koji!).
The MMT did not steer the beam very much;
the spots did not move visibly on the PZT
steering mirrors, and only moved by around 1 cm
40 meters away. The PZT steering mirrors easily corrected for this.
- We are now at atmosphere,
and the access connectors have been removed.
Osamu re-established the PSL beam through the mode cleaner,
and flashes were seen through the faraday isolator.
Remarkably, no steering of the PSL launch was required!
- Now, Rob is establishing a pair of optical levers to
monitor the levelness of the BS optical table, where
all the installation action will be.
Next is to replace an in-vac prism mirror with a regular 2" mirror,
and will use the prism mirror to correct for the
astigmatism in the SP beam in air, where it can be more easily aligned.
Then install the pickoff beamline,
and then intall the PRM and SRM suspended optics
and oplev beamlines, and align everything.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Last week, the digital suspension controllers for the PRM
and SRM were fully tested by having them damp the BS.
This week, Steve & Rob used them to damp the PRM and SRM,
on the South Annex flow bench. Now, everything's been tested
except for the in-vac cables, which were tested when
they were installed, and one satellite amplifier,
which is at Wilson House for full checkout.
- On Monday night, the c1suslinuxpc1 computer which
filters the suspension controller signals for the BS, ITMX, ITMY
suspensions went crazy: the cpu maxed out, the three suspensions
were shaking all night long, and the watchdogs (on a separate
aux computer) failed to shut them down. Rebooting all the
relevant computers in the morning recovered the system,
but the cause of it remains a mystery.
- The shaking might have messed up the suspension alignment;
the OSEM readings were different after damping was re-established.
- It appears that the oplev signals are a better (short-term)
reference than the OSEMs. After the shaking, Osamu found that
the Michelson error signal was better when the P/Y
biases were adjusted to recover the old oplev readings,
rather than the old OSEM readings.
- Shihori has re-measured the
pos/pit/yaw frequencies and couplings
on all the optics whose input matrices she has diagonalized
in the last few weeks. She finds that the frequencies are unchanged,
but that the pos/pit/yaw coplings have degraded a bit.
A document is in progress.
- Optical sensing:
- The oplev QPD readout for the PRM and SRM have been
tested and seem to work well.
- Fumiko recentered all oplevs prior to venting.
She continues to work on calibrating the oplev response.
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- The computer that does the filtering for the
mode cleaner WFS system, c1asclinux, loses time synch
regularly (every day or so). Sometimes it recovers
upon reboot, sometimes not.
On Monday, when it would not recover,
it was power-cycled, which interrupted the RFM network,
bringing down the DSC (digital suspension controllers) system.
To avoid this, Alex Ivanov gave this computer its own
slot in the RFM bypass switch.
- Jay and Alex fixed the code that was reading out the QPDX
signals incorrectly. Now, QPDX appears to be working well.
- The 2 Omega I&Q demod boards needed for
the SPOB signal are being fabricated.
- Mohana is working on the EPICS alarms and vacuum interlock.
- In the process of mode matching (see above),
the PZT steering mirrors were turned on and off
many times, and they always come back very close to where they were.
- The new EPICS controls of the PZT steering mirrors work well.
Osamu will adjust the biases to allow the desiring setting
to be mid-range on the sliders, while ensuring that
the voltage applied to the PZTs are always within the 0-10 volt spec.
- We are startingf to look at the lock acquisition code.
We will need Rolf's help, but it is unlikely that we will
get it soon, since he is saturated with HEPI.
- The STACIS system still is down, awaiting some attention.
- Simulations:
Seiji is using Finesse to address several questions
regarding the length sensing matrix:
- The baseline for the 40m is to use fouble-demodulation
at f2xf1 (f1 = 33 MHz, f2 = 166 MHz) to sense MICH
and f2-f1 to sense PRC and SRC.
Seiji finds that double-demodulation makes noticable improvements
for PRC and SRC as well, so we tentatively plan on using
double demod for all three length sensings.
- Seiji is exploring the demod phases required for double demodulation:
one has to find a pair of demod phases that produces no DC offset
to the error signal while maximizing the error dignal for the
desired length degree of freedom.
He can find workable phases (in principle).
- Seiji explored the relative merits of
different pickoff ports for length sensing, and finds them all to be
roughly equivalent in terms of error signal strength.
We will instrument the pickoff of the light
from the BS to ITMY, for convenience.
- Seiji explored the sensitivity of the
length sensing matrix to deviations from the ideal
macroscopic cavity lengths.
He finds length tolerances of 6 cm for MICH,
3 mm for PRC, and 3 mm for SRC.
It may be difficult to position the PRM and SRM
sufficiently accurately in air, which may require us
to iterate (vent, reposition, pump down).
- Safety (all):
Following up on the action items from the safety inspection of 1/13/04:
- Bob and Steve continue to set up the lockout-tagout system.
- Steve is getting a quote on the installation of a
fire alarm in the South Annex clean room.
- Steve asked the electricians to identify a main breaker
for the south annex which is outside the lab and which
thus could be accessed in case of a fire in the lab.
- Steve asked the electricians modify the rack power kill switches
so that the ground is not broken (as they currently do).
- Steve will ask the electricians to ground all the optical tables
to the 40m vacuum envelope (basically, anything but the racks).
- Steve arranged for routine fire alarm maintenance,
which was done this week.
- Steve and Bob are getting info on formal crane operation
certification from the safety office.
- Bob ordered steel-toed safety boot covers for
crane operation.
- Steve will install drip trays under the vacuum roughing pumps.
- All 40m personnel will get an update on lab safety from Steve
in the next couple of weeks.
-
South Annex Bake Ovens (Taylor):
- Bob is working with Larry Jones and Dennis Coyne
on the design of a new 12" bake oven for the lab,
aimed at achieving AdvLIGO cleanliness specs.
- The SRS RGA has been repaired and is being shipped back to us.
Jan 23, 2004
- Rob Ward has joined the 40 meter team as a graduate research assistant.
Welcome!
- Commissioning (Miyakawa, Kawamura, Sakata):
- We plan to vent for the installation of
the two suspended recycling mirrors, early next next week.
- Osamu remeasured the Michelson asymmetry using
the 33 MHz RF sidebants, and obtained 0.462 +- 0.028 m,
or 0.012+-0.028 m larger than design.
It is hard to reduce the error on this measurement
as it is currently being done.
- Seiji used Finesse to determine that the length sensing matrix
is not too sensitive to the Michelson asymmetry,
and can tolerate a few cm difference from design.
- However, Seiji also found that the lengths
of the power and signal recycling cavities
must be within a couple of mm of design, or the
length sensing matrix will be significantly degraded.
We're not sure how we can place the optics to that level
of accuracy in air! We will try our best, and iterate
(requiring vents) if necessary.
- Osamu looked at the optical axis of the 29 MHz and 33 MHz
pockels cells, and found they differed by 18 degrees!
But, then he found that a HPW placed before the 29 MHz
pockels cell in the PSL IOO path during the re-layout
was actually a quarter wave plate!
He has replaced it, and remeasured the optical axes
of the 2 pockels cells; they are within 3 degrees,
quite tolerable.
He has realigned the beam through all 3 pockels cells
(including 166 MHz), minimized the AM for the 33 MHz,
and found that the AM on the other two frequencies was
small and tolerable.
- He then re-established the mode cleaner lock
with the correct polarization and modulation depth
for all 3 RF frequencies.
- Osamu is testing the use of the in-vac mode matching
telescope and in-vac PZT steering mirrors,
in preparation for mode matching into the main IFO
after installation of the recycling mirrors.
We are relieved to see that moving the mode matching telescope
focus steers the beam only slightly, and the spot
doesn't move off the small PZT steering mirror downstream.
Current plan is to mode match by maximizing
the light transmitted through the arm cavities;
not very sensitive, but good enough for us.
- Before vent, we will recenter all oplevs,
and document all the readbacks and settings
for all servos, OSEMS, oplevs, PZT steering mirrors, etc.
- Rob Ward has built a small Michelson interferometer
for use as a hands-on demo. It works great!
- Seiji has been looking at uses for double demodulation
to improve the diagonality of the length sensing matrix,
and finds that it can be used to improve the matrix
for the PRC, SRC, and MICH degrees of freedom (l+, ls, l-),
*if* the demod phases can be chosen and optimized well.
We are not sure how to do that!
- Bob has returned the dycor RGA head to Steve,
and Steve has reinstalled it on the 40m main volume
and calibrated it.
The electron multiplier on this head
doesn't work, but it isn't a big problem right now.
- Steve has all the 2" mirrors and mounts
needed to install a BS pickoff beam.
He has all the in-vac oplev mirrors.
he has all the weights for balancing the
BS table (cleaned and baked).
He has all the clean air for the vent.
- Bob is getting replacement bulbs for the chamber
illuminators (plus spares).
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- Jay and Peter Fritschel discussed the prototyping
of the sensing beamline centering/stabilization servo at the 40m.
Peter will send us some steering mirrors.
Rob Ward will take responsibility for commissioning
and characterizing the servo.
- Jay has 133 MHz and 199 MHz resonant circuits
working for the LSC RFPDs.
- Jay has 2omega
I&Q demod boards for SPOB signal ordered and are due
by 1/29. They will then be stuffed and tested.
- Mohana is working on the EPICS controls of the
PZT steering mirrors, the mechanical shutters,
and the vacuum interlock (ensure that the PSL shutter is closed,
and the PZT mirrors are not energized, when making transition
from vent to high vacuum and vice versa).
- Rob and Steve discovered a 2 hz comb on the ETMY UL OSEM
noise spectrum. Jay determined that it was due to
ICS110b channel hopping,
and he cold-booted the crate (power down crate;
count to 60; power back up; restart processor)
and it went away.
A day later, it was ETMX LL, again fixed by cold booting.
- The c1asclinux processor (for MC WFS ASC control)
has been falling out of time-synch; the servo works fine,
but the DAQ data is probably screwed up.
Rebooting fixes it. Sigh.
- Lisa Bogue has instructed us on how to back up
the data on our main CDS computer (op140m), and we
will do it weekly.
- Work on ASC readout (especially the QPDs) is in progress.
- The STACIS system still is down, awaiting some attention.
Rob Ward is starting to look at it.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- We have checked out the PRM and SRM digital suspension
controllers (DSC's) by using them to damp the BS.
Next, we will damp the actual suspensions with them
(they are in the South Annex flow bench).
Thus, everything will be well tested prior to installation,
except for the in-vac cables (which were tested when they were
installed last year).
- Shihori has completed the diagonalization
of the input matrix for all suspended optics
except for ETMX (which has a badly-positioned OSEM
which will be fixed during the upcoming vent).
She obtains satisfactory decoupling of POS, PIT, YAW;
the worst cases in the small optics
are ~ 8% cross-coupling; in the ITMs and ETMs,
~ 3%. She is documenting the procedures and results,
and will move on to the output (coil) matrix.
- Optical sensing:
- We should have 12 QPDs looking at the main beam
(as well as 7 oplev QPDs). Most are in place,
have light on them, are being read out, and being logged
to frames (16 Hz).
Steve and Jay are getting two very important ones
(initial pointing position and angle) all checked out.
A few more will be completed after the vent.
(Done: IOPOS, IOANG, TRX, TRY, POX, POY.
In progress: IPPOS, IPANG. Later: SP, AP, MCR, MCT).
- Safety (all):
Following up on the action items from the safety inspection of 1/13/04:
- Bob has installed a lockout-tagout kit, and he and Steve
are setting up the system. We will all be trained on it in a week or 2.
- Steve and Bob are getting info on formal crane operation
certification from the safety office.
- Steve & Bob are getting steel-toed safety boots for
all crane operators (Steve, Bob, Osamu).
- Steve will install drip trays under the vacuum roughing pumps.
- Bob has modified and reposted the emergency procedure for the
South Annex bake-out facility.
- An audible fire alarm will be installed in the
back room of the South Annex.
- Steve has removed obstructions in the areas around
the electrical panels and the emergency exits.
- All 40m personnel will get an update on lab safety from Steve
in the next couple of weeks.
-
South Annex Bake Ovens (Taylor):
- Bob is baking glass dishes to hold the in-vac cables,
to keep the ground braid isolated from the chamber walls.
- Bob continues to work with Larry Jones
and Dennis Coyne on getting the bake ovens
clean enough for AdvLIGO specs.
He's building a new super-clean oven,
and is replacing the temperature controller for another.
Jan 16, 2004
- Safety (all):
-
There was a safety inspection of the 40m lab on Tuesday, January 13.
Several items that were called out last year had not been addressed;
All of these issues are now being addressed, aggressively, belatedly.
- Bob has ordered a lockout-tagout kit, and will set up the system.
All personnel will be trained in its use.
- Steve and Bob are investigating more formal crane operation
certification.
- Bob is ordering steel-toed safety boots for all crane operators
(Steve, Bob, Osamu).
- Steve is ordering, and will install,
drip trays under vacuum roughing pumps.
- Bob is modifying the emergency procedure for the
South Annex bake-out facility in
case of fire, equipment overheating/failure or loss of electrical power,
based on comments from the safety inspectors.
- Bob had the South Annex fume hoods calibrated,
and they are within specs.
- An audible fire alarm will be installed in the
back room of the South Annex.
- Commissioning (Miyakawa, Kawamura, Sakata):
- We are planning to vent for the installation of
the two suspended recycling mirrors, next week. More detail below.
The current work is all preparation for this installation.
- Steve is completing the installation and commissioning
of all the QPDs for beam monitoring, especially the
ones that monitor the initial pointing of the beam
just before it hits the PRM.
- A mechanical shutter has, at long last, been installed
on the PSL periscope. EPICS control of this shutter,
including an interlock to the vacuum state, will be implemented
by Jay soon. Steve and Osamu will install
three more mechanical shutters in the API table, for the
MCR, SP, and AP beamlines.
- The 166 MHz pockels cell has been installed on the PSL table.
All wiring is in place, the pockels cell has been energized;
modulation depth checked with a scope;
signals appear at the 166 MHz I&Q demod board (at the SP beamline);
and into the digital LSC system. The signal generator has been
phase-locked to be exactly 5x the 33 MHz signal.
- Osamu used the 166 MHz sidebands to measure the Michelson
Schnupp asymmetry. He put a HWP before the 166 MHz pockels cell to
induce AM as well as PM onto the light, and measured the transmission
of the AM at the dark port. From this he calculated the
Schnupp asymmetry to be (0.39+-0.05) meters, or (6+-5) cm lower than
design (the design will tolerate a difference of up to 10 cm).
The large errors are due to difficulty in measuring the AM
in the presence of beats at lower frequencies. Osamu is working on
a different, more sensitive method.
- However, the 166 MHz RF PD seems to have sustained some damage,
and Osamu is working on getting a replacement PD.
- Osamu has developed a procedure for aligning the PSL beam
into the Mode Cleaner (in vacuum or in air) using the
MC error signal as a guide. This should make it much easier to use
the PSL beam, in air, to align the interferometer during installation.
- Osamu checked that we are able to robustly lock the arms
(using POX and POY) even at 8% of our usual input power,
thereby simulating the situation when the PRM is installed
(but misaligned so that the power recycling cavity is not in resonance).
Indeed, we can; however, the DC output is very low,
and is in the digitization noise. Jay will look into increasing the gain
on the PD board.
- We will check out the damping of the PRM and SRM
on the bench in the South Annex, using the real
satellite amplifiers and digital suspension controllers;
only the in-situ cables will remain to be tested during installation.
- Steve has assembled all of the vacuum mirrors
needed for installation (Lee Cardenas will assemple a few more
in the next few days), for the pickoff beam, the oplevs, and the video views.
He has also ordered more laser diodes for the oplevs.
He has all the clean air tanks for the vent.
- Steve and Bob will prepare clean glass dishes
to hold the in-vac cables, so that the ground braids
aren't electrically shorted to the chamber.
- Osamu has assembled a detailed installation procedure / checklist.
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- Jay retuned
an LSC PD and I&Q demod board for operation at 166MHz.
The higher frequency required us to use a smaller active area PD.
The PD and demod board are installed and operational in the SPD2 position.
(But see above; it is already damaged).
-
Jay installed 2 more power supplies in parallel
with the +/-15V supplies to raise the maximum current to 8 amps.
Requested sorenson power supplies from LLO
to be used to handle future power supply needs.
- Jay is fabricating another 2 Omega I&Q demod board for SPOB.
- Work on ASC readout (especially the QPDs) is in progress.
- Mohana is implementing the EPICS control of the
in-vac steering mirrors. These will help us to re-establish
correct initial pointing, during and after the installation.
- Mohana is also implementing the EPICS control of the
mechanical shutters, and the interlock with the vacuum.
- Most of the VME cpus went down over last weekend
for some unknown reason. After a few failed attempts,
Jay and Alex got them all back up.
- DTT has not been working well. Alex and Daniel Sigg
have found bugs in the code (related to timing);
they fixed one and are working on another.
- The STACIS system still is down, awaiting some attention.
Rob Ward is starting to look at it.
-
South Annex Bake Ovens (Taylor):
- Bob obtained a new RGA for his bake ovens.
- The SRS RGA was removed from the 40m and is now in Bob's lab.
- Bob has reviewed the draft specs on vacuum cleanliness
for Advanced LIGO, from Dennis Coyne.
- Bob continues to work with Larry Jones on making the mods
to his ovens to mean the Advanced LIGO cleanliness specs;
looks do-able.
- See safety issues, above.
Jan 8, 2004
- Commissioning (Miyakawa, Kawamura, Sakata):
- We are now routinely locking our
Fabry-Perot-Michelson (FPMI).
- During the long break, Osamu worked on filters and
whitening/dewhitening to reduce the noise in the FPMI;
the resulting spectrum can be seen
here.
- Seiji and Osamu tried getting a Michelson control signal using
the 2nd harmonic of the 33 MHz RF; unfortunately, they could not
turn up the modulation depth sufficiently, and thus a signal
at 99 MHz (3rd harmonic demodulation) could not be cleanly seen.
- Osamu, Steve, and Bob are installing the 166 MHz Pockels cell
and associated cabling, for HF RF sensing of the dual-recycling
length (and angular) degrees of freedom.
Jay is preparing the 166 MHz LSC RFPD and I&Q demod board.
- Osamu and Seiji are making plans to measure the Michelson
asymmetry. One approach is to amplitude-modulate the 166 MHz
RF sidebands, and measure the reflection to the SP.
Another approach is to lock the arms one at a time
using the SP RFPD, and measure the difference in demod phase
required to zero the signal at resonance (as Peter Fritchel
explained to us).
- We are making plans to install the power recycling mirror (PRM)
and signal recycling mirror (SRM) in the next week or 2.
In consultation with Mike Smith, we outlined
a tentative alignment procedure for aligning the recycling mirrors,
using an autocollimator beam brought in from outside
(so as to not have to use the PSL beam through the mode cleaner,
while in air; this requires too much re-steering of the PSL,
which then has to be undone after we pump back down).
- We plan to vent in the next week:
install the two suspended recycling mirrors;
install mirrors for oplevs for those suspended optics;
install mirrors for camera views for those suspended optics;
fix a badly-positioned UR OSEM on ETMX;
adjust the in-vac PZT steering mirrors;
commission the PRC PO port; and align the beam through the DR IFO.
We hope that we can complete all these tasks in 2 weeks.
- We also need to replace an in-vac Brewster prism mirror (used to
correct the astigmatism placed on the SP beam)
with a regular mirror; we'll use the Brewster prism mirror
in air, where we can fine tune its position.
- During this time, we will continuously monitor the positions
of the suspended optics with our optical levers.
Fumiko is making sure that all the oplev beams
are centered on their QPDs, and reliably sensing the optic P&Y.
- We will then re-establish the FPMI with mis-aligned PRM and SRM.
Before the installation, we will verify that we can control
the FPMI with the expected loss of incident power through
a mis-aligned 7% transmissive PRM.
- We will postpone the cleaning of the optics
(we know their surfaces are dusty and reducing the visibility
of the high-finesse arms) for a later vent.
- We will postpone fine-tuning the mode matching into the IFO
until after we install the recycling mirrors.
However, we will go through the mode-matching procedure
(changing the MMT focus, and compensating for beam steering
with the the in-vac PZT steering mirrors)
before venting, in order to determine
whether / how much to move the PZT steering mirrors positions.
- Steve is working on the commissioning of the remaining
QPDs for the initial pointing
position, and then the QPDs and cameras at the SP and AP.
- We are working on the commissioning of the LA code
for power recycling and then dual recycling.
currently, we use a fixed sensing matrix for lock acquisition
of the FPMI.
- Jay is working on the readout of the ASC QPDS,
which we need for linearization of the sensing signals
for lock acquisition.
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- Jay delivered to us an LSC RFPD tuned to 99 MHz
and associated I&Q demod board for the 3rd harmonic demodulation
experiment referred to above.
- Jay is now in the process of converting the LSC RFPD and I&Q demod board
for 166 MHz.
The PD will likely require that we use the
smaller active area PDs that we have,
to control parasitic capacitances.
- Several of the chamber illuminators are not working.
Bob will check; they may just be blown bulbs!
- Jay will set up EPICS controls for the mechanical shutters,
including an interlock to shutter the PSL beam
if the vacuum pressure goes up.
-
The STACIS system still is down, awaiting some attention.
-
There will be a safety inspection of the 40m lab on Tuesday, January 13.
An update was made to our 40m PSL SOP (Standard Operating Procedure)
document, as recommended by the safety inspectors last year.
Dec 19, 2003
- Commissioning (Miyakawa, Kawamura, Sakata):
- After some effort, Osamu and Seiji have managed to get the
ETMX and ETMY coil dewhitening filters turned on
after aquiring lock, without losing lock.
This required several changes:
(a) when turning on the hardware dewhitening,
the software inverse dewhitening gets turned on at the same time.
That software (digital) filter was being turned on with "Zero history"
instead of "always on", so there was an initial impulse which
would kick the mirror, causing lock loss.
They changed it to "always on", fixing that problem.
(b) The feedback signal has large peaks at 3-5 kHz and 300-500 Hz,
origin unknown. (They will trace these upstream to see where they
come from). The 3-5 kHz oscillation was saturating the coil driver DACs.
To reduce the effect of these peaks,
they adjusted the filters, reducing the UGF from 300 Hz to ~100 Hz,
adding more phase margin at 300 Hz, and reducing the LPF corner
frequency.
(c) They put in notch filters to eliminate the feedback
at the peaks at 300-500 Hz.
- After all this, they were able to switch on the
ETM coil dewhitening filters (and digital inverse filters)
without losing lock. They saw 30 dB of noise reduction in AS_Q
from 40-300 Hz.
- Next big effort is to mode match the beam into the arms.
Our in-vac mode matching telescope uses fixed mirrors
with a stepping motor for focus. When we adjust the MMT,
the beam is steered. So, we need to complete the setup of the
QPDs that monitor the initial pointing position and angle
of the beam (after the MMT but before the IFO) to correct for this
using the in-vac PZT steering mirrors.
And, we are setting up remote control of these PZT steering mirrors.
Osamu and Seiji are working out methods for sensing mode mismatch
using reflected light through an iris to sense the TEM00 mode,
as the MMT is stepped through its range.
Osamu's first attempt to make this work failed,
presumably due to the ringing of the reflected light power
due to doppler effects.
Seiji is developing another scheme using the Michelson
which should be immune to this effect.
- Seiji and Shihori checked one aspect of the
displacement calibration: is the BW reported by dtt right? It is.
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- Jay has been debugging the electronics readout of the
QPDs that were set up by Steve. He found a bad 3113
and has replaced it.
- Jay
began the tuning of an LSC PD for 99MHz operation. I
t is proving to be difficult due to parasitics in the circuitry.
An I&Q demod board is also being tuned for 99MHz operation.
- Bob is running cables for the remote control of the
mechanical shutters for the input beam from the PSL
and the output beams for MCR, SP, and AP.
- Jay will set up an EPICS channel that can be used to
shut the mechanical shutter at the PSL periscope
if the vacuum pressure rises above some level.
- Bob is running cables for slow EPICS control
of the PZT steering mirrors.
- Steve set up a ccd camera to provide a wide view of the
entire PSL table.
- Bob has run the last of the cables for the ccd cameras
that view all the optics and all the beams (and the PSL table).
- We are following with interest the discussions in the CDS group
about (a) placing multiple RF sidebands with one EOM.
(b) Progress with the PSL ISS at LLO.
(c) The ASI servo at LHO.
(d) Servoing the beams onto the photodiodes on the ISC tables.
-
The STACIS system still is down, awaiting some attention.
- PSL (Miyakawa, Kawamura, Abbott, Nocera):
- The power from the PSL was observed to drop by a factor of 2 on 12/4.
After much investigation, Osamu discovered that it was mode-hopping.
He adjusted the FSS slow loop (temperature servo) DC offset
until the laser re-locked onto the correct mode, and the power
came back up.
-
The PSL ISS system is disabled until Flavio
investigates the dynamic range problem.
- Optical sensing (Smith, Kawazoe):
- Steve completed the instumentation of the POX and POY beamlines
as well as the TRX and TRY, and is now turning to the initial pointing
position QPD, and then the QPDs and cameras at the SP and AP.
- Fumiko has made great progress in establishing the sensitivity
of the oplevs to the motion of the suspended optics,
and also the laser pointing jitter noise.
She will soon be able to turn to implementing
the oplev damping servos.
-
South Annex Bake Ovens (Taylor):
- Bob continues to work on cleaning the bake ovens
and attempting to each the cleanliness levels required for AdvLIGO.
- Several of Bob's bake ovens have RGA heads that are 15-20 years
old and are starting to fail. He will purchase a new one.
- There was a fire alarm test at the lab,
and the alarm could not be heard in the south cleanroom
in the south annex. Steve will follow up.
Dec 12, 2003
- Commissioning (Miyakawa, Kawamura, Sakata):
- Osamu has been out with the flu,
so there hasn't been much commissioning work.
- Seiji wrote up a document describing the
calibration procedure of the Fabry-Perot Michelson,
resulting in a noise spectrum that bottoms out at ~ 2e-16 m/rtHz
above 2 kHz.
- Osamu and Seiji found that the demod phase required to lock
the Michelson if only one arm was locked was different,
depending on which arm it was.
Seiji determined that this is due to contamination
of a large ASI signal into ASQ when the demod phase
is not tuned precisely correctly, to better than 1degree.
This isn't really a problem, because one normally doesn't
bother to lock the Michelson with only one arm locked.
I suppose we will eventually need an ASI_CORR servo.
- Our original plan was to attempt to lock the michelson
using beats between the 33 and 166 MHz sidebands
(ie, not using the carrier, and thus insensitive to the arms).
However, Seiji realized that this could not work, because
both sidebands are phase modulations, and no Michelson signal
can be obtained using phase modulation only.
He suggests using the 2nd-order sideband at 66 MHz,
which is amplitude modulation; beating that against
the 166 MHz will yield a signal at 99 MHz, sensitive
to the Michelson. Seiji verified this with Finesse.
Jay will see about getting an LSC RFPD and demod board
for 99 MHz.
- Osamu is documenting all the 40m procedures
and the performance of the various components (PSL, MC, IFO).
It's already a very substantial document, but still in progress.
- Steve is working on installing the last of the
beamline cameras and QPDs.
- Next big step is to implement 166 MHz RF sidebands
and demod boards at 166, 99, 133, and 199 MHz.
- And, tune mode-matching into the main IFO.
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- Medm screens for the beamline QPDs have been made,
and the QPD channels have been added to DAQS.
- From Jay:
Researching various ways to produce the 133MHz and 199MHz that the 40M
double demod system will require. Our fall back is to use phase locked
IFRs. I am also looking into how to make an LSC PD with resonant peaks
at 133 and 199MHz and a notch at 166MHz. Theoretically it is possible,
but practically it may be difficult.
- Bob is running RF heliac cables for these new RF signals.
- There are plans brewing to add steering servos
to the sensing beamlines, as a prototype for the sites.
It would be relatively easy to add these to the existing controls.
- Bob continues to clean up and label the cable plant
throughout the lab.
- Osamu is preparing to install the 166 MHz EOM on the PSL table.
-
The STACIS system still is down, awaiting some attention.
- PSL (Miyakawa, Kawamura, Abbott, Nocera):
-
The PSL ISS system is disabled until Flavio
investigates the dynamic range problem.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Shihori now has a suspension diagonalization procedure
that seems to work well, and has completed the
input matrix for ITMY.
- She will move on to the other 9 optics,
then work on the output matrices, and then optimize the damping.
- Optical sensing (Smith, Kawazoe):
- Fumiko continues to work on understanding the
oplev signals, to establish the calibrated rms motion
of the sensed optics and distinguish it from oplev sensing noise.
-
South Annex Bake Ovens (Taylor):
- Bob continues to work on cleaning the bake ovens;
some are so dirty that they have to be rebuilt.
He's making progress, and the oven cleanup is improving
the RGA scans.
- At the moment, the ovens in the south annex
(and at the sites) are not clean enough to meet
the AdvLIGO specs. Bob is working with Dennis Coyne and Larry Jones
to see what can be done.
Dec 5, 2003
- Commissioning (Miyakawa, Kawamura, Sakata):
- Osamu, Seiji, and Shihori have been working on tuning
the filters for length control of the Fabry-Perot-Michelson
to achieve low-noise operation.
- They did a careful calibration (documentation in progress)
and a displacement noise spectrum.
To reduce the noise, they are working on implementing
whitening and dewhitening filters in hardware,
with appropriate software compensation.
- They succeeded in reducing the noise above 2KHz
(to around 1e-16 m/rtHz) using the
hardware LSC whitening filter, after adjusting
offsets and gains.
- They had trouble employing the dewhitening to the coil drivers;
there was a large 100 Hz oscillation. They traced it to the MC
servo cross-over (between MCL and VCO).
They reduced the MCL gain, but MC locking became less stable;
they suspect VCO saturation.
- But, with the modified MCL/VCO gains,
the noise in the 30-300 Hz region is now 2x better than before.
- Another problem with the hardware dewhiting filter
is that the board is RevB2; should be B5.
This has been fixed; now, the dewhitening filter transfer function
is according to design.
-
There's also some 4kHz oscillation in the coil driver.
All under investigation.
- The symmetric port beam seems to be clipping
at an in-vac Brewster prism mirror.
This might improve once we properly mode-match into the IFO (not yet done).
- IFO auto-locking scripts have been developed and tested.
- QPDs and cameras have been installed and aligned
at the ends (TRX and TRY).
Still need to install the remaining optics in POX and POY,
and complete the sym port (SP) beamline, including
electro-optic shutter.
- Next big step is to implement 166 MHz RF sidebands
and demod boards at 166, 133, and 199 MHz.
- And, tune mode-matching into the main IFO.
- Osamu is documenting all the IFO locking, tuning, and calibration
procedures that he and Seiji are developing.
- Computing:
- Our main "online" computer, op140m, crashed last week,
bringing all commissioning to a halt.
- Lisa Bogue came to our rescue, and with Jay,
they took the opportunity to finally bring up
our Sun E450's and completely re-arrange the computers
in our control room.
Bob, Steve, and Osamu all helped rearrange and recable
all the computers there.
-
One E450 is now the new op140m, and has all the
controls software (targets, dataviewer, dtt, etc).
One of the old Blade 100's now has 2 screens in "cinematic" mode.
-
Finally, dataviewer and dtt now seem to run reliably
on the E450. These essential commissioning tools were all but useless
when running on our Blade 100's; they now seem to work!
- Lisa is rearranging all the data and accounts
in our martian network, cleaning up a very sloppy
and barely functional system.
- Many thanks to Lisa and Jay for getting our
control room back in shape!!
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- From Jay: ASC aux crate testing is ~90% complete.
- Ben has installed balancing pots on the last three Universal
Dewhitening boards needed for the IFO.
These and others that he had done
previously, are now installed on: ITMX, ITMY, BS, PRM, SRM, ETMX, ETMY,
and MC2. These optics are now finished on this issue except the four
newly installed ones (ITMX, ITMY, PRM and SRM) which need to have their
digital gains balanced by Osamu.
-
Jay continues to develop plans to form double demod signals
(at the sum and difference of 33 and 166 MHz) for LSC.
He suggests first using the sums and differences,
then move to genuine double demod in a second step.
- So, we'll form 133 MHz and 199 MHz
by phase-locking the signal generators,
then bring those signals over to the LSC crate demod boards.
- Bob is running RF heliac cables for these new RF signals.
- Osamu is preparing to install the 166 MHz EOM on the PSL table.
-
The STACIS system still is down, awaiting some attention.
- PSL (Miyakawa, Kawamura, Abbott, Nocera):
-
The PSL ISS system is disabled until Flavio
investigates the dynamic range problem.
- Osamu is working on completing technical notes
on the performance of the PSL post-re-layout.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Shihori continues to work on improving the input matrix
for ITMY and the remaining suspended optics.
- Optical sensing (Smith, Kawazoe):
- Fumiko continues to work on understanding the
oplev signals, to establish the calibrated rms motion
of the sensed optics and distinguish it from oplev sensing noise.
-
South Annex Bake Ovens (Taylor):
- A mistake in the bake oven RGA calibration was found,
and it is now realized that some of Bob's bake ovens
are dirtier than was thought.
Bob is working with Larry Jones and Steve
to diagnose and correct the problem.
-
He is in the process of rebuilding bake oven C,
and has found a large deposity of gunk close to the
turbopump manifold. Under investigation.
- He's also been baking the other ovens
to recondition them.
- AJW compiled an equipment budget for the 40m for FY04,
with input from Jay, Steve, and Bob.
There has been some re-alignment of the budget in order to
relieve the pressure on the overall LIGO budget...
Nov 21, 2003
- Commissioning (Miyakawa, Kawamura):
- Osamu and Seiji now routinely lock MICH, CARM, and DARM
quickly and reliably; locks hold for more than 30 minutes.
- They have been tuning demod phases, gains, filters, etc.
They have added filters to compensate for the cavity pole,
and for notching the violin modes, to avoid ringing them up.
- They calibrated the response of ITMX using Michelson fringes,
measured the OLG, and applied a calibration signal at 100 Hz on ITMx.
Using this info, they
took the first calibrated displacement sensitivity curve on the 14th,
tweaked the alignment and gains, and a second on the 18th:
40m displacement sensitivity.
It's about 5e-16 m.rtHz at 3 kHz, with lots of excess noise below that.
- Since then, they were able to minimize LSC error signal offsets,
turn on whitening and dewhitening filters
without losing lock, and saw improved noise above 3 kHz.
- We still need to lock the arms separately before engaging
CARM and DARM, because we don't yet have lock acquisition
code for a dynamic control matrix to allow direct acquisition
via MICH, CARM, DARM.
- Steve and Shihori have been commissioning the TRX and TRY
transmitted ports. The ASC photodiodes and CCD cameras there
are needed for continued progress.
- Commissioning is *severely* hobbled by the unreliability
of dataviewer and DTT; they often hang or crash or simply
fail to run on our underpowered Suns.
We continue to await help from the computer group to
get our new E450's up and running.
Meanwhile, much of the problem is a beleagered test point manager;
it will need to be rebooted.
-
Steve and Shihori are in the process of installing QPDs
at SP, AP, POX, POB, POY, TRX, TRY, and InitialPointing postition and angle.
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
-
Mohana and Ben have installed and are testing the EPICS crate software
and MEDM screens for all the ASC signals (QPDs and WFSs) at the vertex.
Problems with wiring, databases, and screens are being
found and fixed.
- The ASC QPD modules are now being read out correctly.
The QPDs themselves are still being installed and aligned.
- One LSC photodiode spontaneously had it's power
turned off, and we couldn't get it back on.
Ben traced the
problem to an error in the EPICS control database
for that LSCPD, and fixed it.
-
Jay is developing plans to form double demod signals
(at the sum and difference of 33 and 166 MHz) for LSC.
He suggests first using the sums and differences,
then move to genuine double demod in a second step.
-
The STACIS system still is down. Ben got a PC-based program
to help diagnose the problems, but it wasn't very helpful.
-
Bob and Art laid down heliac cable to run the RF signals from
the RF signal generator rack to the distribution box in the
LSC/ASC rack.
-
Bob ran video cables for CCD cameras at SP, AP, POX, POB, POY, TRX, TRY.
-
Bob is building spare OSEMS for the 40m and for Janeen.
- PSL (Miyakawa, Kawamura, Abbott, Nocera):
-
The PSL ISS system seems to run up against dynamic range
and slowly push down the beam power.
Flavio is investigating to see if this is the same
problem as has been seen and addressed at LLO.
- We need a way to quickly diagnose whether the ISS is working.
Flavio will look into forming ISS_error_rms EPICS channels.
- Conor is visiting, and has drawn up a nice picture
of the new layout of the PSL, as part of his final writeup of the
new system and its performance.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Shihori continues to work on improving the input matrix
for ITMY and the remaining suspended optics.
- Ben finished modifying all of our Universal Dewhite Boards to allow
the nulling, or at least equalization,
of offsets when switching in and out hardware dewhitening.
- Optical sensing (Smith, Kawazoe):
- Fumiko continues to work on understanding the
oplev signals, to establish the calibrated rms motion
of the sensed optics and distinguish it from oplev sensing noise.
- The oplev signal scanning frequency will be increased
from 2 to 16 Hz to allow
us to study the noise spectrum up to 8 Hz Nyquist.
- Modeling (Miyakawa, Kawamura):
- Seiji is continuing to study error signals
with Finesse while sweeping through (l+,l-,ls) space.
He's making "movies" that show how error signals in one DOF are lost
when sweeping through the other two DOFs.
- Matt Evans kindly gave us a tutotial on his lock acquisition
algorithm and code, walking us through all the gory details.
-
South Annex Bake Ovens (Taylor):
- Bob and Steve were doing RGA scans for Larry Jones (AdvLIGO SEI system),
and discovered that the bake oven heaters had failed.
Bob has been rebuilding the heater tape on oven B,
and revamping the temperature controllers.
He's gearing up for many more bakes for Larry.
Nov 14, 2003
- Commissioning (Miyakawa, Kawamura):
- Michelson, X-arm, Y-arm all locked simultaneously
in CARM, DARM, MICH degrees of freedom.
Osamu and Seiji accomplished this by first locking XARM, YARM, MICH,
then moving slowly to CARM, DARM, MICH without losing lock.
Longest lock time so far in this mode is 1.5 minutes.
- Before this, they tuned up the FPMI in XARM,YARM,MICH mode,
measuring the noise power spectrum in the XARM and YARM as they
went along.
- Aligned for both cavities.
- Conpensating filter for cavity pole with zero at 1.6kHz, pole 3kHz.
- Adjusting SP1Q demodulation phase for Michelson to minimize L+ signal at SP1Q.
- FPMI lock with POX, POY and SP1Q signal.
- Low noise FPMI with A.A filter, whitening filter.
- Gain distribution for Michelson servo to remove satiration at feedback signal to BS.
- Filter to remove the violin mode, notch at 884Hz, Q=100, Gain=10.
- Computing:
- Our main "online" disk, op140m:/cvs/cds , died on Monday.
Lisa Bogue did some emergeny repairs, and recovered it,
backed it up, and copied it to a new partition, on Wednesday.
Thanks, Lisa!
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- Ben is installing the last EO shutter controller in the 40m lab.
There is a slight problem in the power, but that should be an easy fix.
- Ben got the Labview exacutable program for the STACIS controllers
at the 40m. So far, the program seems to not be very useful,
but a newer version may be available. He is waiting for a call back from TMC.
- Ben put balancing potentiometers on 6 more Universal Dewhite boards,
and balanced their regular and bypassed paths for each channel.
- Upon installation, the LR channel for ETMY looked bad.
Ben finally traced the problem to a bad connector on the Pentek.
- Ben has been working with Mohana to install her ASC auxillary code and screens.
There are some white fields in the WFS screens that will probably be fixed
once we figure out what is wrong with two of our 4116 modules.
- Ben, Osamu and Seiji installed filters into one of our digital filter banks
with help from Rolf and Alex.
- More progress will be reported in the next weekly report.
Nov 7, 2003
- Commissioning (Miyakawa, Kawamura):
- Michelson, X-arm, Y-arm all locked simultaneously.
- Using three LSC RFPD (POX, POY, and AP),
Osamu and Seiji have succeeded in locking
these 3 degrees of freedom at the same time, robustly, last Monday.
We celebrated with a lunch party, today (Thursday).
-
The Y arm gain has a sign flip with respect to the X arm,
probably due to flipped magnets on ETMX.
-
The Michelson signal was very noisy at first.
This was traced to ADC digitization noise
from the error signal readout with low gain on the whitening boards.
They adjusted the gains and software filtering for the LSC channels,
Now, all 3 loops have software gain around 1,
and exhibit robust, low-noise locking and relatively high UGF's.
- Osamu and Seiji continue to tune and improve the
lock acquisition and in-lock servos optimization,
including better tuning of the Michelson
demod phase, to reduce the influence of the arm signals
on the Michelson.
- The Michelson contrast is very good;
to be measured carefully, soon.
We still need to adjust the mode matching into the arms.
- We need to re-measure the arm reflectivity;
but it sure looks like the mirror surfaces have
lots of dust. We plan to vent soon, to clean them
(and fix a misplaced OSEM on ETMX).
- Next step is to move to the common-mode and
diff-mode control topology, and implement a common mode servo
(based on the LLO incarnation).
-
Then, characterize, measure response, calibrate, noise spectrum, etc.
- The longer-term plan proposed by Seiji and Osamu is to
vent, clean mirrors, fix osems, but don't install
the recycling mirrors yet.
Then, re-establish operation, with clean mirrors.
Then, commission 166 MHz sidebands,
and see how robust the Michelson signal is
in the (166-33) MHz demodulation, where the carrier light is not used.
This is a key element of the AdvLIGO control scheme,
allowing us to control the short degrees of freedom
(Michelson, PRC, SRC) without being sensitive to
the locking and control of the long arms.
We need to build 133 MHz frequency distribution system
and demod boards.
- The mode cleaner and its ASC WFS system are working well.
Remaining low-frequency intensity fluctuations in the
MC transmitted beam are from upstream of the MC,
so Flavio is now commissioning the Intensity Stabilization servo
for the PSL, to address this.
- Osamu and Seiji are optimizing all the control loops
with the help of 6 scopes, including three
fast (100 MHz or higher, with high sampling rate)
4-channel digital scopes.
We need more scopes, more shutter controllers, more SR560's.
(Basically, we need more money!).
- We also need to learn how to use the EZCA scripts
for autolocking, calibration, etc.
- Electronics (B. Abbott, Heefner, Taylor, Nocera, Mageswaran)
- Jay found some problems with signals from one of the LSC PD interface
boards. He and Ben trouble shot the problem, and found two independant
causes. One was a low voltage problem on the +/- 5V supplies, and another
was an ungrounded LEMO connector. Both have been corrected, and the
signals are fine now. Ben will survey all the cables.
- Ben and Sander are getting parts for two more
EO shutter controllers. All the cables for three EO shutters are in place.
- The PCB for the LSC PD tester board arrived Wednesday,
and Ben will stuff and test it today.
- Mohana is completing the code, databases, and screens
for the ASC auxiliary crate, and we hope it will
go in today, so that we can read out all the QPDs
in the vertex and the ends.
- We have a long list of new signals (ISS, ASC QPDs, etc)
that need to go into master.config.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
-
Shihori applied her iterative procedure to
better diagonalize the input matrix, to ITMY and BS
(ITMX is already much better diagonalized).
- She is now working with Osamu to diagonalize
the output (coil) matrix of the BS
to help with michelson lock stability.
- Her work is severely hampered by the inability to
run DTT with bandwidths smaller than 0.05 Hz;
we hope that this is due to the slowness of the Sun Blade 100,
and will be remedied when we get the new Sun E450's online.
- Ben is modifying six of our Universal Dewhite Boards to allow
the nulling, or at least equalization,
of offsets when switching in and out hardware dewhitening.
-
Optical levers (Kawazoe, Heefner, Abbott):
- Fumiko has analyzed her
oplev response calibration data; all 6 oplev sensors
have similar slopes (response in volts versus
pitch and yaw) near their operating point.
- She will use this information to calibrate the
pitch/yaw bias controls,
measure the rms noise (in radians) with the mirrors
(a) undamped; (b) damped; (c) under IFO lock.
- Next step is to import the oplev servo filters
from the sites, make any necessary mods, and commission the servos.
- Optical sensing (Smith, Kawazoe):
- Fumiko aligned
the optical, photodetector, and electronics chains for
the POX and POY beams.
Osamu and Steve did the SP beamline.
Still to be done: TRX, TRY, POB.
-
Fumiko is installing all the QPDs on all the beamlines,
and awaits the installation of the ASC auxiliary readout
software that Mohana will install soon.
- Fumiko will commision the EO shutters on the SP and AP.
-
She and Lisa will put in all the ccd cameras.
- Computing:
- We desperately need to bring our new Sun E450 online
so that we can (hope to) run dataviewer and dtt reliably
(we've had no end of problems with these programs,
running on an under-powered Sun Blade 100).
We will need help from the computing group, and Alex Ivanov.
- Modeling (Miyakawa, Kawamura):
- Seiji is continuing to study error signals
with Finesse while sweeping through (l+,l-,ls) space.
- Per his request, Andreas Freise
quickly implemented the ability to sweep 3 DOF simultaneously,
into Finesse.
Seiji now writing scripts to explore the 3D space.
-
Facilities and vacuum envelope (Vass):
- Flavio and Ben are beginning to look at the STACIS controllers at the
40m. They are having a colorful array of problems, and we will
characterize them as we find them.
Ben has ordered another copy of the
control software that we can use to better understand the fault conditions.
- Steve has been ordering commissioning equipment
(scopes, sensor cards, camera cables, etc).
He sent back the metone particle counter for repair.
It has been reading zero on the South Annex flow bench,
but it was a lie. He checked with our other
(working) particle counter; it's 10-15, still quite low (but not 0).
- The turbopump and scroll pump that failed
during the last pumpdown has been repaired and returned.
-
South Annex Bake Ovens (Taylor):
- Bob has been on vacation for the last 2 weeks.
- Larry Jones needed some RGA scans for AdvLIGO SEI parts.
Steve ran some scans on coils, which failed.
Steve later discovered it was due to a blown fuse on the
heater strips on the bake oven.
He's now doing a magnet bake/scan for Larry.
Oct 31, 2003
- Commissioning (Miyakawa, Kawamura):
- Michelson, X-arm, Y-arm all locked (one at a time).
Using one LSC RFPD (at the asymmetric port),
Osamu, Seiji, Jay and Ben have succeeded in locking
these 3 degrees of freedom, one at a time, robustly.
The high-finesse arms typically take 20 seconds to acquire lock,
and have remained in lock for over an hour at a time.
-
They observed a strong oscillation at ~ 330 Hz, attributed to the
dewhitening filter.
They bypassed the hardware dewhitening filter and
the software compensation filter, in order to make it easier to lock.
They measured the OLTF, and designed appropriate filters
to achieve robust lock, with UGF around 300 Hz.
The violin resonances ar 451 Hz are seen, as well as
its first harmonic (approximate) at 880 Hz.
The AA filter also seems to produce an oscillation near the UGF,
presumably due to insufficient phase margin near the UGF.
- To lock the y arm, they used the same filters,
and only a sign flip in the gain (consistent with the
sign flip needed for damping - the magnets must be reversed
for ETMY compared with ETMX).
- They estimated the cavity reflectivity; it was ~ 50%.
Osamu refocused the retuning beam on the PD, and it went up
to 85%.
-
The 50% reflectivity implies that the loss per mirror
is 90 ppm instead of the 37 ppm design
(and a finesse of 1200 instead of 1270,
and a PRC gain of 6 instead of 14).
And indeed, a lot of dust cattering can be seen on all
mirror surfaces when viewed with an IR viewer through the viewport
(the ccd camerase are too saturated to see this).
We need to vent and clean each mirror.
- All of the above is with poor mode matching into the arms.
In order to tune the mode matching telescope,
Osamu is trying to maximize the arm transmitted light.
He saw large (5-10%) intensity fluctuations
in the arm transmitted light, which is likely due to
(a) aperture limits in the transmitted light beamline;
(b) angular fluctuations from the MC;
(c) real intensity fluctuations from the MC (~ 1-2%).
- He then re-commissioned the MC ASC (WFS) system
to stabilize the MC transmitted light.
He installed a control matrix to feed back onto MC2 and MC3,
and a simple feedback filter.
It now works very well, stabilizing the intensity fluctuations
in the ~ 1 Hz region quite effectively.
- Remaining MC transmitted light intensity fluctuations are all
at lower frequency, and Osamu has determined that they originate
in the PSL. MOPA or PMC? Under investigation.
- Meanwhile, Flavio will commission the ISS,
sensing the light transmitted through the MC,
which should fix the problem, whatever the source.
- The mode cleaner now locks quickly and robustly,
even in low noise mode (with dewhitening filter on),
now that Osamu has applied a limiter in the MCL feedback path.
- Osamu balanced the MC2 coil outputs in the digital filters,
so now the MC dewhitening (and software compensation)
can be turned on and off without disturbing the MC lock.
- Fumiko is in the process of aligning
the optical, photodetector, and electronics chains for
the POX and POY beams. After that: SP, POB, TRX, TRY.
- LSC Electronics (B. Abbott, Heefner, Taylor)
- Ben has
reverse engineered the Common Mode Servo board so that Todd could
reconcile the fully stuffed board that he had with the marked up schematics
and pictures given to him from LLO.
-
Ben then redrew the schematics for the
CM servo board, and made a test procedure for Todd. The new schematics are
going to be sent to Livingston for review.
- Ben
tested a spare CM servo board for Livingston using the new test procedure.
- Ben
made a milled prototype of the LSC PD tester board that could not be
used as the milled board had many shorts on it.
He has sent a board to PCB express, and will test that when it arrives.
- Ben checked the QPD wiring in the vertex, and concluded that it is all
there ready for the ASC auxillary code to come from Mohana, when we can
test the wiring using tester boards and actual QPDs.
Should happen in the next week.
- Ben ordered 50 Ohm SMA terminators for our frequency distribution box.
- Jay reports that ASC code from Rolf is in progress,
and will be a prototype for a new system at the sites.
- We have a long list of new signals (ISS, ASC QPDs, etc)
that need to go into master.config.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
-
Shihori continues to develop and document an iterative procedure to
better diagonalize the input matrix, to distinguish
POS/PIT/YAW.
She has improved the ITMX input matrix,
and is now applying the procedure to ITMY.
-
Optical levers (Kawazoe, Heefner, Abbott):
- Fumiko has taken oplev response calibration data
and is analyzing it.
She will work with Jay to
begin to commission the oplev servos.
- Optical sensing (Smith):
-
All parts for optical sensing are in hand except for one
67% BS, on back order.
-
We have finally received
one last q-switch E/O shutter from Fast Pulse which we have been
waiting for for at least 6 months.
- Ben ordered some cable connectors for the EO shutters that should be
in next week.
- We have heard that the sites are moving away from the EO shutters,
and switching to fast mechanical shutters and simpler methods
for limiting the power to the photodiodes.
Our MC EO shutter works well; we wonder why these changes are necessary,
or desirable at the 40m, where time constants are shorter than at
the sites.
- Steve ordered power supplies and cables for the
ccd cameras that view the sensing beams.
- Computing:
- Alex Ivanov plans to commission one of our
new Sun Ultra E450's to run GDS software
(dtt, dmt, dataviewer).
- Modeling (Miyakawa, Kawamura):
- Seiji is continuing to study error signals
with Finesse while sweeping through (l+,l-,ls) space.
He is finding it difficult to use matlab to do this
by interfacing with Finesse. Hiro suggests
modifying Finesse instead; Seiji is trying to contact
Andreas Freise.
-
Facilities and vacuum envelope (Vass):
- Ben and Flavio are diagnosing the staus of our STACIS system.
- Steve is straightening up the lab and
reducing earthquake hazards
(like using the shelf above the PSL table to store spare optics).
Oct 24, 2003
-
An informal review of the
40 Meter experimental plan,
scope, staffing and budget
was conducted on Tuesday
(Shoemaker, Wilkinson, Strain, Fritschel,
Weinstein, Miyakawa, Kawamura, Vass).
Minutes.
- Commissioning (Miyakawa, Kawamura):
- Michelson locked.
The Length sensing and control (LSC) system wiring & cabling
is just about done, and Rolf and Alex installed new software
on Wednesday afternoon.
Within a couple of hours, Osamu, Seiji, Jay and Ben
used the LSC system to lock the Michelson (after blocking the ETMs).
They then used DTT to take a transfer function,
hastily designed some filters with FOTON,
and made the lock robust.
- The Michelson contrast is better than 99.8%.
However, the beam is not well mode-matched into
the IFO (the MMT was set for the case where the PRM is in place,
which it isn't).
So, the beam is significantly larger than it should be,
making it easier to obtain high contrast.
- They are now working on locking the x arm,
using the AP sensing train.
- We still need to commission the optical,
photodetector, and electronics chains for
the SP, POX, POY, POB, TRX, TRY;
but almost all the parts are in.
- We continue to see the alignment of the
input beam (after the mode cleaner but before the ifo)
changing significantly, from time to time, usually
overnight. The QPD monitoring of the beam alignment
is still not yet in place, but we're working on it.
We continue to suspect that the problem is with
the PZT steering mirrors
(after the mode cleaner but before the ifo)
which were never fully checked out before installation,
since they were the last item to arrive.
The beam is now nicely aligned, and is centered on the PZT1
mirror, but still off to one side of the PZT2 mirror.
- Anyway, Osamu and Seiji re-aligned the input beam
with the PZTs. They had to tweak the beam launch
at the PSL table to eliminate some clipping
that they saw on both the SP and AP beams;
likely, this clipping is at the Faraday isolator.
- Osamu noted that the resonant frequency of the MC,
33.207 MHz, changed by 60 Hz from day to night.
He also notes that there's some excess noise
in the detection of the 33 MHz signal transmitted
from the MC. To be investigated.
- Osamu continues to commission the mode cleaner
wavefront sensors. He sees good error signals,
but needs to calibrate the control matrix between
WFS1/WFS2 and the MC mirrors. In progress.
- The MC transmitted intensity fluctuations
are at the 1% level, good enough for
Flavio to commission the PSL ISS.
- LSC Electronics (B. Abbott, Heefner, Taylor)
- From Rolf:
Modified the LSC software to run the 40m lab system; code installed today.
- From Jay:
The LSC software and 90% of the electronics are now installed and
operational. As a test of the system we locked the Michelson. In the
process of locking the mich. we found several signals and test points
that were not available to DAQ or DTT. These will be corrected.
- Osamu and Ben
checked the four RF PD heads (for AP1, SP, POX, POY)
and all seemed to be functioning fine.
- Ben installed the refurbished PZT mirror driver in its slot,
and Osamu and Seiji aligned the beam using all four controls
(PZT1X, 1Y, 2X, 2Y).
- Ben mailed off two RAID disks to get replaced. One of these was already
sent to us as a replacement. This is the only replacement that has gone
bad so far, and it has been in place for over a year.
- Ben is in the process of laying out an LSC PD tester board that will help
in debugging LSC PD and wiring problems.
- Ben was was having problems with the
enable/disable on the LSC PD screens. He
traced the problem to the LSC PD interface, where the logic chips had been
damaged due to a bad cable. He fixed the bad chips, and one damaged PD head.
This sort of problem can be averted in the
future using the tester board that he is laying out.
- Bob and Art continue to wire and cable up the
LSC and ASC racks. The cabling for the vertex QPDs are going in now.
Cabling for the electro-optic shutters are next.
- Ben got 2 more Kepco power supplies for the ASC rack DC power.
- We have a long list of new signals (ISS, ASC QPDs, etc)
that need to go into master.config.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
-
Shihori is developing an iterative procedure to
better diagonalize the input matrix, to distinguish
POS/PIT/YAW.
She has improved the ITMX input matrix,
reducing the POS motion in the PIT channel
by a factor of more than 10.
- As we commission the IFO, we really need to
better diagonalize the input and output matrices
for all 10 optics. In progress, progressing slowly.
- PSL (Miyakawa, Kawamura, Abbott, Nocera):
- Osamu has final results on the improvement in the PSL
frequency noise (as measured by the MC)
due to (a) reducing the number of folding mirrors
on the PSL table from 6 to 3
(several large peaks between 300 and 800 Hz have disappeared),
and (b) moving the FSS pickoff to after the PMC
(much improved noise spectrum in 1 kHz to 10 kHz region).
These two changes helped a lot, and make it possible
to run with low noise even when the HEPA filters
in the PSL enclosure are on.
- The intensity fluctuations in the MC transmitted beam
have been reduced to ~ 1%.
Flavio can resume commissioning of the ISS servo.
-
Optical levers (Kawazoe, Heefner, Abbott):
- Ben has changed the resistors on all the
oplev QPD preamps from 10K to 100K.
They are now all back in place and reading out
the oplev beam positions.
- Fumiko still needs to center the beams, zero the response
when the beam is blocked, re-measure the response,
characterize the pitch/yaw motion of all the monitored optics,
and begin to commission the oplev servos.
- Optical sensing (Smith):
-
PZT1 STEERING MIRROR:
PZT1 pitch amplifier was received from Piezojena
and is now re-installed.
-
QPD MOUNTS:
Mounts were received, and QPDs are mounted on all sensing trains
(not yet aligned).
-
POX and POY:
40%, 50%, and 67% BS are on back order.
-
INITIAL POINTING:
The mount for the 10 X telescope initial pointing ANG beam is being fabricated.
- Computing:
- We look forward to Lisa and Larry setting up our two new
"cast-off" Sun Ultra E450's, which we desperately need
for commissioning. Our Blade 100's are "dogs":
a typical dataviewer display lags by 20 seconds;
dtt only runs (verrry slowly) one one computer).
- Modeling (Miyakawa, Kawamura):
- Seiji is working on interfacing Finesse with Matlab
to facilitate exploring lock acquisition strategies.
-
South Annex Bake Ovens (Taylor):
- Bob continues to spend most of his time cabling the LSC/ASC racks.
-
Facilities and vacuum envelope (Vass):
- Steve is back from vacation and checked out the vacuum system;
all seems fine.
- Steve is working on the documentation of the last pump-down.
Oct 17, 2003
- Commissioning (Miyakawa, Kawamura):
- Osamu and Seiji measured the 33 MHz sidebands
being transmitted through the mode cleaner.
The new measurement yields 33.194871 MHz (L_MC = 13.547 m).
This is a change of 50 Hz from last year,
and 162 Hz from 3 months ago (before the vent).
- Does a change that large require one to
re-tune the transmission frequency, in order to
avoid excess noise?
To evaluate this, they measured the noise spectrum
of the demodulated signal from the transmitted beam,
and compared it with a noise spectrum taken with the
frequency deliberately mis-tuned by some amount.
They found that the frequency had to be off by more than
500 Hz before any excess noise was noticed.
- The MC is now being operated in low-noise mode.
If lock is lost, it does not re-aquire easily in
low-noise mode; the gains need to be turned down and the
dewhitening filter on MCL needs to be turned off
for robust lock acquisition.
We need to automate this procedure with ezca.
- Osamu and Seiji have been searching for the source
of a ~ 5% intensity fluctuation in both the MCR
and MCT beams, which made it impossible to commission
the PSL intensity servo.
The MCR beam was drifting at the RFPD, causing clipping.
They introduced a lens to make the beam size smaller.
They traced the beam wander to an oscillation in the
MC suspension controller damping, associated with a
Cheb filter. Turning off these filters on all 3 MC optics
reduced the transmitted beam intensity fluctuations from
~5% to 1.2%. This should be enough to commission the ISS.
- Meanwhile, they will begin to re-commision the MC WFS system.
- LSC Electronics (B. Abbott, Heefner, Taylor)
- Ben and Jay have
completed the checkout of the LSC auxiliary controls database,
operator screens and wiring. They are now ready for operation.
- They are now checking out the
front end controls, and found a variety of problems
with the signal mapping,
mainly because the 40m has different RFPD wiring than the sites.
They will go over this
with Rolf on Monday to settle on the required changes
to the software and/or wiring, and screens.
- Ben fixed the three LSC Whitening boards so that they incorporate
the fixes in Flavio's DCN #E030506.
- Todd fixed the two blown LSC PD interface boards
and they are now back in the rack and are no longer blowing up.
- Ben and Art have almost completely finished the
wiring and cabling for the LSC part of the new racks.
They have run long cables to the four LSC RFPDs and five ASC QPDs.
Ben and Osamu will begin plugging them in (including the three
ASC QPDs at the ends) and verify signals, using light from the PSL
flashing in the main IFO.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Ben has balanced the electronic offsets on the MC2 coil dewhite board,
but it didn't cure problems associated with
switching from mode cleaner
lock acquisition mode (dewhitening turned off to increase dynamic
range at the expense of noise, to make lock acquisition robust)
to low noise mode.
Osamu will try to fix this by balancing the gains in the
digital dewhite compensation filter.
- ETMX is not damping at nominal gain (ever since tuesday 8pm);
don't know why. But it's damping ok at 5 times nominal gain.
Ben and Jay will investigate.
- Shihori looked at the
couplings between POS, PIT, and YAW in ITMX,
*after* input matrix diagonalizing.
There's still plenty of cross-coupling in the sensing input matrix;
the diagonalizing procedure needs refinement.
She will look at the other 7 optics, next.
- PSL:
- Osamu noticed that the PSL beam steering into the
frequency reference cavity was not optimal; he will tune it.
- The intensity fluctuations in the MC transmitted beam
have been reduced by a factor 4.
Flavio can resume commissioning of the ISS servo.
- Rolf has a list of all the ISS DAQ channels,
and will need to modify the code running in the c1iovme processor
to read them in and make them available to DAQ, etc.
- Mike has the info he needs to update the PSL table layout
with the locations of the ISS photodiodes.
-
Optical levers (Kawazoe, Heefner, Abbott):
- Ben re-fixed the Oplev photodiodes.
What he thought was a regularly
unlabeled 2.2nF capacitor (as it was found in a drawer labelling it as
such), turned out to be an unusually un-labled 1K resistor. This made the
Oplevs act crazy, and Jay discovered the part was to blame. It has now
been finally fixed.
- Fumiko continues work on centering the oplev beams on the QPDs
and zeroing the offsets.
She's also continuing work on characterizing the
calibrated angular motion spectra, and system noise.
- Optical sensing (Smith):
-
PZT1 STEERING MIRROR:
PZT1 pitch amplifier was received from Piezojena.
-
QPD MOUNTS:
Mounts were received.
-
POX and POY:
An ACAD optical layout for the POX and POY beams was completed. The design
of the focusing lenses for the QPD, video camera, LSC, WFS, and power meter
paths were completed and an updated parts list was generated. Additional
required parts were ordered.
-
INITIAL POINTING:
The mount for the 10 X telescope initial pointing ANG beam is being
fabricated.
- Computing:
- We have acquired two "cast-off" Sun Ultra E450's
from Stuart Anderson.
These will replace our very underpowered Blade 100 online computers,
and hopefully reduce the problems we are having with
DTT, dataviewer, and medm.
Lisa and Larry will get the machines up and running
at the 40m, soon.
- Modeling (Miyakawa, Kawamura):
-
South Annex Bake Ovens (Taylor):
- Bob continues to spend most of his time cabling the LSC/ASC racks.
Oct 10, 2003
- Commissioning (Miyakawa, Kawamura):
- Osamu and Seiji re-measured the PSL frequency noise using
the mode cleaner, and the new procedure outlined in
T030239.pdf.
After some time trying to reconcile a difference
in normalization between the old procedure and the new,
they determined that the new procedure is more reliable,
and the old method had a couple of mistakes in the normalization;
the old noise curves were underestimated by a factor of around 2.8.
With the new normalization, the frequency noise still meets
specs above 50 Hz, except for a set of acoustic spikes
in the 200-1000 Hz range;
the re-layout of the PSL (reducing the number of folding mirrors
and placing the FSS pickoff after the PMC)
has improved things considerably areound 800 Hz and above 1 kHz.
The noise around 100Hz is lower due to the
dewhitening filter in the MC2 suspension controller.
The peak at 180 Hz noticed last week is now gone.
- Osamu and Seiji used the transmission of the 33.2MHz
sidebands to re-measure the length of the MC,
and found it had changed by 5 Hz (out of 33.2MHz)
during the vent; ie, not at all.
They also find that the detection of the 33.2MHz sidebands
is shot-noise limited, even if the MC length varies
by the equivalent of 40 Hz.
- Osamu and Seiji are now working to understand the origin of
the large (as much as 8%) intensity variation in the MC
transmitted beam. The PSL intensity servo cannot be
commissioned until this anomalous intensity variation
is eliminated.
- LSC Electronics (B. Abbott, Heefner, Taylor)
- Mohana installed the LSC auxiliary controls target code
(c1iscaux),
operator screens and databases.
The lsc aux database has been loaded on the processor and everything
appears to be OK.
The XY212, VMIC 3113A and VMIC 4116s addresses were set.
Jay and Ben checked
all auxilary controls for the LSC system, and they are operational.
-
The next step will be to inject signals into the LSC front end
ADCs and propogate them through the code. If all goes well and all field
cabling is completed, the system should be ready operation by the end of
next week.
- In the process of checking out the LSC analog boards
through the auxiliary controls,
Ben smoked two LSC PD Interface boards.
The problem was found to be a bad cable on the XY212
that was connected to both boards.
Replacements are being obtained from Todd.
- The processor for the LSC front end was replaced
and the system appears to be a bit more stable,
but still crashes every once in a while.
- Ben moved the PZT Drivers to 1X3 to get them away from the analog crate
where they were originally placed.
- Bob and Art continue to work on
cross connect and internal rack cabling
for the LSC and ASC, as well as the cables to the photodetectors.
They can get 5000 ft folls of SpectraStrip
multi-conductor twisted-pair cable, for the long runs.
They are making great progress.
- Bob and Art powered up the LSC/ASC analog rack (1X2)
with the Kepco linear power supplies, and discovered that the
WFS demod boards are power hogs.
We'll need to buy more power supplies to keep those boards happy,
but we won't need them for a while.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Ben has balanced the electronic offsets on the MC2 coil dewhite board.
So, switching from mode cleaner
lock acquisition mode (dewhitening turned off to increase dynamic
range at the expense of noise, to make lock acquisition robust)
to low noise mode will not disturb the optic.
- Jay and Ben have checked out all the whitening / dewhitening
switches on the XYCOM screens
for all the suspension controllers.
Finally, they all work as they should.
- Ben redrew the schematics for the end station wiring to reflect recent
changes to the layout. They are now a current representation of the
as-built condition.
- Shihori continues to make DTT spectra of all the core optics
OSEM sensors, to find and diagnose problems.
Most of the problems she is encountering are in DTT!
- Lisa and Shirori (with help from Ben)
re-did the input sensing matrix
for the MC optics, in an attempt to fix the
intensity variation problem in the MC transmitted beam.
But, it didn't help.
Now she's re-doing the output coil matrix for MC2.
Lisa is documenting the diagonalization procedure
that we have been using.
- PSL:
- Flavio cannot commission the ISS servo until the
large intensity fluctuation mentioned above is fixed.
-
Meanwhile, he finished installing all the permanent cables
and DAQ channels.
- Rolf has a list of all the ISS DAQ channels,
and will need to modify the code running in the c1iovme processor
to read them in and make them available to DAQ, etc.
- Mike has the info he needs to update the PSL table layout
with the locations of the ISS photodiodes.
-
Optical levers (Kawazoe, Heefner, Abbott):
- Jay used DTT to measure the
transfer function from The OLYAW_EXC input to the OLYAW_IN1 TP for
ETMY. The transfer function was as expected, flat to a peak at ~0.6Hz
and then falling as f^-2. Foton was then used to generate filters for
a DC coupled OL servo. The servo was engaged and appears to work. The
same filters were installed on PIT and the optic damped in PIT and YAW
using only the optical levers. The filters used had poles at 0.1, 100,
100 and zeros at 0.5, 0.5.
- Fumiko continues to refine her calibration of all the oplev QPDs in
terms of angular displacement of the optic, in radians.
She is now working on getting calibrated angular motion spectra,
and comparing with the detector system noise
and dynamic range.
- Ben increased the gain in the Oplev photodiodes by a factor of 10 as is
called for on Note 2 on its schematics.
- Optical sensing (Smith):
-
PZT1 STEERING MIRROR:
Awaiting repair by Piezojena of the PZT1 pitch amplifier.
- ELECTROOPTIC SHUTTER:
Awaiting delivery of 3rd EOS.
-
QPD MOUNTS:
Awaiting delivery of mounts.
-
POX and POY:
A preliminary ACAD optical layout for the POX and POY beams was completed.
The design of the focussing lenses for the QPD, video camera, LSC, WFS, and
power meter paths is in process. The final choice of lenses will require a
slight change of the path lengths and component locations.
-
INITIAL POINTING:
A mount for the 10 X telescope in the initial pointing ANG beam was
designed; working drawings were completed and will be released to the DCC.
- Mike is updating the ACad drawing with the as-modified PSL table.
- Computing:
- We continue to have lots of problems with DTT.
It only runs on one computer (op140m),
but not on op240m or dmt140m.
With Peter Shawhan's help, we suspect that the problem
is with the way op140m NFS-mounts the disk that has the DTT executable
libraries.
- Even on op140m, it often freezes,
gets out of synch with the data, or fails to
access test points.
Alex Ivanov is trying to figure it out,
and in the meantime, showed us how to
release and set test points manually.
- Alex also changed the GPS
IRIG B slave in the AWG, which helped with the synch problems.
- Meanwhile, it is clear that our online computers,
which are Blade 100's, are not up to the task of
running DTT, Dataviewer, many copies of medm, etc.
We are trying to get one or two surplus Sun 450's
to replace these machines.
- Modeling (Miyakawa, Kawamura):
- Seiji continues to use his Finesse model of the 40m
to study lock acquisition.
He tried to use the scheme employed at the Garching 30m,
using non-resonant sidebands to robustly lock the PRC (l+).
He found, again, that the desired locking point has much
sensitivity to the position of the
SRM and Michelson degrees of freedom (ls and l-).
However, it may be possible to lock l+, and keep it locked
while acquiring lock on ls and l- in a second step.
He is investigating.
-
South Annex Bake Ovens (Taylor):
- Bob continues to keep an eye on the 40m vacuum system
while Steve is on vacation.
- Bob continues to spend most of his time cabling the LSC/ASC racks.
Oct 3, 2003
- Commissioning (Miyakawa, Kawamura):
- Osamu and Seiji measured the PSL frequency noise using
the mode cleaner. The raw error signal spectrum looks
as good or better than we have ever achieved before,
at all frequencies ... except for a new peak at 180 Hz.
- The MC2 coil dewhitening filters make it hard to acquire lock
robustly, but are necessary to achieve low noise operation
of the MC. Switching the dewhitening filters on after acquiring
lock will kick the MC out of lock due to offsets that are
believed to be in the dewhitening board.
Ben is re-balancing these offsets now.
- Osamu and Seiji see an offset in the MC error signal after locking,
always in the same direction. Its origin is not understood.
- The MC transmitted beam
is experiencing significant (~ 1%) intensity fluctuations
at ~ 1 Hz. Osamu believes that it is due to wobbling mirrors.
Lisa Goggin is re-doing the diagonalization of the
input sensing matrices for all 3 MC mirrors, to address this problem.
- They are now measuring the noise using the feedback signal,
and using a measured transfer function to express it as PSL
frequency noise
(see writeup by Seiji,
T030239.pdf).
The shape agrees with the method using the error signal,
but the normalization is off by a factor around 8;
they are trying to understand this.
- LSC Electronics (B. Abbott, Heefner, Taylor)
- All the boards needed for our LSC system are now in.
We're still waiting for filter modules for the AA boards.
- Bob and Art are wiring up all the cables, and running power
from Kepco linear power supplies in a satellite rack.
They have all of the multi-connector cable they need.
They're making great progress, but it's still
days of work to completion.
- Rolf, Alex, and Jay are installing the LSC
front end cpu, reflective memory, software,
epics screens, etc. They ran into some timing snags,
and are working on it.
- Mohana is almost ready to install the LSC auxilliary
crate software and database. Hopefully, by the end of the week.
Then, Ben can test out all the controls with tester boards.
-
Ben has modified the GPS clock driver board for the LSC crate
per Flavio's DCN.
He'll do the other clock driver boards as time permits.
- Ben and Jay diagnosed a problem with the MC servo board;
the ADC on the board which decodes the gain slider settings
was latched up (a problem which is known at the sites).
To reset it, must pull out the board, count to 30, put it back in.
- Jay continues to develop the design for
LSC double-demod boards.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Shihori continues to make DTT spectra of all the core optics
OSEM sensors, to find and diagnose problems.
The test masses all seem to damp the pendulum resonances well,
but some of the optics are noisy at higher frequencies,
presumably due to wrong dewhitening filtering.
-
Ben and Jay are working to make sure all the XYCOM switches
are set up right for the dewhitening filters
for all the DSCs.
- Ben replaced a whitening board for MC2 whose connections were flaky.
Todd has the old one, and will analyze it in his spare time.
- The ETMX UR sensor is not reading out right.
Ben discovered that the satellite amplifier was not putting
out enough current to the LED:
the added resistors that boost the LED drive
current for one of the optics were not properly soldered on one side, and
therefore, that OSEM was dimmer than the others. This caused the OSEM to
be misaligned during the process of balancing the OSEMS, and it means that
it must be adjusted the next time we vent.
- Shihori would like to determine the coil
output matrix for all optics. This is most easily done by
exciting the optic test points with DTT.
However, DTT doesn't work most of the time;
there's some weird timing problem.
Alex Ivanov will try to figure it out.
- Lisa and Shirori will re-do the input sensing matrix
for the MC optics, in an attempt to fix the
intensity variation problem in the MC transmitted beam.
Lisa is documenting the diagonalization procedure
that we have been using.
- PSL:
- Flavio cannot commission the ISS servo until the
large intensity fluctuation mentioned above is fixed.
-
Meanwhile, he will finish installing all the permanent cables
and DAQ channels.
-
Optical levers (Kawazoe):
- Fumiko has calibrated all the oplev QPDs in
terms of angular displacement of the optic, in radians.
She is now working on getting calibrated angular motion spectra,
and comparing with the detector system noise
and dynamic range.
- Jay is installing digital filters in the oplev servo system,
in preparation for turning the servos on.
- However, there is a strange offset in the oplev servo system.
Jay will ask Rolf to look at it when he gets a chance.
- Ben will change the resistors on the BS and ITMY oplev QPDs;
the signal on these QPDs is very weak.
- Optical sensing (Smith):
-
PZT1 STEERING MIRROR:
Awaiting repair by Piezojena of the PZT1 pitch amplifier.
-
QPD MOUNTS:
Awaiting delivery of mounts.
-
INITIAL POINTING SENSORS:
The optical system was designed and a parts list was created for the
initial pointing position and initial pointing angle sensing system. There
is negligible cross-coupling between the position and angle sensing
measurements. The 40 m optical table ACAD drawing was updated. A purchase
req was generated to purchase the components.
-
ETM TRANSMISSION SENSING:
The optical system was designed and a parts list was created for the ETM
transmission sensing systems (TRX and TRY).
The 40 m optical table ACAD drawing was
updated. A purchase req was generated to purchase the components.
- Mike is drawing up the temporary layout of the POX/POY sensing
beamlines, for independent arm locking.
- Mike is updating the ACad drawing with the as-modified PSL table.
- Modeling (Miyakawa, Kawamura):
- Seiji continues to use his Finesse model of the 40m
to study lock acquisition.
- Osamu continues to come back up to speed with E2E/Alfi.
-
South Annex Bake Ovens (Taylor):
- Bob sent the TP2 turbo pump and scroll pump back for repair;
the spares are performing well.
- Bob is doing some solder joints for Helena,
and an inventory of OSEM boards for Janeen.
Sep 26, 2003
- Commissioning (Miyakawa, Kawamura):
- As reported last week, we have PSL light through the mode cleaner
the input optics, and the main IFO.
The MC is locked, and we see Michelson fringes at AP and SP,
and Fabry-Perot flashes in both arms.
- Our current big effort is to wire up the LSC rack
and set up and align all the sensing beamlines.
- In preparation for this, Osamu and Seiji are
tuning up the PSL and mode cleaner.
- They optimized the gains of the PSL PMC and FSS servos.
- They then turned to the mode cleaner,
to measure the frequency noise and compare it to
what we had before the vent and the re-layout of the PSL path.
They adjusted the EOS to put more light on the MCR RFPD,
to minimize the noise.
-
They then measured the noise in the MCR VCO feeback signal
and compared it with pre-vent version.
In almost the entire frequency range, it is as good or better
than before.
AND, they took the measurement with the PSL enclosure HEPA filter *on*.
Previously, noise was *much* worse with the HEPA filter on;
now, noise with HEPA on is as good or better as pre-vent noise
with HEPA off!
- Many peaks in the 300-1000 Hz region, which were
due to PMC and mirror vibrations downstream of the old FSS pickoff
are gone, now that the FSS pickoff is after the PMC.
Mysterious peaks at 25, 32, and 50 Hz are now gone.
- The region from 120-500 Hz was worse than before.
Osamu traced it to the absence of dewhitening on MC2.
When Jay fixed this, the excess noise in that region went away.
The noise spectrum is now better than before at all frequencies.
- The re-layout of the PSL required re-optimization of the
mode matching into the MC. Osamu and Seiji measured the visibility of the MC
to be 75%; should be > 95%. They used a translation stage
to fix the mode matching; visibility is now around 98%.
- They will now re-establish the transmitted sidebands
and re-measure the MC length.
- Installation (Vass, Miyakawa, Smith, everyone):
- Steve and Bob covered up all vacuum viewports.
- We need one more camera mount for viewing the BS optic.
Larry Jones ordered two more camera mounts.
And, Bob will put extensions on existing camera mounts
for cameras with long lenses.
- Electronics (B. Abbott, Heefner, Taylor)
-
The LSC rack is the focus of much attention.
Most of the modules are in place, all of the cross-connection wiring
is done.
Art, Bob, and Ben are beginning the cabling of modules
to cross-connects.
Ben is ready with tester boards.
- Unfortunately, we *don't* have enough multi-conductor
cable for the runs from optical table to rack!
Bob, Jay, and Ben are scrambling to get suppliers.
- Ben installed all of the components needed for the LSC part of the
LSC AUX crate (c1lscaux).
It is now ready for Mohana to install code, databases, screens.
- Rolf is working on the front end LSC code.
The electronics and software are all just about ready.
- Ben will make mods to the GPS clock drivers.
- Lisa sent back the PC projector for repair under warrantee.
- Digital suspension controllers (Sakata, Goggin, B. Abbott, Heefner)
- Shihori made DTT spectra of all the core optics
OSEM sensors, with and without damping on.
Three sensor channels looked dead.
Ben traced it to the LEMO cables from the whitening boards,
and replaced them; this fixed those problems.
It's clear from the spectra that work is required
to optimize the damping of the test mass optics.
- One OSEM still looks like its not working right:
ETMX UR. Ben will check the satellite amplifier.
- Lisa G and Shihori used Mark Barton's method
to diagonalize the input matrices for the 5 new core optics.
The numbers are all within 25% of 1, and are reproducible
from three separate trials.
The numbers are now in the screens, and damping works fine.
They are now working on the output matrix, using DTT to excite position
and watching dataviewer to decouple position, pitch & yaw.
They will use DTT to study the couplings of pos,pit,yaw
as a function of frequency across the pendulum resonances.
- PSL:
- Osamu and Seiji re-optimized the PMC and FSS gains,
now that the FSS pickoff is after the PMC.
- Ben made up and tested two ISS PD boxes and three PD heads.
- Flavio and Ben installed the ISS PDs and electronics in the 40m.
The installation is almost done; they need some longer cables
for permanent routing.
The EPICS crate, database and screens seem to be working.
The commissioning of the servo will begin soon.
-
Optical levers (Kawazoe):
- Fumiko has zeroed the offsets on all oplev quadrants.
- Fumiko has re-checked her calibration of the oplev response
of the 5 IFO optics. She will express it in terms of radians at the optic.
She's measuring the optic motion (with damping on and off),
as well as detection noise,
and comparing it to the region of sensing linearity.
- Next, she will obtain the oplev digital servo filter design
used at the sites, implement it here, and commission the oplev servos.
- Ben will change the resistors on the BS and ITMX oplev QPDs.
- Optical sensing (Smith):
-
PZT1 STEERING MIRROR:
Awaiting repair by Piezojena of the PZT1 pitch amplifier.
-
QPD MOUNTS:
The QPD boxes were modified and mounted to the rigid electrically isolated
table mounts; 2 sets of mounts were missing. Replacement mounts will be
ordered.
- Fumiko is beginning to assemble electro-optic shutters
for the SP and AP beamlines.
We still await one more EOS Q-switch.
- Mike is drawing up the temporary layout of the POX/POY sensing
beamlines, for independent arm locking.
- Mike is updating the ACad drawing with the as-modified PSL table.
- Modeling (Miyakawa, Kawamura):
- Seiji is using a Finesse model of the 40m
to study lock acquisition.
He is studying how the error signals for each of
the short length degrees of freedom (PRC/l+, Michelson/l-, SRC/ls)
change when other degrees of freedom change
(ignoring the arms, for now).
He finds that in some cases, there is no decent error signal
unless the other degrees of freedom are very close
to their in-lock positions.
This will make locking the full DRM hard ... as expected.
He's thinking about ways to make it work.
- Osamu continues to come back up to speed with E2E/Alfi.
-
South Annex Bake Ovens (Taylor):
- While Steve is on vacation (4 weeks!),
Bob is doing all of Steve's daily duties:
checking the vacuum system and controls, N2 level for the vacuum valves,
ion pump V's and I's, and PSL chiller level.
- Bob is doing some bake jobs for Larry Jones.
- Bob is working with Caltech electricians to fix the AC
to the flow benches.
Sep 19, 2003
- Commissioning (Miyakawa, Kawamura):
Osamu and Seiji have re-established the alignment of all suspended
optics (no recycling mirrors) in the 40m after pumpdown.
We have Michelson fringes at the SP and AP ports,
and Fabry-Perot fringes on the X and Y arms!
- Installation (Vass, Miyakawa, Smith, everyone):
- Installation, alignment, and full checkout of the IO and main IFO was completed
last Wednesday. Steve et all secured all chamber doors and access connectors.
- The only known problem is that the driver amp for in-vac PZT2-pitch
is broken; Mike has sent it back to Piezojena for repair under warranty.
- Pumpdown began last Thursday at 9am.
TP2 failed! Bearings need replacement.
And, and its backing scroll-pump
is not pumping up to spec.
Fortunately, Steve has replacements for both.
They were replaced within an hour,
and pump-down recommenced.
It all proceeded smoothly,
and a week later, all looks ok; no sign of any leaks or failures.
- Steve turned on the cryopump on Monday.
RGA scan sees the usual dominance of H2O, with little evidence
of hydrocarbon contamination.
By this Thursday, CC1 was reading ~ 1e-6 torr.
Steve turned off the cryopump this Thursday AM,
and the pressure went up to ~1e-5 torr.
Steve will leave only TP1, TP2, and TP3 running during the
4 weeks that he's away on vacation.
- During pumpdown roughing, we observe the
OSEMs on all suspended optics moving; and oplevs on core optics.
They didn't all go back to where they were before pump-down, not sure why.
-
And sure enough, Osamu and Seiji find that they have to completely re-align
MC1,MC2,MC3 and the initial launch beam from the PSL,
in order to get everything back.
First attempt to align the MC to the incoming PSL beam
produced a MCT beam which was ~ 1 cm away from the Faraday isolator aperture.
This suggests that the initial launch beam from the PSL has moved;
presumably, the fixed folding mirror from the PSL to MC1 has moved;
not sure how or why.
- Osamu and Seiji have now re-aligned the MC to the FI,
and the PSL input beam to the MC.
- They went on and established Michelson fringes by aligning ITMX and ITMY.
Then, aligning ETMX, they saw Fabry-Perot fringes on our high-finesse arms.
- Meanwhile, Steve will install all remaining beam tubes
and viewport covers before he leaves.
- Electronics (B. Abbott, Heefner, Taylor)
-
The LSC front end crate is now installed and ready for Rolf to install
code. The fiber, timing, and ethernet cables are in.
- From Rolf:
Modified the LSC code to run on the CIT 40m system. Main change was to move
DAQ from the VME DAQ network card (used at the sites) to the new PCI network
card used in the 40m system.
Making use of the PCI card DMA engine, able to move
data onto the DAQ network at ~120MByte/sec.
-
Mohana is working on generating database records and screens
for the ISC aux crate (c1iscaux) up and running.
- Ben has completed the latest version of the inventory needed for LSC
completion. This list includes cables and approximate lengths so that
cables can be ordered in good time. Everything else seems to be coming
along fine, and all of the LSC should be ready to go the first full week in
October.
- Bob and Ben will begin LSC wiring with the cables that we have here, and
continue as more cable arrives from the vendors.
- Bob and Ben will set up the Kepco power supplies for the ISC
analog rack. These power supplies will live in a small rack nearby;
no power supplies, or AC of any kind, in the analog rack!
- Ben brought over 8 QPDs and 4RFPDs to the 40m yesterday. They need
mounting hardware to be supplied by Mike Smith, then they can be placed on
the tables, ready for use.
- Flavio is releasing a DCN for the GPS Clock Driver boards that will
necessitate a bit of work to the boards that Ben will do when time and
ongoing work permit.
- Jay is beginning the design of a double-demod board for
40m/AdvLIGO LSC.
- Jay has been cleaning up and re-arranging the target directories and
startup files for the 40 meter processors.
- The DAQS controller c1daqsctrl has synch-faulted several times
in the last few days. It's now clear that this is due to
Shirori's attempts to use DTT to plot noise spectra
for 40 OSEM sensor test points.
Rolf suggested that she instead use the regular sensor channels (2048),
not the 16K test point channels. This seems to work;
she can take 40 spectra simultaneously, without a synch fault.
- Shihori's work is paying off: we found one disconneced OSEM
(MC2 UL; it appears to have lost its signal after the pump-down.
Jay reseated the cable, it's now working fine).
Shihori will next take spectra with the damping off.
- Lisa G and Shihori are continuing to learn how to diagonalize
the IFO suspensions. First attempt didn't work; they will
talk with Stan about how it was done at the sites.
- Flavio is looking at our STACIS system, and assessing
the problems. It looks like at least one controller is bad,
and maybe also one isolator.
- Ben is now familiar with the LLO common mode servo board,
which will be helpful when we go to implement ours.
- The PC projector that displays our beam spots on the wall
has died. Lisa is sending it back for repair under warrantee.
- PSL is performing well.
Osamu plans to re-optimize all the servos,
and measure the frequency noise with the MC.
Flavio intends to install the ISS next week.
-
Optical levers (Kawazoe, Mow-Lowry):
- Fumiko has calibrated the oplev response
of the 5 IFO optics.
She has shifted the QPDs to center the signal;
but she'll have to do it again after Osamu and Seiji finish
their alignment.
- Ben will replace the resistors on the BS and ITMY oplev QPDs
from 10K to 100K, to increase the gain on their oplev readout.
- Fumiko will zero the offsets on all oplev quadrants.
- Nergis educated us on the oplev servo compensation filters
used at the sites; we'll try to get ahold of them.
- Modeling (Miyakawa, Kawamura, Eichenfield):
- Seiji is using a Finesse model of the 40m
to study the length sensing matrix.
He is refining the procedure for establishing the demod phases
for double-demod of the Michelson signal.
He's now beginning to think about establishing
a lock acquisition procedure.
- Osamu has been trying to run E2E/Alfi.
-
South Annex Bake Ovens (Taylor):
- Bob needs to upgrade the clean bake oven E;
2 heating elements went bad, causing some of the insulation
to burn. He plans to replace the heating elements, insulation,
and put on a new, better, heater controller.
- We have no OSEM spares; Bob will build a set
of SOS and MOS OSEMs.
- Bob is still working on a batch of baffles for LHO.
- Bob plans to completely clean up and re-organize
the south annex clean room. This includes fixing the AC
to the flow benches; right now, if we try to run both
flow benches, the breaker trips.
Sep 12, 2003
- Installation (Vass, Miyakawa, Smith, everyone):
- All in-vacuum installation is complete.
-
All components have been aligned: the suspended optics;
input optics (mode cleaner, faraday isolator,
MMT, PZT steering mirrors); all output beams (SP, AP, POX, POY, TRX, TRY);
shutter flags in front of all four test masses,
all oplev beams.
-
All suspended optics check out ok. Jay checked all the OSEM cables
last week and found two OSEMs to be bad;
Steve replaced them and Bob will do a post-mortem on them.
- The beam at the X-end was observed to move
by as much as inches, overnight, several nights in the last week or 2.
The problem was isolated
to be downstream of the mode cleaner and upstream of the
main IFO, and the only reasonable suspects are the two
in-vac PZT mirrors which steer from the IO to the main IFO.
Due to a series of delays, the PZTs and their controllers
were *not* thoroughly tested before they were installed!
And then...
-
The IFO PZT2 steering mirror pitch control amplifier
announced its culpability by spontaneously failing.
The PZT1 pitch control was used to temporarily
correct the resulting pointing error.
We are waiting for directions from
Piezojena to repair the unit under warranty.
Meanwhile, we will begin to commission the IFO
without the PZT2 pitch control; we should be able to work around it,
and install a repaired control amp without having to vent.
No beam motion at the X-end has been observed since PZT2-pitch
was disconnected.
-
The POB beam could not be
accessed because of a physical interference with the BS SOS structure; a
modification of the structure will be required in the future.
- Conor and Fumiko did a full independent checkout of the
installation. Steve, Osamu, and Mike did a full checkout of the alignment.
Michelson fringes were again observed, and
PSL flashes were seen at both ETMs.
- Steve et al removed the HWP in front of the Faraday isolator,
and had to move the Faraday isolator a bit to get the beam
centered on its aperture.
- Steve et al sealed up all doors and access connectors on Wednesday.
- Steve and Osamu began pump-down on Thursday morning.
(The vent lasted from 7/8/03 to 9/11/03).
TP2 (which backs the maglev turbopump TP1 which pumps on
the main volume) promptly failed.
They promptly replaced it with a spare, and proceeded with the pumpdown.
As of 4pm Thursday, the main volume is at ~ 1 mTorr and falling.
-
Optical levers (Kawazoe, Mow-Lowry):
- Fumiko and Conor checked out all oplev beams.
They made some changes to the beams: they now strike the
ETMs from the back, eliminating the need for the in-vac oplev mirrors
(which nonetheless remain in place in the chambers),
increasing the light returning to the QPDs by an order of magnitude.
All oplevs now have adequate light on the QPDs.
- They recommend that we nonetheless increase the gains
on the QPDs for ITMY and BS (replacing 10K resistors with 100K)
to improve the signal for those oplevs.
Ben will pursue.
- Oplev signals are still not making their way into frames,
and many signals (pitch, yaw, sum) are not in Dataviewer or DTT.
Jay will pursue.
- Fumiko is working on calibrating the oplev responses,
and will work with Jay on implementing the servos
and with Mike on testing Mike's oplev telescope.
- PSL: Conor is completing his documentation of: his
mods to the FSS servo board and its improved performance;
his measurements of the PSL PMC finesse; and
his re-layout of the PSL beamlines, and its performance.
This is Conor's last week at the 40m;
his 5 month visit has been tremendously productive, and fun
for all of us - thanks, Conor, we'll miss you, come back soon!
- Electronics (B. Abbott, Heefner, Taylor)
- With fixes and adjustments to various OSEMs,
all suspended optics and DSCs are operating well.
- As noted above, one of the in-vac PZT controller boards
died, and the manufacturer has been contacted.
- Shihori continues to learn about the digital suspension
controllers. She and Lisa are gearing up to diagonalize
the core optics suspensions.
- Lisa G found several problems with the
long-neglected STACIS system; we will get some help from CDS
to get them fixed.
- Lisa G continues to construct lots of nice MEDM screens
to help us keep track of all the 40m systems.
- Next big push is to get the LSC/ASC racks completed.
- Modeling (Miyakawa, Kawamura, Eichenfield):
- Seiji is using a Finesse model of the 40m
to study the length sensing matrix.
His matrix is very similar to the one
predicted by Twiddle; AJW and Seiji will compare details
to see if they can be made to agree exactly.
Seiji is also exploring the use of
double demodulation, with carefully chosen demod phases,
to improve the signals.
He is developing a method for setting the double
demodulation phases.
-
South Annex Bake Ovens (Taylor):
- Bob took a few days off; now back.
- Bob is continuing to service last-minute installation needs.
Sep 5, 2003
- Installation (Vass, Miyakawa, Smith, everyone):
- Steve and Bob installed the last of the optical
windows, and established camera views for the BS and the FI.
- Ben made final control cables for both in-vac PZT
steering mirrors, and the system is now in,
in closed loop, and apparently operational.
- Mike and Steve installed mirrors to pick off the
light reflected from both arms (POX and POY),
and aligned these output beams.
- Mike and Steve re-established the alignment of the
main IFO, including the SP and AP beams
and the two Initial Pointing beams (at the BS and at ETMX).
-
40 M IFO PRE-ALIGNMENT (Smith):
All IFO mirrors are aligned. Bright port and Dark port beams are
directed out the viewports onto the ISC table. The POXprime and
POYprime pickoff beams are directed out the viewport onto the ISC
tables. The POB prime beam cannot be picked off because of
interference with the BS SOS structure; a modification to the
structure will be required in the future. The PZT IFO steering mirrors
were adjusted to mid range. Optlev beams for the BS, ITMs and ETMs are
aligned and active. The initial pointing position and angle beams are
directed out the viewports, awaiting installation of the QPD
readouts. Video camera viewing of the Faraday isolator input is
aligned and operating.
- All the picomotor controls of the shutter flags
and the MMT have been tested. However, the shutter flags
need to be adjusted to ensure that the beam passes through
their apertures. This will hopefully be done today.
- Conor and Fumiko have checked out all of the oplevs.
They re-arranged three of the oplev beam paths
to bounce the beam off of
the back, AR-coated side of the test mass.
This increased the light power returning to the QPD
substantially, to well over 100 uW in most cases.
- Final installation and alignment is just about complete.
The MC is flashing as it goes through resonance
(we are not attempting to lock the MC in air),
and the flashes have been seen at the ITMs and ETMs.
We have seen Michelson fringes at the SP and the AP ports.
Cause for celebration, including champagne.
- However, we are plagued by several persistent
problems. The beam appears to be moving occasionally,
by significant amounts; it is consistent with some
pathology in the PZT mirrors that steer from the MC to the IFO.
- Also, ITMX keeps acting up. Jay can calm it down by
flipping the sign of the gain on the side osem damping loop (!!).
Very strange.
- There are periods when both these problems give way
to stability. During those times, we are doing
the final leveling and alignment tweaks.
- AJW wrote up a detailed checkout procedure
for all installed in-vac components, alignment,
suspended optics, and oplevs.
- Tomorrow (Friday), we'll do a final checkout, seal everything up,
and then monitor the situation throughout the weekend.
If things are stable, we'll proceed with the pumpdown on Monday.
- Electronics (B. Abbott, Heefner, Taylor)
- As noted above, the DSC for ITMX is acting very strange.
- The PZT interface board for the ASC PZT mirrors arrived on Tuesday.
Ben stuffed the boards, milled some front panels for them
from the aluminum panels already on the controllers,
and set them in place. With the help of Steve,
Ben swapped the cables from their temporary FLKM blocks,
to the new patch panels, and realigned the PZTs one by one.
- The EPICS servers running in the linux box (c1epics)
were running multiple "IOCs", and were not communicating to the EDCU,
so EPICS channels were not available to DAQs or dataviewer.
Jay and Alex are working on a fix which combines all channels
onto one IOC, and will test it tomorrow.
- Jay and Alex will get the EPICS timeserver going
on the EDCU, and test it tomorrow.
- Ben has been helping Aidan with his photon actuator experiment.
Aidan finished testing a filter that Ben made for him,
and he found that it has the shape that he wanted,
so he is now attempting to put it into a control circuit.
He is having problems getting his 5W or 0.5W lasers to work
with Mohana's driver board, but Ben will help iron that out.
- Ben is in the process of testing some ISS PD boards
that he and Flavio will take to Livingston on Monday.
- Shihori is learning about the digital suspension
controllers, and is taking DTT spectra as an aid to
optimizing gains and diagnosing problems.
Lisa and Shihori are learning how to diagonalize suspensions.
- Lisa G is trying to diagnose problems with the
long-neglected STACIS system.
- Lisa G has been constructing lots of nice MEDM screens
to help us keep track of all the 40m systems.
- Modeling (Miyakawa, Kawamura, Eichenfield):
- Seiji continues to develop a model of the 40m and AdvLIGO with Finesse,
and comparing with Twiddle calculations.
- Computing (Ivanov, Bork, Goggin, Wallace, Bogue, Pedraza):
- We are able to run medm on our wireless laptop PCs on the martian network,
mounting the our online software disk (containing all the .adl files)
via samba. Unfortunately, various display pathologies appear on the medm
screens, making some of them useless.
- However, we continue to have intermittent wireless and network problems.
Lisa Bogue has been helping.
-
South Annex Bake Ovens (Taylor):
- Bob is continuing to service last-minute installation needs.
Aug 29, 2003
- Installation (Vass, Miyakawa, Smith, everyone):
- Osamu has re-established the alignment of the
PSL -> IOO -> ITMx and ITMy, and back out the SP and AP.
Michelson fringes have been observed!!
- Steve & Mike have installed all the components
in the vacuum chambers,
and Mike is doing the last alignments (of the Initial Pointing beam
position and angle beams to QPDs).
- Well, a few more components remain:
Bob is installing the last mirrors for camera views.
Camera views for ITMx, ITMy, ETMx, ETMy are in place;
the one for the beam input to the faraday isolator
is going in today, and and one for BS/PRM/SRM
will go in last (next Tuesday).
One or two more optical viewports need to be installed.
- The two in-vac PZT steering mirrors were tested
successfully by Ben. However, he only had enough cable to
test one of them at a time. He's made a 2nd cable,
but encountering problems.
We need to have both PZT's powered for the final alignment.
Fortunately, these PZTs have strain-gauge readbacks and
feedback loops, so we can be optimistic that they will
return to their proper places when they get powered on again.
- Mike's autocollimator was finding that the ETMx yaw
was changing from day to day, even though the OSEMs showed
no indication of movement. Fortunately, there's bee no evidence
of movement in the last ~ 5 days. An oplev is monitoring it.
- Picomotor controls for the MMT and the in-vac shutter flags
all check out.
- All the oplevs were set up and aligned by Naman
before she left, but they all need to be re-aligned.
- Mike & Steve eliminated a potential clipping of the
AP beam on the faraday isolator, by moving things slightly.
- We hope to complete this installation and alignment,
check everything out, and pump down early next week.
- Electronics (B. Abbott, Heefner, Taylor)
- PZT controls for in-vac steering mirrors:
Ben finished testing the PZT chain; as of last Friday,
everything checked out fine.
Ben made and routed a second cable so that both
PZT could be actuated simultaneously.
When this was done, the old PZT controller didn't work properly.
Ben's out of town till next Tuesday, will check it out then.
- The interface board for the PZT controls
should be in tomorrow, and in place next week.
- Aidan's photon actuator experiment design
came back from the boardhouse on Friday.
Aidan stuffed it and is still in the process of testing it
ready for use early next week.
- Ben has made up and finished two of the the ISS PD boxes
and six PD heads for Flavio so that he can test his ISS boards
with the PDs in place.
- Art and Bob are continuing to work on the LSC and ASC
rack cross-connects. They have been wired, mounted, and grounded.
- Ben has compiled a list of components that we will need to
finish the ASC and LSC systems, and is taking steps to get
everything we need.
- Lisa G finished wiring up all of the video monitors
in the control room, and spiffed up the video switch control screen.
- Jay and Ben will assemble the equipment they need
to move all the front end timing signals to a separate
"pizza box" crate, independent of the DAQS crate.
- Jay and Ben are thinking about 166 RFPDs and demodulation,
and double demod.
-
Optical levers (Bhatt, Goggin, Smith, Vass, Taylor):
- Just before Naman left, we turned on the oplev servos
and used them to control the pitch and yaw of the
suspended optics at DC.
It worked reasonably well for ETMy and BS.
The beams were blocked at ITMy and ETMx for various reasons.
The ITMx oplev sorta worked,
but the response was consistent with the beam moving off of the QPD.
- With Naman gone, Fumiko will take over the development
of this system.
- The oplev beams (red) are attenuated to only a few microwatts
by the time they get to the QPDs.
Most of the loss appears to be at the suspended optics.
More reflectivity can be obtained by moving the beams off of
the coated part of the optic surface.
We will attempt to maximize the light on the QPDs as part
of the final checkout next week.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor is documenting all of the changes he made to the
PSL table, and the changes he and Ben and Rich made
to the FSS board.
- Ben accidentally blew the PA85 on the FFS board,
then promptly fixed it.
- Ben made the HVamp daughter board on the FSS card into a permanent mod.
- Osamu found that the PSL beam was getting clipped slightly
at one of the IOO pockels cells.
This explained the ellipticity Conor had noted before.
Osamu re-aligned it and eliminated the clipping.
- Conor then re-aligned the two IOO monitoring QPDs
near the periscope.
He is all set to re-commissioni the MCR and MCT monitoring QPDs
as soon as the MC is back up.
- Conor cleaned up the PSL table, removing all unused components.
- Optical sensing (Smith):
-
OPTICS PARTS LIST, Orders pending:
Spherical collection mirror from Rolyn for the BRDF meter.
-
40 M IFO PRE-ALIGNMENT:
The symmetric (bright) port was aligned by centering the PSL input beam
with a target at the ITMx and then retroreflecting from the ITMx to produce
the bright port beam. The overlappig reflection from ITMy produced visible
fringes at the bright port.
The initial pointing beam splitters were aligned by using modecleaner
flashes to produce an observable initial pointing beam. The initial
pointing position beam was aligned out through the viewport. The initial
pointing angle beam remains to be directed out the the x-end viewport.
Spacers need to be placed to raise the x and y end optical tables to the
designed 4 inch beam height. The IFO PZT steering mirrors change their
pointing direction when energized; however, the pointing direction can be
adjusted electronically and when the PZT feedback loop is activated, the
mirrors appear to reproduce their pointing when the voltage is turned on
and off. One of the steering mirrors was not functioning electronically.
The video image mirrors in the BSC chamber and input chamber for observing
the Faraday isolator input aperture were installed and aligned. Beam dumps
were placed in the BSC chamber to catch the reflected beams from the x and
y spoiling flags in front of the ITMx and ITMy mirrors. The POX pickoff
mirror was installed and aligned. The ETMx and ETMy output optical trains
have not been aligned. All optical lever beams are functioning, but may
require final alignment. The video turning mirror for viewing the BS from
the input chamber is assembled and awaiting installation.
- PHOTON DRIVE R&D:
The test of the photon actuation control of the mode cleaner is awaiting
the pump down and commissioning of the mode cleaner.
Aidan Crook is staying an extra week and will test the photon actuation
control of the mode cleaner after it is locked.
He has boards from Ben and from Jay to test his servo,
which is designed to notch out a line in the MC error signal
at 153 Hz (a mechanical resonance of the MC suspensions).
- Modeling (Miyakawa, Kawamura, Eichenfield):
- Seiji continues to develop a model of the 40m and AdvLIGO with Finesse,
and comparing with Twiddle calculations. He's exploring the use of
double demodulation in all degrees of freedom to improve the LSC matrix.
- Computing (Ivanov, Bork, Goggin, Wallace, Bogue, Pedraza):
- Lisa Bogue set up samba to serve the our online software disk
(op140m:/cvs/cds/caltech) to PCs on our martian network.
Jay installed EPICS on our PC laptops. Now we can run EPICS
and medm screens on PCs, with no extra load on op140m!
- Jay and Alex think they know why many of the new EPICS channels
(for oplevs and QPDs) are not being read out correctly
for logging to frames or display with dataviewer.
They will need to reboot DAQS (and just about everything else)
to implement the fix. They'll do that early next week.
- Lisa G has constructed a new "40m checklist"
medm screen with most all important EPICS channels,
so that the status of all active systems can be seen at a glance.
- Jay is working on getting the epics timeserver going
so that epics will finally know what time it is!
- Lisa was able to reboot zuben, the Sun blade 100 on Dennis' desk.
-
South Annex Bake Ovens (Taylor):
- Bob is shipping baffles for LHO to the heat treaters.
- Bob is cleaning some parts for Larry Jones.
- Bob is cleaning up the South Annex clean room,
and re-organizing the cabinets so that less time is spent
looking for parts.
Aug 22, 2003
- The 40 Meter Technical Review Board
(chair:
Ken Strain, kstrain@physics.gla.ac.uk)
met on Wed, Aug 20, at the LSC meeting, Hannover.
Osamu Miyakawa presented the
40m status report.
- Installation (Vass, Miyakawa, Smith, everyone):
- The PSL -> IOO -> IFO is now completely aligned in air,
including all output beams, all oplev beams,
and with all suspended optics' OSEMs at mid-range.
- Mike is trying different places to put the
autocollimator for a final, out-of-vacuum alignment.
- It's not final, yet: the last oplev mirrors, camera
view mirrors, shutter flags, will be installed today.
This should have negligible effect, but the full
alignment will be re-established afterwards.
- But, there's a problem: a few suspended optics
have been observed to drift significantly in their alignment, overnight.
The obvious suspect is the settling of the
seismic isolation stacks (with viton springs);
but it seems too big an effect. Mike and Steve
continue to investigate this.
- If the alignment does not continue to drift,
we hope to complete this installation and pump down early next week.
- Also, Mike discovered that the BS suspension clips
the AP beam. He and steve will construct a jig to move the
BS suspension to get rid of this.
- Steve is reviewing the placement of all optical-quality
viewports, and re-arranging as necessary.
- The interface board for the in-vac PZT mirrors
is finished, and was sent to the
boardhouse on Tuesday; should be back by Monday.
But we hope to seal up on Monday; so in the meantime,
Ben is testing the system with a cross-connect block
in place of the interface board.
- Electronics (B. Abbott, Heefner, Taylor)
- ITMx was damping poorly.
Steve discovered that it was banging on an EQ stop.
He backed it out; now all suspended optics are damping well
at nominal gains.
- The DAQS was crashing last week, but has not crashed
once this week. Not sure why; there may have been a loose
ethernet cable that was inserted more firmly.
- Ben had some simulation problems with Aidan's photon actuator experiment
filter designs. He finally fixed the problem on Monday, and the design went
to the boardhouse on Tuesday. When it arrives, it will be stuffed and
tested ready for use early next week.
- Ben has assembled an inventory of all the parts we need
to finish the ASC and LSC systems,
and is taking steps to get everything we need.
- Lisa G is running more video monitor cables from the
video switch to the monitors in the control room.
-
Optical levers (Bhatt, Goggin, Smith, Vass, Taylor):
- Naman, with help from Jay, Ben, Steve, and Mike,
has oplev beams on all 5 optics: BS, ITMx, ITMy, ETMx, ETMy;
all work fine, through to EPICS screens and dataviewer.
- Except, the beam for ITMx is severely attenuated by the time
it gets to the oplev QPD. She is investigating.
- Ben changed the gains on the oplev QPD circuit by 10x to see if
that would help with the weak ITMx signal,
but the problem seems to be due to too many mirror bounces.
- Alex and Jay installed and verified
new code for the optical levers in the vertex.
The segments on the optical lever servo screen now match
the segment definitions for the aux crate,
i.e. segment 1 is segment 1, etc.
This is the same definition used for the ends.
-
As part of the new code installation in the vertex, Jay tested the
optical lever signals in dataviewer. We observed the 4 segment signals
for the BS in dataviewer and verified that we could see them. They all
work.
- Next step is to set up and turn on the digital servo
and see if it damps.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor measured the OLTF of the FSS with the pickoff
after the PMC and before the PMC.
They look exactly the same (and the same as before the re-layout)
at 100 kHz and below, with +16.5db of gain at 100 kHz
(LIGO spec is +12db at 100 kHz).
-
The PMC pole rolloff is clearly seen above 200 kHz.
We can easily switch between having the pickoff
before and after the PMC, with no change in gain at 100 kHz;
this will allow us to easily evaluate the effect of the change
on the frequency noise spectrum measured by the mode cleaner,
as soon as we get the mode cleaner back up.
- This good performance at 100 kHz means that there's
no need to make further mods to the FSS to increase
the UGF. In particular, no PMC pole compensation is needed.
- Conor and Ben will make the
HVamp daughter board on the FSS card into a permanent mod.
- Conor is re-commissioning the 4 QPDs that monitor
the PSL beam position, PSL beam angle, MCT beam position,
and MCR beam position.
- Conor is investigating some beam ellipticity
in the vicinity of the PSL periscope.
- There was a slight delay on the ISS PDs boxes silkscreening. They are
now ready, and I will go and pick them up tomorrow. The head enclosures
are finished, and just need some screws to finish them off.
- One set of ISS boards and PD's is earmarked for our PSL.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
Spherical collection mirror from Rolyn for the BRDF meter.
- 40 M IFO PRE-ALIGNMENT:
Both arms have been aligned. The antisymmetric (dark) port has been
aligned. We are in the process of aligning the symmetric port with the
autocollimator.
-
PHOTON DRIVE R&D:
Tom Essinger-Hileman has aligned an optical system with 4 bounces from the
MC2 mirror. He presented his SURF talk, and has completed his SURF program.
Aidan Crook is staying an extra week and will test the photon actuation
control of the mode cleaner after it is locked.
- Modeling (Miyakawa, Kawamura, Eichenfield):
- SURF Keiko Kokeyama presented her results on testing (in MATLAB)
the approximate solution for the dual-recycled summation cavity
for E2E. It looks good! Implementation in E2E can now begin.
- Seiji continues to develop a model of the 40m and AdvLIGO with Finesse,
and comparing with Twiddle calculations.
- Matt continues to develop his Simulink model of
the MC WFS system. He talked to Luca at LHO about how they
do the servoing there.
- Computing (Ivanov, Bork, Goggin, Wallace, Bogue, Pedraza):
- Lisa Goggin assembled a database of all the computers
and their target directories in /cvs/cds/caltech/target,
and labelled all the embedded computers.
She updated the network status medm screen.
- Lisa Bogue set up cron jobs on all the online Suns
to synch their system clock with our gateway computer,
which synchs to a GPS server on campus.
We hope that will reduce the time synch problems
that prevent us from running DTT.
- Jay looked at the problems with running dataviewer on op140m,
"The problem was with the number of
queues. I did an ipcs -q and found 9. I then used ipcrm -q to remove
each one. Dataviewer now appears to work. I started it with 8
different optical lever signals from different optics and they all
display. The updates are very slow since op140m is such a dog. We
should get a fatser machine to run dataviewer on."
- We use PC laptops to display medm screens, off of op140m.
We can lessen the load on op140m considerably by running medm
directly on the PCs, if they can mount the op140m disk.
Jay suggests getting Samba to run on op140m, to serve the disk to
the laptops. We'll ask Lisa B.
- The Sun blade 100 on Dennis' desk won't boot;
Lisa B has been alerted.
-
South Annex Bake Ovens (Taylor):
- Bob is working on yet more baffles for LHO.
- Bob is baking more misc parts for installation,
including remachined shutter flags.
- Bob has prepared optical viewport assemblies for Steve.
Aug 15, 2003
- The 40 Meter Technical Review Board
(chair:
Ken Strain, kstrain@physics.gla.ac.uk)
meets on Wed, Aug 20, at the LSC meeting, Hannover.
Osamu Miyakawa will present the
status report.
- Installation (Vass, Miyakawa, Smith, everyone):
- Steve, Mike, and Osamu continue to align
the main IFO (BS, ITMs, ETMs; the PRM and SRM
will be installed after we learn how to lock the
Fabry-Perot Michelson).
- The path from PSL -> MC -> FaradayIsolator -> MMT
-> BS -> ITMx and then back through FaradayIsolator
to symmetric port beam has been completed.
- The path from autocollimator BS -> ITMx -> ETMx
and the path from autocollimator BS -> ITMy -> ETMy
have been completed.
- Next, the dark port beams and pickoff beams
will be established.
- Then, we'll screw it all up by adding oplev
mirrors, camera mirrors, shutter flags.
And screw it up even more by balancing all the OSEMS
on all suspended optics.
Then re-do all the alignment again!
- Hope to complete this and pump down by end of next week.
- Electronics (B. Abbott, Heefner, Taylor)
- Ben changed the power on all DSC satellite amplifiers
from 24 to 20 volts.
- All 10 digital suspension controllers are functioning
and 8 are in continual use (SRM and PRM are still on the bench).
- ITMx continues to damp poorly; suspect a mechanical problem
(wire out of standoff groove); will be investigated.
- The DAQS crashed several times this week,
and wouldn't reboot with a cpu reset to c1daqscntrl.
Powering down the DAQS crate, reseating the GPS board,
powering back up, and restarting all the front end CPUs
did the trick, but it crashed again 22 hours later.
Ben and Jay got it back up.
It may be a dying GPS board. Fortunately we have a spare.
- Each time we try to reboot the DAQS, the DSC's go crazy.
Don't know if it's because of the timing or the RFM.
We'll need to put a separate timing GPS system into a
separate crate ("pizza box"), and make sure the
RFM network bypass switch is working. Rolf will
investigate when he returns next week.
- Ben is getting QPDs and LSC RFPDs for the
SP, AP, pickoff, and end transmitted sensing beams.
- Art is finishing up the LSC rack cross-connects.
All LSC modules are being fabricated and/or purchased;
Jay and Ben will inventory them.
- There is a bad VME crate in the LSC rack; it was
pulled out of the ETMx rack because the cpu would hang.
Ben will see if it can be fixed; else, replaced.
- Ben is setting up the drivers
for the in-vac PZT steering mirrors.
He is designing an interface board that will go between the PZT
driver cables in the ASC rack, and the flange feedthroughs.
It's almost done. It should go out to the board house today.
- Ben has been helping Aidan with his photon actuator experiment filter
designs. Aidan gave Ben a transfer function that I have made into a
hardware design. It should go to the boardhouse tomorrow.
-
Optical levers (Bhatt, Goggin, Smith, Vass, Taylor):
- Naman has calibrated the response of the 7 oplev PD's,
in terms of volts on the EPICS screen versus x/y of beam on QPD face.
- She measured the RMS noise spectrum in pitch and yaw
(in Vrms) with the laser pointing directly at the QPD,
both for short lever arms (laser and QPD on same table)
and 40m lever arms.
She's working on the conversion to meters-rms.
- Naman and Jay chased down the differences between
the two ETM electronics chains and the other 5.
All 7 QPDs are the same, but the ETM screens display
the 4 quadrants differently than the other 5.
It looks like the problem is in the readout software.
Alex will be notified.
- Naman and Steve will install the remaining
in-vac oplev mirrors by the end of this week.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- The PSL has been operating robustly in its new
configuration (fewer mirrors between PSL and periscope,
FRC pickoff after the PMC).
- Mike is updating the ACad optical layout to reflect
the changes in the PSL table.
- Conor noted that the beam near the periscope was elliptical;
he'll re-adjust the optics between the PMC and the periscope
to fix it.
- The new layout puts less optical power into the FRC;
the electronics gain is maxed out.
Conor increased the power into the PMC from 1w to 2w,
and observed the FSS going unstable.
He turned down the electronics (common) gain,
and it is now stable, with headroom to spare in the electronics.
- Conor is re-commissioning the diagnostic devices
(QPD, camera, OSA) at the periscope pickoff
and at the MCT beamline.
- Conor and Ben will continue to work on the mods
to the FSS card which increase the UGF too 800 kHz:
making the HVamp daughter board permanent,
adding a zero to compensate for the PMC pole,
and maybe a pole to roll off the gain above 1 MHz.
- The stands and boxes for the ISS PDs are finished being fabricated,
anodized and silkscreened. Ben will go and pick them up on Friday.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
Spherical collection mirror from Rolyn for the BRDF meter.
-
OPTICAL LEVER ASSY:
Naman is installing all of the external and in-vacuum components. She is in
the process of testing the 40m long focal length lens for the optlev receiver.
-
40 M IFO PRE-ALIGNMENT:
The IR autocollimator was used to establish the y-arm cavity centerline and
to align the BS and the ITMy. The ETMy is recalcitrant and has yet to be
aligned.
- POX and POY: Mike is designing cantilevered mirror mounts
to catch the pickoff beams reflected off the two arms.
-
PHOTON DRIVE R&D:
Tom Essinger-Hileman has aligned an optical system with 4 bounces from the
MC2 mirror, with the addition of 8 bounces if necessary, and is awaiting
the locking of the mode cleaner to complete his photon acuation of the mode
cleaner cavity.
He has acheived around 10 dB of intensity noise suppression,
bringing the intensity noise to around -140 dB,
in the LIGO band.
Aidan Crook has designed the filter for the additional photon actuation
servo loop (focussing on suppressing a suspension
mechanical resonance at 154 Hz).
Ben is making a hardware filter. Aidan and Tom will test the
photon actuation control of the mode cleaner after it is locked.
- Modeling (Miyakawa, Kawamura, Eichenfield):
- Osamu, with SURF Keiko Kokeyama, is testing out (in MATLAB)
the approximate solution for the dual-recycled summation cavity
for E2E.
- Seiji is developing a model of the 40m and AdvLIGO with Finesse.
- Matt continues to develop his Simulink model of
the MC WFS system.
- Computing (Ivanov, Bork, Goggin, Wallace, Bogue, Pedraza):
- With all the changes to the embedded computers in the lab
(front-end pentiums, EPICS mvme162s, linux PCs for front-end filtering,
linux PCs for EPICS access, general computing, ...),
Lisa Goggin is inventorying all the computers
and their target directories in /cvs/cds/caltech/target.
- Both dataviewer and DTT are cranky, extremely slow,
and often hang or give errors. We hope Rolf and/or Alex
can help with this when they get back from MIT.
- Can't plot or excite test points with DTT.
- DTT requires the host Sun to be synched to GPS time
within one second. We need to make this happen, somehow...
-
South Annex Bake Ovens (Taylor):
- Bob assembled and vac-prepped the picomotors for the shutter flags
and the camera mirror mounts.
- Bob is working on more baffles for LHO.
- Bob is building more OSEMs for Janeen/Calum, GinGin, and Glasgow.
- Bob is baking more misc parts for installation,
including camera mirror mounts.
Aug 8, 2003
- Installation (Vass, Miyakawa, Smith, everyone):
- The in-vac PZT steering mirrors were installed,
as well as most of the remaining in-vac mirrors needed
for the IO system.
- Matt and Naman installed in-vac oplev mirrors on ETMy.
The other 6 sets of in-vac oplev mirrors are
ready for installation but not yet in.
- More counterweights were needed, and Betsy sent us some
from LHO. Thanks, Betsy!
- Steve, Mike and Osamu have been aligning all the components
of the main IFO (except for the PRM and SRM, which will be
installed at a later stage).
- Osamu has sent the PSL beam through the mode cleaner mirrors,
the fraraday isolator, the mode matching telescope,
the beam splitter, and ITMx. The beam reflects off of ITMx
and back through the faraday isolator, exiting the vacuum
enclosure as the SP beam.
- Meanwhile, Mike and Steve used the autocollimator beam
entering at ETMx, aligning ETMx and ITMx and the BS,
back towards the mode matching telescope.
- Mike and Steve moved on to the y (south) arm,
and noticed that the beamsplitter is in wrong.
They rotated it by 180degrees, and are now in the process
of re-establishing the above 2 steps before moving on to
the y arm alignment.
- Mike modified his optical layout drawing
so that POX and POY carry the light *reflected*
from the two arms, not incident on them.
- Steve has installed optical-quality (BK7), 1/2 degree wedge,
1064 AR coated viewport windows
on the input from the PSL, the output for SP and AP beams,
and TRX. He will also do TRY and POX.
The remaining BK7 windows are broad-band AR coated;
one will go on the POB beam.
- Bob has completed in-vac cables for the PZT steering mirrors,
and picomotors for the shutter flags and MMT.
- Matt has checked out the picomotor controller
and tested it on the 4 shutter flag picomotors
prior to their installation.
He will check the picomotor on the mode matching telescope
as soon as alignment work in that chamber is complete.
- Four shutter flags, and
a few in-vac camera view mirrors remain to be installed.
Teflon flags for the shutter flags are being re-worked
and vac-prepped.
- Electronics (B. Abbott, Heefner, Taylor)
- Last week, Ben and Jay fixed the xycom screens for the ETMx and ETMy
DSC's, they are now
fully functional and switching the End Station Whitening and Dewhitening.
- Last week, Ben changed the power to the ETM
satellite amplifiers from 24v to 20v.
He will do the same for the vertex satAmps.
- Last week, Ben and Jay got the ETM DSCs all working
and damping the ETMs. However, they require high gains
(~ 25 instead of 1); being investigated.
- A few days ago, ETMy was discovered to be not damping.
Ben found a couple of minor electronics
errors. Then Matt noted that ETMy seemed to be resting on
an EQ stop (probably after the oplev mirrors were installed;
se below). After this was backed off, ETMy damps just fine.
- However, ITMx damping is not very good;
under investigation.
- Matt has taken DTT spectra of all 7*5 OSEM sensors
(ETMx is still EQ-stopped for alignment, and SRM and PRM
are not yet installed).
There are several anomalies, under investigation.
This is the beginning of a systematic characterization
of the performance of all 10 DSCs / suspended optics.
- Ben is setting up the driver electronics and cabling
for the in-vac PZT steering mirrors.
Ben is designing an interface board that will go between the PZT
driver cables in the ASC rack, and the flange feedthroughs.
There are no spare flange feedthroughs on the BS chamber!
-
Optical levers (Bhatt, Goggin, Smith, Vass, Taylor):
- Naman has checked out all 7 oplev electronics chains
and all 7 oplev QPDs. All look ok.
- Except, that both ETM oplevs get mapped onto the
EPICS screen differently than the other 5.
Will investigate whether this is a cabling, electronics,
or software problem.
- Naman has measured the reflectivity of the old
(pre-upgrade) in-vac oplev mirrors; they seem to be
fine for the job.
- Naman and Matt have installed in-vac oplev mirrors
on ETMy and have used them to diagnose a problem with
ETMy damping.
- Naman is calibrating the position response of the oplevs /
electronics chains.
- As suggested by Seiji, Naman will measure the
oplev signal noise without any suspended optic,
to see how it compares with the signal expected
from the damped optics.
- Naman is trying to get the oplev beam into Mike's
prototype oplev telescope; it's not easy to align it.
- Naman plans to model the oplev system and design
optimal filters.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor, Ben and Rich finished the testing of the
FSS board mods; the servo is now operating with the
extended bandwidth circuit, and we are seeing bandwidths
approaching 800 KHz.
The implementation is still temporary, and is missing
two potentially important pieces:
compensation for the FSS pickoff being taken
after the PMC, and a roll-off beyond 1 MHz.
- Conor has completed the re-layout of the PSL optical paths;
it looks great!
And the stray light in the PSL enclosure is under control.
- The PMC and FRC both have > 80% transmission.
- Osamu measured the error signal spectra
for both the PMC and FSS loops; they are essentially
unchanged with respect to the re-re-layout configuration,
except for a peak in the FSS spectrum at 25 kHz
which is no longer present. This is presumably due to
mods to the FSS card, not the re-layout of the optical paths.
- However, the optical gain in the FSS path is reduced
with the new layout, and the electronic gain has been
raised to maximum, to compensate. This needs to be remedied.
- Seiji has analyzed the predicted noise performance
of the PSL with the FSS pickoff moved to after the PMC. This
technical note T030149
concludes that the move should be advantageous.
- But the true test will come when we finish installation,
pump down, and analyze the frequency noise with the mode cleaner.
Conor has made it easy to switch the pickoff between
pre-PMC and post-PMC locations.
- The ISS PDs for the sites have almost finished being fabricated in the
back shop. Testing will begin soon.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
1 q-switch E/O shutter from Fast Pulse. Spherical collection mirror from
Rolyn for the BRDF meter.
-
OPTICAL LEVER ASSY:
Naman is installing all of the external and in-vacuum components. She is in
the process of testing the 40m long focal length lens for the optlev receiver.
-
IFO STEERING MIRRORS:
The PZT steering mirrors have been installed and aligned in the vacuum
chamber.
-
SPS BREWSTER PRISM MIRROR:
Installed and aligned in vacuum chamber.
-
IN-VACUUM MIRRORs:
In-vacuum mirrors for the IO path have been installed and aligned in the
chambers.
-
40 M IFO PRE-ALIGNMENT:
The entire optical path from the PSL laser through the x-arm has been
aligned. The IR autocollimator was used to establish the arm cavity
centerline and to align the ETMx and ITMx, and to initially align the IO
mirrors back to the MMT. The PSL laser was used to align the Faraday
isolator, the MMT, and to make a final alignment of the PZT1 and PZT2
steering mirrors to obtain a retroreflection from the ITMx. The
retroreflected beam was aligned with the Brewster mirror and was sent out
the bright port viewport on the output chamber.
-
PHOTON DRIVE R&D:
Tom Essinger-Hileman has closed the loop of his 0.5 watt intensity
stabilized laser servo system. A relative intensity noise close to 1E-7 was
measured. The initial result was obtained with PDA 55 photodetector, and
subsequently Ben found the problem with the intensity stabilization PD and
similar results were also obtained. Tom had spacers made to raise the
height of the external optical table to be compatible with the optical
table in the mode cleaner chamber. He has designed an optical system which
will allow initially 4 bounces from the MC2 mirror, with the addition of 8
bounces if necessary.
Aidan Crook has calculated the bandwidth of the photon acuator for the mode
cleaner based on the available effective laser power (which is proportional
to the number of bounces). He is in the process of designing the filter
functions for the additional photon actuation servo loop.
- Mode Cleaner (Miyakawa)
- Matt continues to develop his model of the MC WFS system.
He has completed a detailed model of the optical plant,
and is now adding the sensing, actuation, and feedback modules.
-
South Annex Bake Ovens (Taylor):
- Bob is completing paperwork for all the bake jobs he's been doing
for Janeen and the site baffles.
- Bob is building more OSEMs for Janeen/Calum, GinGin, and Glasgow.
- Bob is baking more misc parts for installation,
including camera mirror mounts.
July 25, 2003
- This is Dennis' last week before moving to San Antonio.
So, there are more parties than usual.
Dennis has completed the PSL and Networking chapters
of the 40m Procedures Manual.
- Installation (Vass, Ugolini, Miyakawa, Smith, everyone):
- Steve and Helena commissioned the CO2 snow blower
to clean off the ETMs before installation.
- Dennis and Steve installed ETMy and ETMx in their
chambers. Matt carefully positioned the suspensions
in their correct location.
The tables were levelled with counterweights.
The EQ stops are currently in.
- Osamu and Seiji have aligned all the input optics,
using the PSL beam with the wrong polarization
to get through MC1 and MC3 better:
PSL -> MC1 -> MC3 -> MCT pickoff -> temporary HWP ->
faraday isolator -> alignment iris ->
mode matching telescope -> first IFO steering mirror
in BS chamber.
All optics in the Input Optic Chamber (IOC) have been installed,
and the SP and AP paths are clear.
- MCT pickoff beam is aligned onto a camera on
the MCT sensing table (the PSL table).
- According to Mike's alignment procedure
T030141-00.pdf,
we no longer need the
PSL beam. So, Conor is now performing the PSL re-layout (see below).
- With more weight in the IOC, we needed more counterweights.
Steve & Bob are hastily making up a bunch more, with help from
the machine shop.
- Currently, we have pickoffs
of the light incident on the arms (POX and POY).
Osamu and Seiji believe that we should instead have pickoffs
of the light reflected from the arms (call them POX' and POY')
to help in lock acquisition.
Mike Smith will work out how to change the pickoff mirrors
and beam stops to get these paths out.
- Steve and Bob are preparing the in-vacuum cabling for the
two PZT steering mirrors, and for the pico-motors used by
the MMT and the shutter flags.
- Next step: Steve will put new optical-quality viewports
at the ends (and everywhere else where they are not yet in).
Then, continue with Mike's alignment procedure,
using the autocollimator from the ETMx end, on in.
- Steve is continuing to assemble and prepare
all the misc things that must be installed, including:
optical-quality viewports, in-vac oplev mirrors,
cameras, beam dumps, shutter flags,
cables for the MMT picomotor, shutter flag picomotors, and
PZT steering mirrors.
- Electronics (B. Abbott, Heefner, Taylor)
- Ben continues to work through the subtleties of
setting up the Xycom switches for hardware and software
whitening and dewhitening in the DSCs,
especially the ends, with help from Osamu and Jay.
- ETMy has been wired to its suspension controller.
Ben checked it out; after fixing some problems
(with Bob's help), he sees all the sensors.
- Steve has backed out the earthquake stops,
and Ben is now damping the optic.
The gain settings are little wierd,
Ben will investigate.
- The DSC sattelite amplifiers are all being
powered with +-15 v, and they should be more like +-18 or 20v.
Ben and Bob will investigate and make the needed changes.
- The ETMx DSC crate was locking up repeatedly
after boot-up. Jay discovered that the problem
was with the crate; switching in another crate
fixed the problem, reproducibly.
Jay & Ben will find a permanent crate for that location
so that the ETMx DSC can be commissioned next.
- Jay reports that the rest of the parts for the
LSC/ASC racks cross-connects are in, and Art and Bob are
finishing them up.
- Linear power supplies for the LSC system
are in. They will go in a small rack
near the LSC/ASC racks.
- Jay ordered Penteks for the LSC/ASC system,
and will ask Rolf about the Pentiums, RM boards,
and other modules.
-
Optical levers (Bhatt, Goggin, Smith, Vass, Taylor):
- Naman has checked out all 5 vertex oplev electronics chains
from the QPD to the EPICS screens, with help from Ben.
Two end oplev chains remain to be checked out.
- Naman checked out 7 oplev QPDs. Two are bad,
and Ben brought them over to Art to be diagnosed & fixed.
- Naman is working on understanding Mike's
oplev telescope design, and has reproduced many of the numbers
with a Mathematica model.
- Naman is working with Steve to prepare the in-vac
mirrors for all 7 oplevs.
- Naman and Steve Beam-scanned a couple of the
oplev laser diodes, and found that their profile
is rectangular. Shouldn't be a problem, we think.
- Naman is calibrating the response of the QPDs
and electronics chains, by scanning an oplev laser beam
across the face of the QPD and reading out the response
on the EPICS screens.
- Naman identified some unintuitive aspects of the
EPICS screens that display the oplev position information;
but, if that's what they live with at the sites,
I guess we can live with it as well.
Jay will check whether that's really how it's done at the sites.
- Naman and Jay are thinking about the filters
needed for the oplev servos, and will start a model
of the system.
- Bob is making more cables for the optical levers at the ends.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor, Ben and Rich have been implementing changes
to the FSS board: replacing a slow HVamp with a new faster one
on a daughter board, and adding an additional LV amp.
They have increased the FSS UGF from 200 kHz to 700 KHz,
and the servo is locking robustly.
The gain curve is rather flat beyond 700 kHz;
they will consider adding a notch filter
for a ~4 MHz EOM resonance peak,
and maybe something to roll off the gain faster beyong 700 kHz.
- To do this measurement, they had to borrow an HP 4195
from Wilson House, since ours seems to be malfunctioning.
The loaner was promptly returned!
We will need to get ours repaired.
- Conor and Matt have begun to re-layout the PSL,
and are proceeding quickly.
They've already laid down the new main beam path,
have mode-matched into the PMC in its new location,
and are ready to test the PMC servo.
- Seiji is developing a noise model
to understand the potential advantage of moving the
FSS pickoff from upstream of the PMC to downstream.
He's derived all the transfer functions
from each noise source to the frequency noise of the
PMC-transmitted beam.
- Mike is evaluating the consequences of having the
PSL->MC PZT steering mirrors only 20 cm apart
instead of ~ 1.5 meters (as required for the re-layout).
Doesn't seem to be a big problem.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
1 q-switch E/O shutter from Fast Pulse. Spherical collection mirror from
Rolyn for the BRDF meter.
-
FARADAY ISOLATOR:
Faraday isolator was installed and aligned.
-
OPTICAL LEVER ASSY:
Naman is staging all of the external and in-vacuum components. She has
independently checked the design of the 40m long focal length lens for the
optlev receiver, and has verified the design by Mike Smith.
-
IFO STEERING MIRRORS:
The PZT steering mirrors are awaiting installation in the vacuum chamber.
-
SPS BREWSTER PRISM MIRROR:
In process of being installed in vacuum chamber.
-
IMMT:
The input MMT was installed and aligned.
-
IN-VACUUM MIRRORS:
In-vacuum mirrors are in the process of being assembled with the
appropriate mirrors and beam splitters.
-
40 M IFO PRE-ALIGNMENT:
Alignment apertures are in place before the MMT. Alignment targets for the
IR autocollimator beam were cleaned and ready for installation. The IR
autocollimation equipment has been staged in preparation for the pre-alignment.
-
PHOTON DRIVE R&D:
Tom Essinger-Hileman has re-designed the 40m photon drive optical layout so
that we can provide four bounces onto the same spot on the MC2 mirror. He
has wired up and tested the 0.500 mw 1047nm laser and the photdetectors. He
is in the process of setting up the SR 560 servoamp with Osamu's help to
stabilize the laser's intensity.
Aidan Crook received valuable information from working with Peter
Fritschel at MIT. He has completed a simulink model of the 40m PSL/mode
cleaner system with the addition of a photon actuation loop. He is in the
process of determining the suitable frequency range over which the photon
actuator loop will be able to perform length control of the mode cleaner.
- Mode Cleaner (Miyakawa)
- During installation, the PSL beam has been
going through MC1 and MC3 (with the "wrong" polarization
to increase transmission), with no attempt to lock
the MC in air.
- Matt continues to develop his model of the MC WFS system.
He has validated his Simulink model of the optical plant
with independent Matlab and Mathematica models.
-
South Annex Bake Ovens (Taylor):
- Bob coimpleted a set of baffles for LLO
and shipped them out on Monday.
- Work on the LHO baffles is in progress.
- Bob continues to do quick clean and bake jobs
of misc components for the 40m installation
(irises, counterweights, pigtail cables, etc).
- Bob continues to re-supply the South Annex lab
with consumables such as cleaning chamicals, wipes, clean bags, etc.
July 18, 2003
- Installation (Vass, Ugolini, Miyakawa, Smith, everyone):
- The 40m was vented on Tuesday 7/8 without incident. We did notice,
however, that the ion pump currents rose somewhat after the pumpdown
even with their gate valves closed. One has since begun to decrease,
and John Worden has told us the rest will probably follow suit.
- Steve moved the MC2 feedthroughs to the east side of the
MC end chamber, and put a window on the back of the chamber for
Mike Smith's photon actuation experiment. A 4'x3' table has been
placed next to the window as well, for Mike/Tom's laser.
- Several irises have been cleaned by Bob, and were installed
on Friday 7/11 to lock down the laser alignment.
- The old steering mirrors for PSL->MC, MC->MCR, and MC->MCT
are being replaced by mirrors with better (DLC) mounts,
with due attention to polarization (unlike before).
- The PSL beam was observed to flash through the MC (in air),
verifying the correct alignment of all the above changes.
- The remaining input optics (Faraday Isolator,
mode matching telescope, various steering mirrors and
pickoffs, PZT steering mirrors, etc) are installed
and are being aligned to the PSL beam.
-
A procedure for pre-aligning the 40M IFO was developed by Mike Smith
and described in the
document T030141-00, which is in the process of being finalized. Alignment
targets were designed and manufactured and are in process of being cleaned
and baked. The IR autocollimation equipment has been staged in preparation
for the pre-alignment.
- The first step of the procedure is to use the PSL beam
to align the IO train through the Faraday isolator,
and lay down defining irises. This step is nearing completion,
and the PSL beam will no longer be needed for alignment.
The 2nd step uses the IR autocollimator to align from the ETMs
back through to the Faraday Isolator, for the hand-off.
We are beginning this phase now.
- We hope to install both ETMs by the end of this week,
so as to pursue the alignment 2nd phase,
and to facilitate debugging of the ETM DSC's.
- We have decided to NOT install the PRM and SRM
during this vent, to make the commissioning of the
FabryPerot Michelson easier.
We'll have to shedule another vent, some months from now,
to install the recycling mirrors and re-align everything.
Meanwhile, the mirrors will sit in the clean flowbench in the south annex.
- Steve is continuing to assemble and prepare
all the misc things that must be installed, including:
optical-quality viewports, in-vac oplev mirrors,
cameras, beam dumps, shutter flags,
cables for the MMT picomotor, shutter flag picomotors, and
PZT steering mirrors.
- Electronics (B. Abbott, Heefner, Taylor)
- Ben has been testing the ETMY suspension rack 1Y9. The
auxiliary crate readbacks appear to be working fine, but the
front end crate is not.
Ben figures that we still need a Xycom
controller screen for the dewhitening switches;
Jay cranked one out yesterday.
Ben is now beginning the remainder of the ETMY testing,
and will move on to ETMX.
- We plan to install the ETMs in the next few days,
so Ben can try to damp them.
- All of the remaining electronics racks were anchored to
the floor last week.
- Ben continues to populate the LSC/ASC racks 1X2 and 1X3.
- Art is waiting for FLKM 64s to arrive from the sites so that he can
finish the LSC wiring in 1X3.
- Jay, Ian, and Calloway successfully prototyped their new
digital demodulation board using the PMC at the 40m PSL.
-
Optical levers (Bhatt, Goggin, Smith, Vass, Taylor):
- Naman and Lisa have looked at the signals from one oplev QPD
through the electronics chain to the EPICS screen.
- They found some channel assignment problems,
with help from Ben.
It turned out to be a code problem which Alex quickly fixed.
There seems to be another problem in the EPICS display,
a flipping of the sign of pitch or yaw; being debugged.
- Mike and Naman went over the oplev parts list.
All the parts for all 7 oplevs are in hand,
and Naman is assembling them on their proper tables,
and beginning the job of checking out the readout chain for each.
- Naman is thinking about what lens to put in front of the
QPDs, ie, what the optimal spot size should be.
We have a 10mm dia QPD, we figure a beam with
beam radius w = 3 mm should be about right.
Naman will use the beam scan to measure the beam size and divergence.
- Mike has to update the telescope design.
He designed it for 960 nm light, but we're using
read 670 nm laser diodes.
- Naman continues to learn about the oplev system and
Mike's telescope design. She'll assemble and test the prototype.
- Bob is making more cables for the optical levers.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor continues to refine his plan to re-layout the PSL.
Seiji has been thinking about, and plans to help with, these mods.
- Reducing the number of mirrors in the main beam path by 2
requires us to put both PZT steering mirrors on the periscope,
20 cm apart. Conor figures this is sufficient lever arm
to displace the beam at the MC input by a sufficient amount
to servo it effectively (should we choose to implement
the MC ASC this way, which we currently don't plan to do, anyway).
- Conor and Rich and Ben are modifying the frequency servo board
to bypass a slow slew-rate op amp with a faster one.
This should allow us to increase the UGF of the PSL FSS
from ~ 200 kHz to the neighborhood of 1 MHz.
- Conor has a clean way to switch the optical path of the
FSS pickoff from pre-PMC to post-PMC, easily,
and requiring no changes to the mode-matching lenses.
- Moving the FSS pickoff to post-PMC
*may* require us to compensate for the PMC pole
in the frequency servo board.
This change is easy to do and undo, to easily compare the noise
performance in both configurations.
-
Ben has put together and tested an ISS PD for Mike Smith so that he can
use it in his Photon Actuation tests.
Now he has to make a pile more, for the sites.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Received parts: Aluminum coated mirrors for optlev mirrors and additional
mirror posts and clamps were received. The mirrors for the PZT steering
assemblies were received.
-
Orders pending:
1 q-switch E/O shutter from Fast Pulse. Spherical collection mirror from
Rolyn for the BRDF meter.
-
FARADAY ISOLATOR:
Faraday isolator was placed inside the input chamber and is process of
final alignment.
-
OPTICAL LEVER ASSY:
Naman is staging all of the external and in-vacuum components.
-
IFO STEERING MIRRORS:
A revised layout was done to simplify the path between the two PZT steering
mirrors. The change reduced the path length between the IMMT and the ITM.
This effects the mode-matching slightly, but the mode-matching of the IMMT
can be re-optimized to < 10E-6 by changing the defocusing of the telescope
from the pre-focused value of 1.2 mm to 1.1 mm; the correction is less than
the uncertainty in the pre-focus of the telescope, and this change will be
made with the Pico motor once the IFO is locked. The new placement of the
displacement steering mirror still provides a range of displacement of the
IFO beam at the PRM of +/- 1mm. The PZT steering mirrors are awaiting
installation in the vacuum chamber.
-
SPS BREWSTER PRISM MIRROR:
Installed in vacuum chamber.
-
IMMT:
The input MMT was placed inside the input chamber and is process of final
alignment.
-
IN-VACUUM MIRRORS:
In-vacuum mirrors are in the process of being assembled with the
appropriate mirrors and beam splitters.
- PHOTON DRIVE R&D:
Tom Essinger-Hileman has designed the optical system using the ABCD matrix
formulation with Mathematica, and has established three congugal image points:
the laser spot, the spot on the mirror, and the spot on the ISS PD.
He has made a layout of the 40m photon drive
experiment using ACAD. All of the parts have been received for the
apparatus. Tom and Steve installed a 3ft x 4ft optical table at the end of
the MC chamber for mounting the apparatus, and Steve moved the OSEM wiring
to the side viewport and installed a new viewport in the end of the MC
chamber. Tom completed an analysis of the change in photocurrent as a
result of beam displacement jitter and spot size on the surface of the QPD.
He is working on a new layout in which the laser beam is sampled before
hitting the mirror, rather than the present design which samples the
returned beam.
Aidan Crook is at MIT working with Peter Fritschel.
- Mode Cleaner (Miyakawa)
- Osamu recentered the MC beam on MC2 before the vent, and
realigned all of the MC optics.
- Osamu found that the
dewhitening filters for the MC1,2,3 DSC's,
which have had repeated switching problems,
were still off. He jumpered back
in a filter that had been bypassed, and will work with
Ben and Jay to make sure these switches work in the future.
- With that change, the mode cleaner noise is now as good
or better than it ever was!
It is dominated by seismic noise below 30 Hz.
From 30 Hz on up, it is as good or better than specs,
except for a forest of peaks near 200 Hz which is
associated with acoustic noise on the PSL table.
Conor's mods (see above) should reduce this.
- Osamu still thinks there's excess electronics noise
which can be improved. The mods to the FSS to increase
its UGF (see above) should help at higher frequencies.
Osamu plans to replace the resistors in the DSC coil drivers,
which should reduce the electronics noise in the 100 Hz region.
- Osamu had reduced the gain of the position, pitch and yaw
damping in all 3 MC DSC's, from 1.0 to 0.1,
so that the Q's of the pendulum modes went from ~4 to ~ 40.
He found that this was helping reduce the noise.
Now, with the above changes and fixes,
he no longer needs to do this;
gains are back up at 1.0.
Mode Cleaner WFS system (Ourjoumtsev, Abbott, Eichenfield):
-
Alexei had a very productive July 4 weekend before leaving us.
He has commissioned the MC WFS system and ASC feedback to
MC2 and MC3 P/Y (four feedback loops). He has used it to demonstrate:
- If you misalign the mode cleaner "by hand" (changing the offsets
on MC2 and MC3 P/Y), the MC transmitted power falls.
Switch on the ASC, and the alignment and transmitted power
quickly go back to their optimal points, and the transmitted power
becomes more stable.
- Transmitted power is observed to decline by a factor ~ 2
overnight, presumably due to thermal variations.
With the ASC system on, transmitted power remains stable for many hours.
- The noise spectrum of the transmitted power was measured
with ASC off and on.
With ASC off, there is a large peak at microseim and at the
various pendulum frequencies ~ 0.85 Hz.
With ASC on, that peak disappears, but new (smaller) peaks at ~2-3 Hz
appear. Presumably, this is an artifact of un-optimized
feedback filtering, and can be eliminated.
-
This is a tremendous acheivement!
Alexei has documented these measurements, along with a first-draft
"User manual":
Preliminary report on Mode Cleaner WFS alignment system commissioning.
- Conor and Matt absorbed the final
core dump from Alexei
on both the WFS and EO shutter systems,
before he returned to France.
They will pursue the optimization and full characterization of the system,
over the summer (once our vent is over and the MC is back in operation).
- Matt is also working
on his WFS Simulink model and making great progress.
He and Conor have found some errors in some of the WFS documentation.
He is emailing lots of questions to Daniel Sigg and Nergis.
-
South Annex Bake Ovens (Taylor):
- Bob is working on the baffles for LLO.
Since this is high priority, it preempts all his 40m work.
- Bob continues to do baking and scanning
for the Gingin hybrid OSEMs and associated parts, for Janeen.
- His small sonic cleaner has broken again, but the larger one is
still fine.
- Bob continues to work with Steve and Mike to get all the
parts to be installed in the vacuum prepped and ready.
July 4, 2003
- Alexei leaves next week. In his six months at the 40m,
he has made major contributions to all aspects of the project,
often working for 14 hours a day.
Amongst his more major contributions:
He laid out most of the sensing beamlines.
He helped assemble and commission the Faraday Isolator.
He developed a powerful and easy-to-use Gaussian beam propagation
analysis tool.
He assembled, installed, and fully commissioned the EOS system.
He has assembled and commissioned the MC ASC system, almost
single-handedly; a tremendous acheivement.
We are immensely grateful to Alexei, and hope he comes back soon!
- Core digital suspension controllers (DSC), LSC, ASC,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- The vertex DSC's have been running fine since Rolf's changes.
- The end DSC's are still being commissioned by Rolf and Ben.
- Ben has been testing the auxiliary (EPICS) controls in
the ETMY rack. He found and fixed problems with switching
the dewhitening filter (the XY220 outputs need to be re-set
via an epics screen after reboot).
Aside from this, ETMY looks ok, and Ben is moving on to ETMX.
- Bob replaced the fiber link to ETMX. Rolf is now working
on getting the ETMX and ETMY front end code running.
- From Rolf:
Continued installation of 40m lab ETM controls. We were having problems with
ETMY controls, as the 110B ADC was only reading zeros, and, after a few hours,
the reflected memory would lock some bits. We replaced the RFM card, and now
everything seems fine. Don't have a clue what this had to do with the ADC
readings.
- Ben has stuffed the ASC & LSC racks as much as can be done for now.
All of the VME and Eurocard crates are in, and are stuffed with the modules
that we have so far.
Todd is keeping Ben appraised when the new modules will be complete.
- The cross connect lists for the ASC and LSC have been generated by Jay.
The 1X3 rack was put into place last week.
Art is busy making up the cross connects for the LSC/ASC racks.
1X2 is now complete, and 1X3 is coming along nicely.
Ben will be helping Jay and Rolf
install and commission these systems in the coming weeks.
- From Jay: The QPD to ICS110 interface module layout
has been completed and the
board was sent out for fab by 6/27. Boards should be received back
in two weeks.
- Lisa has more-or-less completed the cabling of the
video cameras to the switch and the monitors;
she needs a bunch more ables to complete it.
Her EPICS-based controls work well.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu adjusted the MC gains, and it is now locking
quite robustly.
It didn't even lose lock when holes were drilled into the
concrete floor to secure the LSC and ASC racks.
- Osamu measured the OLTF and the the frequency noise
of the MC servo, and comparing it to what it was before the
DSC re-wiring (2 months ago,
when it met specs over almost the entire
frequency range).
At first, it was 100 times worse, in the 20-700 Hz range;
due, presumably, to changes in the MCL actuation path.
He added a low-pass filter for MC2, which improved the noise
but it was still 15 dB higher than before.
He and Dennis searched through all the changes,
and found problems with the control
that switches between software and analog dewhitening.
Ben fixed that. Software dewhitening
contributes to the noise, so we are using analog dewhitening.
-
Still, changes to the analog and software filtering
that no longer adequately filter DAC noise
appear to be causing the excess noise.
-
Osamu found that a resistor in the coil driver
was not the right value;
changing it would reduce this DAC noise,
but also reduce the dynamic range of the coils.
He will consult with Jay about what to do.
- Osamu measured the OLTF of the DSC loops for the MC2.
With a gain of 1, he measured a Q of 4.
Then he turned down the damping gain to 0.1 (Q ~ 40),
and found reduced noise in the MC servo.
We don't understand this, but for now,
we're keeping it that way.
-
Mode Cleaner WFS system (Ourjoumtsev, Abbott, Eichenfield):
- Alexei has been working like mad; he's leaving next week.
Conor and Matt have been helping and learning
about the MC WFS system from him.
- Alexei found a 3 MHz oscillation on one WFS head,
and traced it to a wrong component on the board; he fixed the
board and eliminated the oscillation.
- He changed some capacitors on WFS head 1;
Ben will do the same for WFS2.
- Now, Alexei give a clean bill of health
to all the WFS hardware (modulo the point above).
- Alexei checked and tuned the gains and RF phases
on all 2x4 WFS quadrants, to give zero readings
for aligned MC mirrors and maximal signals for misaligned mirrors.
The gains on all the demod boards are within 20% of each other.
- He adjusted the Guoy telescope lens for WFS1
to provide maximal signal from a misaligned MC2,
and is now in the process of doing the same for
WFS2 -> MC3.
-
If we intend to feed back on the PZT input beam steering mirrors,
we'd set the relative Guoy phases of WFS1 and WFS2 to be
90degrees apart. But, instead, we think we'll beed back to
MC2 and MC3.
MC3 is 60degrees of Guoy phase away from MC2.
So, the Guoy phase for WFS2 will be set accordingly.
- Alexei saw some pitch/yaw coupling from MC2 -> WFS1.
He developed a simple alignment procedure to minimize /
eliminate this, by adjusting the height of the Guoy telescope lens.
- Alexei chose some default digital filters and gains,
and closed the WFS1->MC2 loop.
First he misaligned MC2; when he closed the loop,
it brought MC2 back to the right spot,
maximizing the transmitted beam intensity.
He observed a marked reduction in
fluctuations in the transmitted beam intensity with the loop on.
ie, it works!
- Then, he measured the 2x2 DC transfer matrix from
MC2,MC3 -> WFS1,WFS2. He inverted this and input it into the
servo matrix.
Then he turned on the full 2x2 loops in both pitch and yaw.
Again, it worked quite nicely, taking out misalignments
and reducing the transmitted beam intensity jitter.
- Much more tuning is necessary to optimize the MC ASC servos,
including better filtering and calibration and Guoy telescope optimization;
this work will be continued by Matt.
- Matt is developing a Simulink model of the full WFS
alignment system for the Mode Cleaner.
He's making good progress, with help from Hiro,
and papers by Mavalvala and Sigg.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor is ready to re-layout the PSL, to
(a) reduce the number of mirrors in the main beam path by 2, and
(b) pick off the FSS beam after the PMC, rather than before.
- A problem with (a) is that mode-matching lenses
will have to be placed after the first PZT steering mirror.
Since this doesn't sound like a good idea,
Conor is evaluating how much worse the beam steering will be
if the two steering mirrors are both on the periscope,
close to each other.
- A problem with (b) is that it didn't seem to help at LLO
or at LASTI. Conor will talk with Nergis and Peter Fritschel
to see if they think it is a bad idea or not.
Meanwhile, Conor is prepared to do only (a), and (b) later if desired.
-
The box panels for the ISS PD boxes are now complete. Their PCBs are
being stuffed, and a few should be available next week, as Mike Smith
wanted me to make a set for him, and then we will have more for the ISS
testing.
- Jay and SURF Ian plan to test out their Digital Demod board,
which operates out to 207MHz, on our PSL PMC servo loop.
Tentative plan is to do this on Monday Jul 7.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa, Arai):
-
OPTICS PARTS LIST,
Orders pending:
1 q-switch E/O shutter from Fast Pulse.
-
MODE MATCHING TELESCOPE:
Assembly is complete, awaiting installation.
-
FARADAY ISOLATOR:
Assembly is complete, awaiting installation.
Mike and Alexei measured a transmission of 97% and
extinction ratio of 4e-4, better than specs.
-
OPTICAL LEVER ASSY:
Updated parts list was given to Naman. Aluminum coated mirrors and
additional mirror posts and clamps were ordered.
-
IFO STEERING MIRRORS:
Steering mirrors mounts with PZT platforms were assembled. The mirrors were
ordered (off the shelf).
-
SPS BREWSTER PRISM MIRROR:
Assembly is complete, awaiting installation.
-
MISSING PARTS:
All is well that ends well; the 10 DLC mounts were found in the 40m optics
lab, and are ready for installation.
-
IN-VACUUM MIRROR:
A list of in-vacuum mirrors was made and the mirrors are in the process of
being assembled with the appropriate mirrors and beam splitters.
- A camera for looking at the beam entering the Faraday Isolator,
and associated telescopic lens and in-vac mirrors,
is being prepared for installation.
- PHOTON DRIVE R&D:
Tom Essinger-Hileman is designing the optical system using the ABCD matrix
formulation with Mathematica. He has made a preliminary layout of the 40m
photon drive experiment using ACAD. Most of the parts have been received
for the apparatus. Steve Vass will place a 3ft x 4ft optical table at the
end of the MC chamber for mounting the apparatus and will move the OSEM
wiring to the side viewport; the actuation beam will enter through a new
viewport in the end of the MC chamber and will reflect from the back side
of MC2 mirror. No steering mirrors will be needed on the MC2 optical table
inside the chamber. Tom has written a progress report.
Aidan Crook has made a Simulink model of an SOS mirror suspension having
displacement and pitch motion with photon force actuation on the mirror;
the model includes velocity damping for both motions. He has written a
progress report.
-
Optical levers (Bhatt, Goggin, Smith, Vass, Taylor):
- SURF Naman Bhatt and Bob are working on completing
the remaining cabling for the oplev photodiodes
for all 7 core optics. Most of the vertex optical levers
are cabled; the ends will be done soon.
- Naman is learning about the oplev system and
pursuing some relevant calculations.
She's playing with the oplevs that are already set up
near the beamsplitter chamber.
She's working on getting the signals into EPICS
and the DSC front end, and calibrating the response.
- Electro-optic shutters (Smith, Ourjoumtsev):
- Alexei completed the installation and tuning of the
EOS on the MCR beam line, and has documented the system
and tuning procedure. We will complete the other two EOS's
(for the SP and AP beamlines) later;
we're still waiting for delivery of a 3rd Q-switch.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- We plan to vent for installation next Tuesday, Jul 8.
Dennis has written an installation plan.
Over three weeks, we will
install and damp the remaining core optics (ETMx, ETMy,
PRM, and SRM). We are debating whether the PRM and SRM
will be installed in their correct location,
or temporarily in another chamber.
We'll install the Faraday isolator, mode matching telescope,
PZT steering mirrors, input and output beam
folding mirrors and pickoffs, shutter flags,
irises, baffling.
We'll install optical quality output port mirrors,
including one on the MC2 chamber for photon actuation.
-
Then we'll align everything. Mike Smith is writing up
an alignment procedure using his autocollimator.
We hope to re-commission, with the PSL in air,
by the 3rd week in July.
So, this is a very major installation!
- After the first few days of vent, when the
PSL beam path is fully defined via irises and initial pointing spots,
Conor will re-layout the PSL.
- Dennis, Conor, and Matt calculated the effect of refraction
on the (IR) beam over 40m of air and estimates it to be displaced
by 28 microns (28 cm for 4km). Negligible for us!
- Steve is completing an inventory of all the things that will be
installed. He's getting the remaining items: cameras, oplev mirrors,
beam dumps, and
cables for the MMT picomotor, shutter flag picomotors, and
PZT steering mirrors.
- Steve has received all the remaining cameras
and lenses we need.
- Racks 1X1, 1X2, 1X3, 1X4, and 1Y9 are being bolted to the concrete floor.
-
Modeling (Miyakawa, Goggin):
Lisa continues to learn about Finesse and develop a model
of the 40m and AdvLIGO with that tool.
-
South Annex Bake Ovens (Taylor):
- Bob lost then found the DLC in-vac mirror mounts.
- Bob continues to work with Steve to get all the
parts to be installed in the vacuum prepped and ready,
including the cables for the shutter flags and PZT
steering mirrors.
- Bob is assembling 11 more hybrid OSEMs for Janeen & Calum.
- Bob is preparing several big bake jobs for Gingin suspensions.
June 20, 2003
- Core digital suspension controllers (DSC), LSC, ASC,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- Status of DSC system:
Over the last 2 weeks, Rolf and Alex Ivanov have
consolidated the two reflective memory (RM) networks,
fast controls and DAQ, into one 2Gbit network.
After some struggle, it is back up as a single network,
and the DSC system and DAQ are running fine.
- Art and Bob have completed the wiring and cabling of the end racks.
However, one fiber run is bad, and the second is suspect.
Both will be replaced when new fiber arrives
in the next week.
- The DSC system software for the ETMs is mostly in place
but is currently not operating.
Ben is back from vacation and is waiting for Rolf
to come back and get the ends processors up and running,
so that he can
check out the auxillary and front end wiring and code.
- However, timing issues still prevent the operation
of the AWG (arbitrary Waveform Generator, which must be synched
with the DAQS). Currently, the AWG is disconnected.
- Status of LSC/ASC electronics, from Jay:
- Art has started cross connect wiring and assembly for the LSC.
- The 1X3 rack will be put in place, in the next week.
The Sorenson power supplies will be put in a separate rack
nearby, to minimize EMI.
- An inventory of required modules has been generated. Modules that are
not on hand will be procurred or fabricated.
- Layout of the QPD to ICS interface board has not been started due to
other higher priority tasks.
- Jay found an error in the wiring drawing for the 1X1 auxiliary rack.
He fixed the wiring, and now Ben is fixing the drawing.
- Lisa continues to complete the cabling of the many video cameras
and refine tyhe EPICS controls.
Quad splitters are in place, and monitors are in place in the control room.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- The DSC and MC electronics are back up, and the
MC suspensions are damped.
- Osamu worked on re-acquiring MC lock.
Since several things
had changed in the last few weeks, this was not an easy task:
- the modulation index was modified as discussed below;
- an offset in the MCS error signal was traced to AM modulation
due to imperfectly aligned polarization after the changes
to the pockels cell path. This was fixed, as discussed below;
- The MCL signal was not getting to the DSC system.
The C1IOOVME processor was rebooted, and that fixed it.
- The EOS was fully commisionied in the MCR path, and its setting optimized,
as discussed below.
- The MC is now locked robustly. Visibility is now ~ 97%,
better than it's ever been.
- However, the error signal is observed to drift over hours.
This is likely due to changed MCL gain.
- Osamu is now measuring the OLTF and noise spectrum,
and is optimizing the gains, cross-over frequency,
and other parameters, to improve lock stability and
minimize the frequency noise.
- After tuning gains, the MC lock is extremely stable.
However, the noise is much higher in the 30-1000 Hz range
than before. Prime suspect is electronic noise due to the new
MCL signal path. Under investigation.
-
Mode Cleaner WFS system (Ourjoumtsev, Abbott, Eichenfield):
- Alexei and Matt are recommencing
work on commissioning the IO WFS system
now that the MC is back in lock
and the EOS is in place.
They need the AWG, which is not currently working,
so this is hampering their progress.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Matt, Conor, Osamu et al measured the modulation depth
of the MCR sidebands with an OSA and found it to be quite small.
Matt traced the full electronics path for the modulation
depth setting from EPICS to the pockels cell.
- Conor and Stan realized that the wrong polarization
was being sent through the pockels cell:
it was P (as in the site drawings) but should be S.
(One wonders how the PSLs could be working at the sites,
but we guess this is yet another example of changes made
at the sites that are not documented sufficiently well for
us to find them).
- Conor inserted a HWP to rotate the polarization,
and he and Osamu tuned it's orientation, re-aligned the Pockels cells,
and re-measured the modulation depth. It was a healthy 0.1.
- Conor and Dennis set up a standard set of power levels
on the PSL table. It's now ~ 8.3 watts out of the MOPA.
It is now being attenuated to 1.0 W into the PMC,
~ 0.6 W out of the PMC, 0.5 W at the periscope.
It can be attenuated further at the periscope if desired.
Changing the power level upstream of the PMC will require
changes to the FSS gain, PMC servo gain, etc;
so we won't do that unless we need to.
- Conor's plan to re-layout the PSL is finalized.
We will begin this work during the installation vent,
which is tentatively scheduled for June 30.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa, Arai):
-
OPTICS PARTS LIST,
Orders pending:
1 q-switch E/O shutter from Fast Pulse.
-
FARADAY ISOLATOR:
Assembly is expected the week of 6/16.
-
IFO STEERING MIRRORS:
Parts are cleaned and baked. Assembly is expected the week of 6/16.
-
SPS BREWSTER PRISM MIRROR:
Parts are cleaned and baked. Assembly is expected the week of 616.
-
MODE MATCHING TELESCOPE:
Telescope is aligned and is awaiting installation.
-
OPTICAL LEVER ASSY:
SURF student Naman Bhatt has begun working on the optical lever
telescope assembly.
- PHOTON DRIVE R&D:
A SURF student, Tom Essinger-Hileman,
has begun working on the photon drive experiment at the 40m IFO at CIT.
A second SURF student, Aidan Crook, will arrive the week of 6/23
to begin work on modeling the advanced LIGO photon drive system.
- Electro-optic shutters (Smith, Ourjoumtsev):
- Bob and Alexei have completed the EOS EPICS wiring.
- Alexei has completed the commissioning of the EOS on the MCR beamline.
It works well, including all the EPICS controls.
It was tested with the MC: when the MC lock was broken,
the EOS closed, allowing in a small amount of light to re-acquire lock.
MC lock was quickly required, and 100 msec later,
the EOS opened; the MC remained locked.
- Alexei has established correct settings of the EOS
for different power parameters. He has documented the system,
including some nice transparencies.
- He is now moving on to fully instrumenting
the remaining two EOSs (on SP and AP).
We still await delivery of a 3rd Q-switch;
most everything else is in place.
- Electricians will bring bAC power to the small racks
containing the EOS equipment, by the end of the week.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- We tentatively plan to vent for installation on June 30.
If WFS commissioning requires it, we can delay this for a week.
- Steve is getting together all the things that will be
installed: the suspended ETMx, ETMy, PRM, SRM;
the mode matching telescope, Faraday isolator, PZT stering mirrors,
main laser folding mirrors, oplev mirrors, shutter flags.
- Steve found some problems with the shutter flags,
and had the shop re-machine them. Bob vacuum-prepped them.
- Steve and Bob will arrange for in-vac "pigtail" cables
for the MMT picomotor, shutter flag picomotors, and
PZT steering mirrors.
- Steve is ordering more cameras, and a wide-angle lens
for the PSL table.
- The portable A/C is now working in the control room.
-
South Annex Bake Ovens (Taylor):
- Bob sent the vac-prepped errant beam baffle parts to LHO, and they
have been received.
- Bob finished the vac-prepping of the picomotors
used to drive the shutter flags,
and is now vac-prepping the remaining shutter parts.
- Bob is preparing 10 more hybrid OSEMs for Janeen.
June 13, 2003
- Koji Arai helped Mike Smith and Alexei Ourjoumtsev
re-assemble and align the vacuum-prepped
mode-matching telescope and Faraday isolator
before he left, and is preparing a writeup of the procedure.
- Lisa G and SURF students Matt and Naman are going through
daily lab checklists, using EPICS, dataviewer and the iLog.
- Osamu returned from Japan, where he helped
Kentaro lock his 4-meter signal-recycled Michelson, detuned.
They moved on to the signal-recycled
Fabry-Perot Michelson, in broad-band RSE.
After much tuning and aligning, they were successful
in both configurations.
He modeled the error signals and power outputs with Finesse,
and saw good agreement with the experiment.
- Core digital suspension controllers (DSC), LSC, ASC,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- From Rolf:
- Primary goals for this week are to get the ETM controls installed and running
the the 40m lab and, now that we have enough high speed (2Gbit/sec) network
interface boards, to remove the slower network completely from the 40m lab and
go with the single fast network.
- The first objective is almost complete. The ETM control PC and ETMY VME systems
are installed and running. There is about a day of testing remaining, primarily
DAQ and GDS connections. The ETMX VME is a direct copy, so should come up
quickly after ETMY testing.
- The move to the single network is complete, but there was a snag. The Arbitrary
Waveform Generator (AWG) software was written to run on the older MIPS
processors, but the new network cards do not work on these CPU boards (don't
even get power indications on the cards). So, we have had to port the AWG code
to Pentium processors. While this seemed straight forward and compiled fine, it
did not work properly. It looks like Alex got it running last night though, so
we'll test it more thoroughly today.
- From Jay:
- The databases, processors and VME modules for the ends are installed
and operational. Medm screens need to be generated. Checkout of the
racks will begin next week.
- From Jay:
- All rack drawings and wiring diagrams for the ASC and LSC are now
complete.
- Cross connect fabrication will begin next week and should take about 2
weeks. Rack assembly will begin after the cross connects are complete.
- The schematics for the new QPD to ICS interface moduel are complete.
Board layout will begin next week.
- Art and Bob have been completing the remaining cabling
to/from the ETM racks; just a bit more to do.
Dennis set up ethernet hubs at the ends.
-
Dennis set up memory dipswitches on 1X1 VME boards with Alexei.
- Lisa has got the video EPICS controls working, and
succeeded in getting signals to the control room projector and monitor.
So right now we can see ITMX, ITMY, MC13 & MC2.
She's running cables from the PSL and IMCR & SPS beamline
cameras to the switch, with help from Bob.
She has added illuminator buttons to the video EPICS screen,
and is refining the layout.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- The DSC and MC electronics are down,
while Rolf and Alex make big changes.
- Osamu is back, and preparing to
optimize the gains, cross-over frequency,
and other parameters, to minimize the frequency noise.
-
Mode Cleaner WFS system (Ourjoumtsev, Abbott, Eichenfield):
-
Due to the DSC and PSL activities, WFS commissioning
has been less productive than last week.
- Alexei tuned the second WFS demod board
- Alexei measured DC gains on both WFS heads.
- As soon as the MC is back up, Alex will
measure the RF gains and match the overall phases on the WFS.
Then he'll move the PZT mirrors with dtt.
Then he can finally start taking transfer functions
and commission the servo loop.
- Matt is helping Alexei with the WFS work
and is learning all about it, to continue that work
when Alexei leaves.
- Matt is working through Eric Black's paper on PDH locking, w
hich led him to working out the FP arm reflected beam properties
when it is not in equilibrium with the cavity
(found a good paper by Benno Wilke and Robert Byer)
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Plan to re-layout the PSL sometime in the next two weeks.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa, Arai):
-
OPTICS PARTS LIST,
Orders pending:
1 q-switch E/O shutter from Fast Pulse.
-
FARADAY ISOLATOR:
Assembly is expected the week of 6/16.
-
OPTICAL LEVER ASSY:
Assembly on hold.
-
IFO STEERING MIRRORS:
Parts are cleaned and baked. Assembly is expected the week of 6/16.
-
MODE MATCHING TELESCOPE:
Telescope is aligned and is awaiting installation.
-
SPS BREWSTER PRISM MIRROR:
Parts are cleaned and baked. Assembly is expected the week of 616.
- Electro-optic shutters (Smith, Ourjoumtsev):
- Alexei realigned the EOS after modifications on the PSL table.
Transmission goes from 0.025% to 98%, half-wave voltage is 3.79V.
- Alexei is commissioning the EPICS control of the EOS's.
Bob did some of the cabling for it.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Steve Regenerated cryo. Maglev is still noisy a bit.
- Steve ordered quad splitters for video monitors.
- Steve helped Koji with mode-matching telescope alignment.
- Steve measured 670nm transmittance of 40m safety glasses.
-
South Annex Bake Ovens (Taylor):
- Bob is doing a bake job on some more of the LHO baffle parts for Ken
Mailand, they are in the oven now.
- Bob is doing the clean and bake of the Pico Motors
used to drive the shutter flags.
- Bob has received the spare MOS and SOS suspensions to be baked
when he gets a chance.
June 6, 2003
- Koji Arai is visiting from TAMA,
and is helping Mike Smith and Alexei Ourjoumtsev
re-assemble and align the vacuum-prepped
mode-matching telescope and Faraday isolator. Thanks, Koji!
- Core digital suspension controllers (DSC), LSC, ASC,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- Dennis and Jay debugged and fixed some problems with a dewhitening
board for the DSC.
- Ben and Art are populated the two end racks
(ETM DSC's, oplevs, QPD's, etc),
and wiring is close to completion,
including 40m runs of fibers.
Almost all of the hardware is there;
Rolf will install the Pentiums, linux box,
RM fiber loops, etc, on Monday.
- From Rolf:
Primary work this week is to complete end station software for 40m lab.
The PC side is complete. The VME is 95% complete, with only the GDS
EXC/TP function to add.
We will install and start testing the system at the 40m lab on Monday.
At this time, we will also remove the present separate DAQ network and
move all traffic onto the new high speed network. The DAQ controller, TP
manager, and Arbitary Waveform Generator (AWG) code has been modified to
accomadate this move. The AWG code has also been ported to move onto a
Pentium CPU instead of the MIPS CPU, as used at the sites.
- From Jay:
first draft rack and wiring diagrams for the ASC and LSC
are complete and under review.
These include a new board for interfacing the beam line QPDs
to an ICS110B for beamline servoing.
Hope to get started on these racks in the next couple of weeks.
- Lisa is making progress on adopting the
Hanford video switch control state code, EPICS database,
and PICS screens, for the 40m.
Steve ordered monitors for the control room, they are expected
in the next week.
- We have been unable to use dtt to take transfer functions,
because the computer clock was not synch'ed to GPS
to less han 1 second. Lisa Bogue, Dennis and Rolf debugged
the problem and determined that the Sun's
clocks drift by 0.7 secs every 10 minutes!
Lisa set up a cron job
to resynch with ntp (network time) every 10 minutes.
- Dennis has reorganized and rationalized the
/cvs/cds/caltech file directory, putting medm screens
in sensible places, etc.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- The mode cleaner has been locking reliably and robustly,
despite intensive work on the MCR beamline.
-
We still have to optimize the gains, cross-over frequency,
and other parameters, to minimize the frequency noise.
This can wait till Osamu returns next Tuesday.
- Conor noticed that the RFAM photodiode in the
MC transmitted path wasn't working, and will
look into it.
-
Mode Cleaner WFS system (Ourjoumtsev, Abbott, Eichenfield):
- Alexei and Ben have made much progress debugging the WFS
sensing electronics and PZT mirror actuation path.
They've actuated on the PZT mirrors, and observed hysteresis.
- Alexei has tuned all the WFS phases and offsets,
for WFS1, and will do WFS2 next.
- Now that we can use dtt, Alexei will begin
taking transfer functions for the open loop of the
alignment servo.
- Matt is learning about the system to develop a
simulink model of the servo, includin actuation on
both the PZT mirrors and the suspended optics.
- Suspended optics:
- Steve and Lisa re-hung the
SRM optic after baking, damped it, and prepared it
for installation.
All core optics are now either installed
or ready for installation, on the bench with their EQ stops engaged.
- When we install in the next month,
we'll probably put the PRM and SRM
off to a side, to begin commissioning a
"simple" Fabry-Perot Michelson.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor & Stan realized that the PSL beam
was going through the 3 pockels cells
with the wrong polarizations. Conor inserted
half-wave plates to correct it.
- Conor has completed a detailed layout of
the PSL which reduces the number of turning mirrors
and picks of the FSS beam after the PMC.
He has passed it on to Mike for updating the
detailed AutoCAD layout.
-
He and SURF Matt Eichenfield finished calculating
all the mode matching lenses that are required
for the new layout (mode matching into the
PMC, the FRC, the suspended mode cleaner,
and through the AOM and the EOMs).
They used Alexei's snazzy
beam optics GUI, as well as mode matching code by Matt.
- Alexei continues to develop his beam optics GUI.
- Plan to perform this re-layout while we install
all our in-vac components, sometime in the next few weeks.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa, Arai):
-
OPTICS PARTS LIST,
Orders pending:
1 q-switch E/O shutter from Fast Pulse.
It had fallen off their list; Mike put it back on.
-
FARADAY ISOLATOR:
Final assembly and alignment is expected the week of 6/9.
-
OPTICAL LEVER ASSY:
Assembly on hold.
-
IFO STEERING MIRRORS:
Parts are cleaned and baked.
Final assembly and is expected the week of 6/9.
-
MODE MATCHING TELESCOPE:
Telescope is assembled. Final alignment is expected by 6/6.
-
SPS BREWSTER PRISM MIRROR:
Parts are cleaned and baked. Assembly is expected the week of 6/9.
- SURF Naman Bhatt will implement the optical levers
and their use in local alignment sensing and control.
- Electro-optic shutters (Smith, Ourjoumtsev):
- Alexei installed one EOS on MCR, and it is operating
under manual control; work to get EPICS control
is progressing.
-
He has set the "open" and "closed" HV on the EOS so that the light on
the WFS's never gets too big during loss and re-aquisition
of lock, and so that there's sufficient light on the LSC PD
to re-acquire lock and not lose it when the EOS opens up.
He's working out how to change the settings if the
light power into the IFO changes.
- however, the EOS leads have gotten damaged,
and it may be serious. Under investigation.
- Electricians will get
AC power to the small racks
that hold EOS electronics, from rack 1X1, next week.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The STACIS active pre-isolation system
has one or more problems (faulted electronics?)
that needs attention...
- Power has been installed
for a portable A/C unit for the control room.
-
South Annex Bake Ovens (Taylor):
- Bob completed the vacuum-prepping of the
parts for the Mode Matching Telescope,
Faraday isolator, PZT steering mirrors, etc.
Bob is preparing all the traveller paperwork.
- Bob completed the bake of the SRM optic
and gave it to Steve to be re-hung.
-
The ultrasonic cleaning bath crapped out.
Bob repaired it, cleaned it out, and it is ready
for use again.
- Bob tuned up the Dycor RGA's, they now have
very good AMU resolution.
May 30, 2003
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Dennis and company diagnosed and fixed a set of problems
associated with the new MCL electronics path,
and the mode cleaner is now locking robustly.
- He measured the transfer functions from the
MC servo board to the coil driver.
He discovered a filter on the Pentek Interface Board
that apparently was implemented at LLO;
we don't know why it's there, but it didn't exist
in our old path; Dennis bypassed it.
He found a gain 10 stage in the digital PZ filter,
which is not a good place for it (it amplifies any offsets);
he took it out.
He found that the software filter that compensates for the
hardware dewhitening was not set correctly, and fixed it
Finally, he found that the RF local oscillator cable
was 180degrees out of phase with what was needed
(don't know why!). He shortened it.
After all that, the MC locked immediately and robustly!
-
We still have to optimize the gains, cross-over frequency,
and other parameters, to minimize the frequency noise.
This can wait till Osamu returns.
- Core digital suspension controllers (DSC), LSC, ASC,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- All 6 installed optics are damping well.
There is an issue with the Universal Dewhite board which is the
wrong Rev for the MC2 optic, however.
Dennis and Ben are fixing this.
- Ben and Art are populating the two end racks
(ETM DSC's, oplevs, QPD's, etc).
They are progressing rapidly and hope to complete
the wiring by Monday.
- Rolf is working on the software required for the end DSC's.
He reported last week that the work required
to prepare the end DSC software should only take a few days.
Rolf hopefully has the Pentiums, Penteks, RM cards
and fiber cables that are required.
- We will bring the GPS time signals from the
vertex area to both ends via long (40m) cables.
We hope this will work; if the signals degrade too much,
Jay and Ben are thinking about building an optical driver
for the signals.
- Jay reports that
work on the rack and wiring diagrams for the ASC and LSC has resumed
and should be complete by the end of the week.
- From Jay:
A new board for interfacing the beam line QPDs to an ICS110B has been
designed. After the wiring diagrams and cross connects ahve been
designed this board will be layed out and sent out for fab.
- Lisa continues to develop the EPICS controls
(screens, state code, and wiring and cabling) for the video switch,
and Steve is ordering monitors for the control room.
-
Mode Cleaner WFS system (Ourjoumtsev, Abbott, Eichenfield):
- Alexei has checked out all the IQ demod boards for the WFS system.
He is tuning the boards so that there's exactly 90degrees RF phase
difference between I&Q.
He's preparing to determine the overall phase to maximize
the misalignment signal.
- Alexei and Ben will continue to debug and commission
the photodetectors, electronics, and actuators (PZT mirrors
on the PSL table) for the WFS system.
-
We will pursue feedback to these PZT steering mirrors
and to the MC suspended optics; so we are following the work
done by Joe Kovalik and Valery Frolov at LLO.
- Alexei continues to prepare the EPICS screens
and databases that control the WFS system.
- It would be really nice to be able to use dtt
to produce a transfer function for the MC ASC.
However, dtt can't operate in real-time (for transfer
functions) unless the computer it runs on is synch'ed
with the data (GPS time) to within 1 second
(accd to Daniel Sigg). This requires NTP
to be running on the machine, to get the network
time from our gateway computer, which hopefully
can get the time from some accurate clock
on the campus net. It's not clear whether this
will be possible; we have asked Larry & Lisa to help.
We may have to purchase a GPS-based NTP server for the lab.
- SURF Matt Eichenfield is learning Matlab/simulink
to model the MC WFS system properly.
- Suspended optics:
- Bob will be baking the SRM optic this weekend.
Early next week, Steve will rehang it,
and prepare it for installation.
That's the last of the core optics to be prepared.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor wants to measure the cavity pole of the
pre-mode cleaner, but it is too high to measure by
conventional means. Nergis suggested that we
obtain a broadband AOM, and Conor will see if we
can scare one up.
- Conor continues to develop a detailed layout of
the PSL which reduces the number of turning mirrors
and picks of the FSS beam after the PMC.
He and SURF Matt Eichenfield are calculating
all the mode matching lenses that are required
for the new layout.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
-
OPTICS PARTS LIST,
Received parts:
1 Brewster's angle polarizer for SPS anamorphic prism steering mirror from
KLC; New mirror holders for PZT steering mirror.
-
Orders pending:
1 q-switch E/O shutter from Fast Pulse.
-
FARADAY ISOLATOR:
Parts are baked and ready for assembly.
-
OPTICAL LEVER ASSY:
Assembly on hold
-
IFO STEERING MIRRORS:
All parts are on hand, ready to be cleaned and baked.
-
MODE MATCHING TELESCOPE:
Parts are baked and ready for assembly.
-
SPS BREWSTER PRISM MIRROR:
All parts, except for the Brewster prism are baked and ready for assembly.
The Brewster prism is on hand ready to be cleaned and baked.
- Mike will work with visitor Koji Arai to
assemble, align, and prepare for installation,
the Faraday isolator and mode matching telescope.
They hope to begin the work by the end of this week.
- Mike is
working on designing an AdvLIGO R&D experiment
with a SURF student this summer to
study photon-force induced movement of a locked cavity mirror. The 40m mode
cleaner cavity curved mirror will be pushed with an external photon beam
and the loop response will be measured (photon calibrator).
It may be possible to actively
control the mirror position with the photon beam within a narrow frequency
band (photon actuator).
- Alexei installed one EOS on MCR.
It is not yet powered, so a half-wave plate is in place
to permit the beam to get to the MCR LSC photodiode and WFS's.
Unfortunately, the EOS controller box is dying on him;
he will work with Sander to debug it.
- Alexei continues to prepare the EPICS screens
and databases that control the electro-optic shutters.
Dennis has booted up the
the EPICS cpu (c1aux) in 1X1 which will control these devices.
He and Bob will get the remaining cables in place.
- AC power is being run to the small racks
that hold EOS electronics, from rack 1X1.
- Steve ordered picomotors and one controller
for our shutter flags
(one goes in front of every test mass,
to block or attenuate the beam if desired).
Bob has vac-prepped the shutter flag parts.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Steve got the cranes inspected.
The vertex crane did not work (again!).
The crane repair guy fixed it today.
- Steve has arranged for power to be installed
for a portable A/C unit for the control room.
-
South Annex Bake Ovens (Taylor):
- Cleaned and baked the parts for the Mode Matching Telescope.
- Cleaned, baked and shipped the Baffle parts for LHO.
- Cleaned and baked the Faraday Isolator parts.
- Cleaned and baked the Brewster Mirror ASSY.
- cleaned and baked the special fix in vacuum 1.5 Mirror Mount.
- Helped Art with wiring the So. End 1Y9.
- Cleaned calcite Prisms for Faraday Isolator.
- Finished Hybrid OSEMs for Janeen.
- Will finish cleaning and start bake job on silver mirrors tomorrow.
- will start bake job on ETM optic tomorrow.
May 23, 2003
- SURF Matt Eichenfield from UNLV has begun work
at the 40m.
He's starting by working with Alexei on the MC WFS system.
Welcome, Matt!
- Core digital suspension controllers (DSC), LSC, ASC,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- All installed optics (MC1, MC2, MC3, BS, ITMX, ITMY)
are damping well with the new DSC system.
-
Dennis and Conor completed the diagonalization
of the sensor readings for MC1, MC2, MC3,
starting with the P/Y biases they obtained
from their recent alignment work.
The results were reproducible,
and close to what they were before we tore apart the DSC system.
They will move on to diagonalizing the outputs (coils).
They will then move on to diagonalize the core optics DSCs,
and optimize the damping gains.
- Ben rearranged the end rack drawings to reduce the number
of needed VME crates by one per end.
The drawings have been reviewed by AJW and Jay,
and Ben has begun to assemble all the hardware for the end racks
(all of which should be in hand).
-
Rolf reported last week that the work required
to prepare the end DSC software should only take a few days.
We are aiming towards completion of the system
before Ben leaves for vacation in less than 2 weeks!
- Ben matched the gains and filters in the Generic DAQ Intfc Board
in 1Y2 (new read-out for fast PSL and MC signals)
to the requirements.
- Jay reports that the drawings for the core IFO
LSC system, and for much of the ASC system,
are almost complete; he just needs to add in some
QPDs. He is contemplating designing a new board to interface
QPD signals into an ICS110B for DAQ.
He thinks that an LSC system can be assembled by July.
- Ben has updated the drawings for the 1X1 auxiliary rack
(EOS's, mech shutters, video switch, illuminators),
and has implemented the changes in the 1X1 wiring.
Lisa is cabling up the cameras to the video switch.
Dennis and Steve will order some monitors.
Dennis and Lisa are preparing the EPICS code to control
all these devices (c1aux).
- Alexei is preparing the EOS EPICS screens.
We aim to complete this system in the next week or 2.
- We need to run AC power to the small racks
that hold EOS electronics. Steve & Ben will pursue.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
-
The MC1, MC2, and MC3 optics are all damping well,
and the DSC's have been diagonalized.
- Dennis and Conor improved the alignment of the mirrors
(looking at TEM00 fringes on the cameras)
in preparation for acquiring lock with the new system.
- Lock acquisition has been problematical.
The MC_F path to the PSL appears to
be behaving normally, but the MCL path is not. Which
makes sense, because only this path had changes made:
Signal digitized by Pentek rather than ICS110B;
New suspension code (one error in this code has already
been fixed);
Pole-zero module moved from a VME board to a digital filter;
Dewhitening filter is now in use.
Thus, the gain is substantially different,
and it's not clear if all the filtering is appropriate.
Dennis is taking transfer functions and trying
to compare with ones made by Osamu before the DSC changes
(unfortunately, Osamu is in Japan).
Work in progress.
-
Mode Cleaner WFS system (Ourjoumtsev, Abbott, Eichenfield):
- Alexei and Ben have been finding and fixing problems
in the MC WFS heads (bad op amps replaced)
and MC WFS demod boards in 1Y2 (bad op amps replaced).
- Alexei is fixing small problems in the (new, digital)
WFS EPICS screens, and bringing over missing databases and
screens from the sites
so that the attenuators on the WFS heads can be switched.
He's adding the DC WFS quad signal monitoring.
- Alexei now sees good RF signals on all 2*4 channels,
as well as DC signals in EPICS.
He continues to await good MC locking.
- SURF Matt Eichenfield is learning Matlab/simulink
to model the MC WFS system properly.
-
The output to the PZT steering mirrors on the PSL table
are being debugged.
We will pursue feedback to these PZT steering mirrors
and to the MC suspended optics; so we are following the work
done by Joe Kovalik and Valery Frolov at LLO.
- Suspended optics:
- Steve & Conor balanced and re-hung the PRM.
It damps well, and is ready for installation.
- Steve & Conor, with help from Matt,
balanced and glued the SRM.
Bob is baking it, and it will be re-hung
and prepared for installation by the end of this week.
That's the last of the core optics to be prepared.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
Working well. Development work on hold.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
-
OPTICS PARTS LIST,
Orders pending:
1 q-switch E/O shutter from Fast Pulse; 1 Brewster's angle polarizer for
SPS anamorphic prism steering mirror from KLC; New mirror holders for PZT
steering mirror.
-
FARADAY ISOLATOR:
Parts are in process of cleaning and baking by Bob.
Vacuum-ready parts expected by 5/28.
-
OPTICAL LEVER ASSY:
Assembly on hold.
-
IFO STEERING MIRRORS:
The mirror holders were manufactured incorrectly and are being remade by
the vendor. New parts are expected by 5/23.
All other parts are in process of cleaning and baking by Bob.
Vacuum-ready parts expected by 5/28.
-
MODE MATCHING TELESCOPE:
Parts are in process of cleaning and baking by Bob.
Vacuum-ready parts expected by 5/28.
-
SPS BREWSTER PRISM MIRROR:
All parts, except for the Brewster prism, which is expected the week of
5/19 are in process of cleaning and baking by Bob.
Vacuum-ready parts expected by 5/28; prism to follow.
-
AUXILIARY VAC WIRING:
Completed a spread-sheet detailing the in-vacuum wiring for auxiliary
components inside the chambers: MMT focus motor, PZT steering mirrors,
motorized beam flags. Gave information to Jay H. regarding the IFO ISC
signal interface with the PZT mirror drivers.
Bob has OSEM pigtails, vacuum-ready, for the MMT focus motor
and motorized beam flags. The PZT steering mirror cables
need to be RGA scanned, and a 25-pin connector added.
- Steve proposes that we move the mechanical shutters
for MCR and SPS beamlines to the first table
that they go through after exiting the vacuum envelope (AP1)
instead of the table that they are sensed on; for safety purposes.
Mike will look at re-layout of the drawing.
- Alexei is ready to install EOS's on MCR and SPS beamlines
as soon as the 1X1 software is ready
and AC power is run to the small racks
that hold EOS electronics.
- Steve has almost all the parts that were
designed by Larry Jones for our shutter flags
(one goes in front of every test mass,
to block or attenuate the beam if desired).
Bob is vac-prepping the parts this weekend.
Steve is ordering picomotor controllers for them.
Mike will design beam dumps for them.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- We plan to install almost all the remaining
in-vac equipment for the first round of experiments,
in the next month:
PRM, SRM, ETMx, ETMy, Faraday Isolator,
MMT, PZT sterring mirrors, all other steering mirrors,
shutter flags, camera mirrors, optical viewports, etc.
Mike will develop an initial alignment procedure.
We hope to have this complete, sometime in July
(Seiji arrives July 1 to help).
- Steve has LOTS of surplus vacuum equipment
(including high-quality VAT right-angle manual valves)
available to any interested LIGOn.
Ed Chargois will ship some of it to the sites.
- Two PC's had virus warnings. They were
decontaminated by Mike Pedraza.
- Steve ordered an A/C unit for the control room
(which is starting to really warm up),
and will call in electricians to wire it up.
- AJW ordered two new PCs for the hoardes of summer visitors.
-
South Annex Bake Ovens (Taylor, Cardenas):
-
Bob is currently baking the last optic (SRM) before final hanging.
- Bob has lots of clean/bake jobs from Mike (MMT, FI, etc);
all six vacuum bake ovens, and the air bake oven, in the South Annex
will be in use, this weekend!
- Bob will be building hybrid OSEMs for Janeen next week.
May 16, 2003
- Core digital suspension controllers (DSC), MC WFS,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- All installed optics (MC1, MC2, MC3, BS, ITMX, ITMY)
are damping well with the new DSC system.
The electronics for PRM
and SRM seem to operate fine, but are having trouble damping because the
optics are not installed yet.
- From Rolf:
Code had to be fixed this week to get the all the
suspension signals into DAQ properly and the MCL signal properly sent to EPICS
from the suspension PCs.
- Rolf:
The GDS signals from the suspension PCs are late by 1/16 second. This
should be an easy fix in the DAQ router software.
- Rolf:
Added the capability of the IOO VME system to
acquire 16KHz channels to the DAQ as well as 2KHz channels. This allows the IOO
VME system to acquire all IOO/PSL DAQ channels, thereby removing the previous
long DAQ cable runs from the PSL area down to the DAQ analog data collection
unit (ADCU).
-
Ben made a list of DAQ channels for Rolf, and learned that the Generic DAQ
Interface Board needs modification to condition all of the channels
correctly with regards to gain and filtration, and to reorder one of the
channels to limit them to 16.
- Rolf: Signals to IOO M1/M2 are comming off the wrong (3rd) pentek. This is
corrected and needs a reboot to move the outputs back to the first Pentek.
- Rolf:
Work will start next week on the 40m end station controllers, which should only
take a few days (very minor mods to existing software).
- Ben is rearranging the end rack drawings to reduce the number
of needed VME crates by one per end.
- Dennis et al are preparing to re-diagonalize any optics that need it.
- The servo gains will be tweaked to optimize x_rms.
From dtt displacement spectra it looks like the ITMs will need higher gain.
- Bob continues to wire the auxiliary rack (1X1),
which holds the electro-optics shutter signals, video switch,
and other misc stuff.
He had to shift all the crates back several inches
so that the rack door would close.
Dennis will set up to boot the cpu;
He and Alexei will work on the database for EOS channels.
- Ben is updating the rack drawing for 1X1 to incorporate
recent changes.
- We need to run AC power to the small racks
that hold EOS electronics. Steve & Ben will pursue.
- We have enumerated all the places, in vacuum,
which need wiring to auxiliary components
(PZT steering mirrors and picomotors for shutters, flags, MMT).
We will prepare pigtail-like in-vac cables for these devices.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
-
The DSC system, and MCL path, now all work.
-
Dennis restored Autoburt biases to the mirror pitch & yaw,
and saw flashes on MC2 and light on the photodiodes;
so alignment hasn't changed much.
-
Dennis & Conor are re-aligning the MC mirrors,
and attempting to re-lock.
- Alexei is working on the MC WFS system:
Ben helped Alexei troubleshoot a bad WFS Demod board
and replaced the bad
chips. It now operates fine.
2 of 4 quads on the WFS2 head appear to have large offsets.
The output to the PZT steering mirrors on the PSL table
are being debugged.
Signals from dtt excitation are seen on test points.
Rolf and Alexei are checking out the path to the mirrors themselves.
IO WFS medm screens are being refined.
- Suspended optics:
- Bob cleaned and baked the new part to hold
the OSEMs on our SOSs which have the PRM and SRM,
and which have 2.5degree wedges, necessitating the changes.
Steve et al will re-hang these optics
and prepare them for installation, in the next week.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor is planning a re-layout of the PSL beam, to
(1) reduce the number of turns from the MOPA to the periscope
by two mirrors;
(2) pick off the FSS beam after the PMC, as is done at LLO,
to stabilize against PMC displacement noise.
-
Conor has measured and modeled the frequency reference cavity
pole, and is doing the same for the PMC cavity pole,
in case it needs compensation in the FSS servo.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
-
OPTICS PARTS LIST,
Orders pending:
1 q-switch E/O shutter from Fast Pulse; 1 Brewster's angle polarizer for
SPS anamorphic prism steering mirror from KLC;
-
FARADAY ISOLATOR:
Updated the parts list and released the final assembly drawing.
Parts will
be disassembled for cleaning and baking.
Prepared traveller.
-
OPTICAL LEVER ASSY:
Assembly on hold.
-
IFO STEERING MIRRORS:
Updated the parts list and released the final assembly drawing.
Parts are
on hand, awaiting assembly for fit checking.
Prepared traveller.
-
MODE MATCHING TELESCOPE:
Alternate MMT with spherical mirrors was assembled and tested with the COS
IR autocollimator. The astigmatism is so bad that with a double pass test
through the autocollimator, only the on-axis portion of the reticle pattern
could be focussed. By comparison, the off-axis parabolic mirror telescope
causes negligible distortion of the double pass reticle pattern.
Updated the parts list for the parabolic mirror version and released the
final assembly drawing. Parts will be disassembled for cleaning and baking.
Prepared traveller.
-
SPS BREWSTER PRISM MIRROR:
Updated the parts list and released the final assembly drawing.
Prepared traveller.
All parts
are on hand except for the Brewster prism, which is expected the week of 5/19.
- Alexei discovered that all the beamsplitter mirrors on the MCR beamline
downstream of where the EOS will go (to the LSCPD and WFSs)
were for S-polarization,
not P-polarization; he replaced them with the correct mirrors.
He continues to evaluate how much power the WFSs need.
- Alexei received three 6KV DEI pulsers for the EOS system.
He continues to work on getting EPICS control of the EOS systems,
and AC power to the EOS control racks,
with help from Dennis and Bob.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Steve and Bob cleaned and removed a bunch of cabinets
to make room for desks for summer students.
There's LOTS of surplus vacuum equipment
(including high-quality VAT right-angle manual valves)
available to any interested LIGOn; check it out!
- Steve is getting a portable air conditioning unit for
the control room, before the summer students (each of whom
burn hundreds of watts) arrive.
He's also getting desks and chairs.
- Larry has the shop making six picommotor-controlled
in-vac shutter flags.
Steve is working with Mike Smith on vac-compatible beam dumps.
- The east end ion pump (EEIP) has been repaired and is working fine.
- Dennis has completed the vacuum and psl sections
of the comprehensive procedures manual, and is moving on
to other sections.
-
South Annex Bake Ovens (Taylor, Cardenas):
-
Bob cleaned, baked, and scanned the re-machined OSEM bracket
for our PRM and SRM suspensions, and some vented screws and mirror mounts.
- Bob helped
Ken, Mike finish the new LIGO1 errant beam baffles and clean them,
they will go too the heat treaters today.
-
Bob is ready to clean and bake the MMT and Faraday isolator,
as soon as they're fully checked out.
- Osamu continues to work on
development of
the dual-recycling summation cavity for E2E,
while in Japan for the month.
May 9, 2003
- Suspended optics:
- Our two ETMs are ready for installation.
- Steve and Osamu attempted to balance our PRM and SRM,
but discovered that the large (2.5degree) wedge on the optic
in the SOS suspension causes the magnets to be offset
with respect to the OSEMs.
After consulting with Janeen and Helena, they decided to
remove the OSEM holding brackets,
and machine out holes to allow the OSEMS to be
shifted a bit, thus centering the magnets in them.
The machining is already done, and Bob has cleaned it and
it's in the bake oven.
Hope to have the PRM and SRM ready for installation by the end
of next week.
Janeen will submit a DCN with the changes.
Conor took some great pictures with his new 4MP digital camera.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor proposes to re-layout the PSL beam, to
(1) reduce the number of turns from the MOPA to the periscope
by two mirrors;
(2) pick off the FSS beam after the PMC, as is done at LLO,
to stabilize against PMC displacement noise.
Peter and Rich think it's a good idea.
We may have to compensate the FSS for the PMC cavity pole,
so Conor will attempt to measure it.
- Core digital suspension controllers (DSC), MC WFS,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- Ben, with help from Jay and Dennis, have at last
completed the troubleshooting and fixing of the newly configured DSC
system. All the whitening boards are now fixed.
Several software problems were fixed by Alex.
Jay and Ben fixed the Anti-Alias chassis that was giving us trouble.
- Now, all installed optics (MC1, MC2, MC3, BS, ITMX, ITMY)
are damping well!
-
Attempts to re-lock the mode cleaner are now in progress.
The MCL signal is taking a different path,
and problems are being debugged.
- Alex is continuing work on the IO WFS Linux PC code, in
particular getting the GDS test points working.
- The IO WFS VME code still needs some work; Rolf will
need to get the 16K DAQ channels working.
- Dennis and Conor will see if MC1,MC2,MC3 need re-diagonalizing.
- Bob continues to wire the auxiliary rack (1X1),
which holds the electro-optics shutter signals, video switch,
and other misc stuff. Dennis and Bob tested the video switch
manually, to be sure it works.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
-
OPTICS PARTS LIST,
Received parts:
Repair of damaged tilt platform S/N 70416 with drive amplifier from Piezo Jena.
-
Orders pending:
1 q-switch E/O shutter from Fast Pulse; 1 Brewster's angle polarizer for
SPS anamorphic prism steering mirror from KLC;
-
FARADAY ISOLATOR:
Parts will be disassembled for cleaning and baking.
-
OPTICAL LEVER ASSY:
Assembly on hold.
-
IFO STEERING MIRRORS:
Parts are on hand, awaiting assembly for fit checking
-
MODE MATCHING TELESCOPE:
MMT was assembled and tested with the COS IR autocollimator. The primary
and secondary mirror spacing was varied by means of the attached "Pico
motor"; best focus (@infinity) was determined by observing the sharpness of
the retro-reflected reticle pattern through the MMT. The best focus could
be determined within +/- 0.25 mm of the correct mirror spacing. An
approximately Gaussian 1064 laser beam was transmitted through the MMT and
the beam profile was scanned before and after the MMT. Within the
uncertainty of the slightly non-Gaussian beam profile, the MMT appears to
preserve the Gaussian profile of the beam.
Further, it focuses the beam well in both x and y,
showing no evidence of astigmatism.
- Alexei got some beam reflected off the newly damped MC1,
and thence to the MCR beamline and the newly installed
WFS's. There was too much light; the Kepco HV power supply
drew too much current. Since there is one supply for 2 WFS's,
it affected the other WFS when only one was exposed to the beam.
Alexei and Conor are evaluating how much light should be on the WFSs.
- Meanwhile, however, Alexei sees 29MHz demodulated
signals from the WFS.
- Alexei has ordered 6 kV pulsers for our electro-optic shutters,
and has returned our 3 kV ones.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The east end ion pump (EEIP) had a bad fan on the controller;
Steve fixed it.
-
South Annex Bake Ovens (Taylor, Cardenas):
-
Bob is cleaning and baking the re-machined OSEM bracket
for our PRM and SRM suspensions.
-
Bob is ready to clean and bake the MMT and Faraday isolator,
as soon as they're fully checked out.
- Osamu has confirmed his understanding of the matrix
summation approximation in
the dual-recycling summation cavity for E2E,
and is beginning to write Matlab code to simulate it.
He'll be in Japan for the next month,
and will work on this there.
He will be working with Japanese students
who will come in the summer to work with Seiji and Hiro.
May 2, 2003
- Suspended optics:
- Steve and Osamu rehung both ETMs after baking.
Two more pairs of EQ stop screws are being cleaned and baked,
and then these two suspensions will be ready for installation.
- Steve and Helena have bonded the guide rods and magnet standoffs
to our PRM and SRM, and they're ready for balancing.
- All 4 of these
remaining suspended optics should be ready for installation
by the end of next week.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor and Dennis re-aligned and mode-matched the PMC;
the transmission is around 60%.
- They have searched for power loss between the
laser output (8.9 W) and the PMC input (6.2 W).
Most (all?) of the loss is in the HWP and beam cube
used to attenuate the power. It can attenuate down to zero,
but when opened up, has poor transmission.
They will investigate aligning it better.
- Conor will attempt to measure the FRC pole
by dithering the laser current shunt.
- The mods to the FSS have reportedly caused problems
at LLO, so we are putting our plans for implementing those
mods at the 40m on hold until the dust settles.
- Now that Conor has fixed the double-passing of the
beam through the AOM, Osamu will re-measure the VCO noise.
- Ben and Flavio have assembled and functionally tested
the new ISS PD. It seems to work fine,
and Flavio has brought it to the PSL lab for further testing and
incorporation into the ISS there.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
The Digital Suspension Controllers are in the process of being rebuilt,
so there's been no work on the MC.
- Core digital suspension controllers (DSC), MC WFS,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
Ben is now in the midst of troubleshooting and fixing the
the DSC rewiring.
The AA chassis still has problems, and 3 of 8 blown whitening
boards have been fixed. Sander and Todd are on it.
Hope to have the system up and working any day now!
- Once everything is back up, it will be interesting
to see whether we need to re-diagonalize all the MC suspension controllers.
Dennis will show Conor how to do it.
- Bob has just about finished wiring the mode cleaner WFS
system (1Y2). Some issues were found with the
high voltage wiring, but it will be done today.
- Rolf and company have all the code up and running
in 1Y2, for the mode cleaner WFS ASC,
analog LSC inputs, and fast PSL and MC signals.
- Alexei continues preparation for
commissioning the MC WFS system.
We have reviewed all the new screens that
Rolf and company have put together, and
are addressing problems and issues.
- From Rolf:
Continued installation of 40m systems. All controls now installed and
under test. One problem has been that the suspension VME software
would die (or appear to) after anywhere from 5 minutes to 5 days. We
installed a bus analyzer and found that the new 2Gbit network card was
hanging up, continuously replying on the bus with Target Device Not
Ready - Retry. Unfortunately for us, this is not a bus error,
therefore the processor PCI interface chip will forever retry and not
return to the code. We found this was happening on a read cycle after
we did 16 writes to the card, but again, not always as it can run for
some time. We contacted the vendor and after sending a few bus
analyzer traces to them, they were able to recreate the problem in
their lab and are working on it. In the meantime, by changing our code
from writing to the network card to instead command the card to become
the bus master and read from the CPU memory, we are able to get around
the problem.
- The fast PSL and MC signals have been moved
from 1Y7 to 1Y2, but the latter only digitizes at 2kHz.
We are considering keeping the MCF signals in 1Y7
to keep the 16kHz sampling. Rolf is checking whether
it's possible to read in a few channels at 16kHz.
- Alexei and Bob have measured the
MC WFS RF cables; they are all the same length to 1 cm.
They fixed some problems with HV to the WFSs,
and can now see signals from the WFSs.
- Lisa continues to learn how to develop EPICS screens and software,
practicing on the 1X1 video switch.
- Ben will arrange for power to the little racks
that hold the EOS electronics.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
-
OPTICS PARTS LIST,
Orders pending:
Repair of damaged tilt platform S/N 70416 with drive amplifier from Piezo
Jena expected delivery 5/1; 1 q-switch E/O shutter from Fast Pulse; 1
Brewster's angle polarizer for SPS anamorphic prism steering mirror from KLC.
-
FARADAY ISOLATOR:
Mike and Alexei aligned the
Brewster's angle Faraday isolator and measured
>96% transmissivity (dominated by non-AR-coated internal surfaces
of the polarizing beam splitter),
and (much?) better than 4e-4 extinction ratio.
Alexei beam-scanned the input and output alignment beam
and found no evidence of beam distortion.
It is now being disassembled for cleaning and baking.
-
OPTICAL LEVER ASSY:
Assembly on hold.
-
MODE MATCHING TELESCOPE:
IR autocollimator alignment equipment is set up and working. SORL Primary
mirror was manufactured out of specification, 0.12 too short; however, a
standard 0.125 spacer washer has been purchased to adjust for the short
length. Mike is now aligning it, and it looks good.
-
PZT VAC STEERING MIRROR
Awaiting repair of damaged PZT tilt platform.
Mike will get the wiring requirements to Jay.
- Mike and Steve will look into installing a camera
and in-vac mirror to view the beam as it exits
the mode cleaner and enters the Faraday Isolator;
probably the tightest squeeze in the vacuum chambers.
- We need new pulsers to operate our
electro-optic shutters properly, so we will trade in our
3kV models for 6kV ones (more money, of course).
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Steve began pumping on the main volume
with the newly-reinstalled maglev turbopump (TP1),
and saw a burst of SO2 on the RGA.
It died away, and appears to have been a coincidence.
Bursts of SO2 have been seen before,
and they die away afer a few hours of pumping.
The maglev is working fine.
- The east end ion pump (EEIP) has a bad fan on the controller,
explaining why it was running hot. Steve will fix it.
- Still waiting for a replacement controller board for
cold cathode gauge #3 (CC3).
- Still waiting for replacement parts for the HEPA filter
fan on the PSL enclosure.
- Steve has developed Carpal Tunnel syndrome.
He brought in the "Ergo-lady", who gave him many suggestions.
She will bring in the chair-and-desk guy, who will
probably tell us that all our chairs need replacing.
- Speaking of which, Steve will look into getting new
desks and chairs for the expected
hoardes of summer students and visitors.
-
South Annex Bake Ovens (Taylor, Cardenas):
Bob is ready to clean and bake the MMT and Faraday isolator,
as soon as they're fully checked out.
- Osamu has had a significant breakthrough in understanding
the dual-recycling summation cavity for E2E,
and thinks that the remainder of the development work will be
straightforward. He says that Hiro is happy.
April 25, 2003
- Suspended optics:
- Steve and Osamu finished balancing both ETMs,
and Bob has baked them. They are ready for final suspending.
- Steve and Helena have bonded the guide rods & standoffs
on to the PRM (T = 7.7%), and are gluing the magnet standoffs
and magnets.
Helena has cleaned the SRM (SRM01) and it's ready for
bonding the guide rods & standoffs.
- All 4 remaining suspended optics should be ready for installation
by the end of next week.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor and Dennis have tuned up the FSS optical path
over the last couple of weeks, and it looks to be in good shape.
- Osamu is working on mods to the FSS board that were
implemented on the LHO PSLs.
- Conor is working on the PMC.
He has measured the beam size entering the PMC
with the BeamScan, and is adjusting the mode-matching accordingly.
He will measure and optimize the transmission, visibility,
- Ben's new stands for the ISS PD are done being fabricated, and fit the
head boards well.
- The ISS PD transimpedance heads seem to work fine, and I hope to attach
two of them and test them out with the satellite box by the end
of the week.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
The Digital Suspension Controllers are in the process of being rebuilt,
so there's been no work on the MC.
- Core digital suspension controllers (DSC), MC WFS,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
The DSC rewiring is completed, and
Ben has tested the AUX crate and the DSC FE Input crate in 1Y4 and 1Y5 after
fixing some minor problems with the wiring, they are both
functioning fine.
- Dennis and Ben are now in the midst of troubleshooting and fixing the
suspensions racks.
The DAQ interface chassis that sends the sensor signals to the ADCs
has a variety of problems, including 850 Hz LPF's
(inappropriate for 16 kHz readin), and Ben is getting it fixed.
It appears that ALL of the whitening boards have failed
in some way, and Paul Russell is diagnosing them.
ICS110B channel hopping, and VME CPU instability
is hampering progress.
They are making headway, but it will take some time.
We hope to be damping optics sometime next week.
-
Bob will finish wiring the MC WFS system (1Y2) this week,
moving the fast PSL and MC signals from 1Y7 to 1Y2.
- Getting all the code working in this system
(including the readout of the MC length signal
with a Pentek,
and the fast PSL and MC signals with an ISC110B)
probably requires Rolf, who is on vacation this week.
- The MC WFS RF cables need to be measured to make sure
they're all the same length.
- Dennis fixed a problem with the PEM EPICS crate,
so we are once again reading out the dust monitor and STACIS.
- Dennis and Lisa are developing the EPICS screens and software
for the 1X1 video switch.
- Dennis is cleaning up and reorganizing
all the EPICS code.
- Ben will arrange for power to the little racks
that hold the EOS electronics.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
-
OPTICS PARTS LIST,
Received parts:
Brewster's angle polarizer mounts for the Faraday isolator were received.
-
Orders pending:
Repair of damaged tilt platform S/N 70416 with drive amplifier from Piezo
Jena; 1 q-switch E/O shutter from Fast Pulse; 1 Brewster's angle polarizer
for SPS anamorphic prism steering mirror from KLC.
-
FARADAY ISOLATOR:
Polarizer mounts were received and are being checked before preliminary
alignment of the Brewster prism Faraday isolator. Brewster mirror parts
were received, except for the Brewster calcite prism from KLC.
The assembly will be fully checked out
by Mike and Alexei, and then passed to Bob for vacuum prep.
-
OPTICAL LEVER ASSY:
Assembly on hold.
-
MODE MATCHING TELESCOPE:
All parts are in. Mike and Alexei will align with the autocollimator,
then pass on to Bob for vacuum prep.
-
PZT VAC STEERING MIRROR:
PZT tilt platform collar was received. Awaiting repair of damaged tilt
platform.
Mike will get the wiring requirements to Jay.
- Jay is at LLO examining how they wire and control
their electro-optic shutters.
It is not clear how they can operate these
with the pulsers that they have.
Alexei is prepared to order higher voltage pulsers
to get our EOSs to operate properly,
and we are waiting on Jay.
- Alexei is preparing to commission the MC WFS system.
He is calculating the Guoy telescope lens positions
and tolerances,
and the predicted sensitivity to misalignments.
- We have a new CrystalLaser IR laser
with good beam quality, for aligning the new sensing trains.
Hope to get started on this soon.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Steve re-installed the maglev cryopump
and RGA scanned it; it looks clean.
He's been pumping on the main volume with the cryopump,
and will switch to the maglev soon.
-
South Annex Bake Ovens (Taylor, Cardenas):
Bob is baking the two ETMs in preparation for their final installation.
He is ready to clean and bake the MMT and Faraday isolator,
as soon as they're fully checked out.
- Osamu and Hiro continue to make progress in the development of a
dual-recycling summation cavity for E2E.
April 18, 2003
- Suspended optics:
- Steve and Osamu (with help from Helena and Jay)
suspended one ETM (ETM03), and balanced and damped it.
- They've glued the magnets and standoffs for the 2nd ETM
(ETM02), and are in the process of balancing and damping it
as of Thursday afternoon.
- They will move on to the two recycling mirrors
next week, while the ETMs bake.
We have three PRMs, with T = 6.5%, 7.0%, 8.0%.
We'll start with the 8% mirror
(which will give us the lowest gain, most over-coupled PRC),
and change if necessary later.
- Bob is ready to bake both ETMs next week.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor and Dennis have been studying the power fluctuations
on the light coming out of the AOM in the FSS path.
They see very odd behavior, which depends on the VCO voltage.
They will follow up, asking the experts.
- Last week, Osamu reported increased noise in the FSS loop
and strange phase behavior in the open loop tranfer function.
He has traced this to saturation due to the large
signal he was injecting to do the measurements.
He reduced the injected signal size, re-optimized the FSS gains,
and now the noise is back to where it was, exept for a large
peak at 20 kHz, which is the cross-over frequency
for the slow and fast FSS paths.
He concludes that the fast (high frequency) path needs
higher gain, to increase the UGF and phase margin.
So, it's time to implement the mods that Rick and Paul
implemented on the FSS card for the LHO PSLs.
Osamu will get started on that.
- Meanwhile, Conor will move on to optimizing the PMC performance.
- Ben's new stands for the ISS PD are fabricated and are scheduled to be
done by the end of this week.
-
The PCBs for the ISS PD transimpedance heads and the satellite
electronics have arrived.
Ben has stuffed and preliminarily tested three of
the head units, and will begin stuffing the satellite electronics PCBs
this week.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
The Digital Suspension Controllers are in the process of being rebuilt,
so there's been no work on the MC.
- Core digital suspension controllers (DSC), MC WFS,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
-
Ben and Bob finished all the rewiring (cross-connects,
front and back panel) for the DSC system (racks 1Y4 & 1Y5).
- Ben has modified the DB and
made up some new screens for the testing of the AUX crates in
these racks, and will begin this testing tomorrow.
- From Rolf:
Began installation of new systems at 40m lab:
-
Suspension and IO WFS VME crates installed and running.
-
Updated auxillary suspension controller EPICS databases and undergoing
testing.
-
Epics up and running on a Linux PC. New suspension screens added to
epigen and then generated for all suspensions.
-
One suspension controller PC installed and running; Remaining
suspension PC and ASC PC are due in today.
-
GDS router installed into the IO WFS VME unit; GDS software for
suspension PCs should be complete today or tomorrow.
-
Remaining 2Gbit network cards arrived; still waiting on network hub.
-
Having problems with the AWG CPU; Alex is working on it.
-
DAQ configuration updated to include new systems' DAQ/GDS signals.
Main DAQ screen updated to reflect new systems and status.
Also added a network layout and status screen.
- We should be ready for damping
optics sometime next week.
-
Bob will finish the last wiring for the mode cleaner WFS system (1Y2)
this week.
Alexei can begin commissioning that system, starting next week.
We need to make sure that the WFS RF cables are all
the same length, with a TDR (time delay reflectometer).
-
Bob is wiring the cross-connects on rack 1X1,
which controls the electro-optic shutters, mechanical shutters,
illuminators, video switch.
- Lisa is learning how to develop EPICS screens and software,
starting with the 1X1 video switch.
- Bob will maintain documentation
for all the rack wiring, and log books for any changes.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
-
OPTICS PARTS LIST,
Received parts:
Received repaired spare tilt platform S/N 70418.
-
Orders pending:
Repair of damaged tilt platform S/N 70416 with drive amplifier from Piezo
Jena; 1 q-switch E/O shutter from Fast Pulse; 1 Brewster's angle polarizer
for SPS anamorphic prism steering mirror from KLC; Brewster's angle
polarizer mounts for the Faraday isolator are in process; .
-
FARADAY ISOLATOR:
Awaiting the polarizer mounts.
They should arrive in the next week,
after which the assembly will be fully checked out
by Mike and Alexei, and then passed to Bob for vacuum prep.
-
OPTICAL LEVER ASSY:
Reworked parts were received and are awaiting checking and assembly.
-
IFO STEERING MIRRORS:
Awaiting one PZT tilt platform.
Mike will get wiring requirements to Jay.
-
MODE MATCHING TELESCOPE:
All parts are in. Mike and Alexei will align with the autocollimator
next week, then pass on to Bob for vacuum prep.
-
INTEGRATED LAYOUT DRAWING:
Updated the IMC_R layout with correctly positioned Guoy phase lens for the
WFSs.
- Alexei will install the MCR WFS Guoy telescopes,
verify that they are in the right place with the BeamScan,
and proceed to commission the MC ASC system.
- Alexei confirmed with Mike Zucker that indeed,
the electro-optic shutters (EOSs) operate at ~ 3.8 kV,
not the ~ 1.8 kV implied by the LaserMetrics spec sheets.
The DEI pulsers we purchased cannot operate beyond
3.5 kV, so we will return them for credit towards
(more expensive) models that operate up to 6 kV.
Jay will figure out what went wrong in ordering these HV pulsers.
- Alexei has assembled and tested two EOS assemblies,
and will begin on the 3rd as soon as the 3rd Q-switch arrives.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The east end ion pump (EEIP) has failed and can't restart.
Steve will work on it.
- One of the two HEPA filter fan motors on the top
of the PSL enclosure started to fail, vibrating madly;
the PSL FSS and PMC servos stayed in lock!
Steve has removed the motor, and it will be repaired
and re-installed by Caltech electricians.
Meanwhile, we can run with the other HEPA filter.
- The controller card for the CC3 gauge is busted,
and Steve has ordered a replacement.
- The maglev turbopump came back from the manufacturer,
and Steve is trying to find out whether they'll guarantee
it's cleanliness, before he re-installs it.
- The rain revealed a roof leak in the South Annex clean room.
- The STACIS and dust monitor systems are not being read out;
Dennis will investigate, when he returns.
-
South Annex Bake Ovens (Taylor, Cardenas):
Bob has readied all the ovens for baking
the suspended optics, and the MMT and Faraday isolator.
- Osamu is making progress in the development of a
dual-recycling summation cavity for E2E.
April 11, 2003
- Conor gave a well-received LIGO seminar on
QND and squeezed-light work at Australia National University.
- Suspended optics:
- Steve helped Helena in preparing an optic for GinGin.
- Steve and Helena are suspending one ETM this week,
and will do the 2nd ETM next week. The two recycling mirrors will follow.
All four suspensions are ready to go.
- Jay got us a new stand-alone SOS controller for this work.
- Bob is ready to bake the optics after gluing.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- Conor and Dennis made some significant changes to the
beam going into the frequency reference cavity (FRC).
Conor fixed several problems with the beam through the AOM;
he increased the RF drive to the AOM through the VCO,
aligned the beam as close as possible to the PZT side of the
AOM, and discovered that the beam
was not being double passed, so he fixed that.
The power going to the FRC was thus increased from 5 to 17 mW.
This required the power to the reflected RFPD
to be attenuated by a factor 3 to compensate.
-
He and Dennis then re-aligned the beam to the FRC,
and fiddled with the mode-matching lenses.
The visibility peaked at 50%. This is much lower than before,
but before, the reflected beam was not being focused
on to the reflected RFPD; it was only sampling the inner
TEM00 part of the reflected beam.
They will investigate whether the limited visability
is due to poor mode matching or due to HOM's coming
from the laser (which probably could use a tune-up).
This is important, because HOM's from the laser
may be the cause of the relatively poor transmission through
the PMC.
- Osamu then played with the FSS gain, and remeasured
the in-loop frequency noise. It was 3x worse than before,
with a huge peak at 30 kHz (the cross-over frequency
for the slow and fast FSS loops)
and a pi phase shift at low frequencies.
Osamu, Conor and Dennis will go over all the changes
that have been made to the FSS, and try to figure out
what has gone wrong.
- Then, they'll move on to the PMC, and,
if necessary, tune up the laser.
- Ben's new stands for the ISS PD are in the machine shop being
fabricated. They should be done early next week.
- Ben has sent in the PCB for the ISS PD transimpedance heads, and the
satellite boxes. The heads should be here by Friday, and the boxes'
PCB should be back by Tuesday. The whole thing should be ready to go
to Livingston for testing, the week of the 21st.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
The Digital Suspension Controllers are in the process of being rebuilt,
so there's been no work on the MC.
- Core digital suspension controllers (DSC), MC WFS,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
-
Ben and Bob should be finished with
rewiring the DSC system by the end of this week.
- New DSC controls, from Rolf:
-
Most of the new VMIC 2Gb/sec reflected memory boards arrived. The
PC and VME code was updated to make use of these new cards, which
involved writing some new driver code.
-
The suspension control software is complete. We will go with two
Pentium 4 PCs (each running 4 optics) and one VME crate, which does
the I/O and DAQ for 8 optics in the initial installation.
-
The IO WFS software is complete. Last task was to port the
digital signal processing part to a PC, which completed Tuesday.
-
Since we had all the parts in our development lab, we hooked all
the systems together and ran timing tests, injecting timing signals at
various points and checking them on a scope. All of the timing looks
good.
-
We are now in the process of moving the whole system into the 40m
lab. With any luck, we should up and running next week.
- Rolf and Alex Ivanov have installed
one of the 2 controls linux PCs
for the new DSC system
(a third will be needed for the ETMs),
and a VME pentium to serve EPICS channels
(this will move to a dual-CPU linux PC,
once the EPICS port to Linux is complete).
They are in process of commissioning the software.
The fiber runs are temporary (while we wait for longer ones),
and a few 2Gbit reflective memory boards are still on order
and expected any day now.
- Mode cleaner (IO) ASC and LSC:
Jay reports that
rack wiring and installation is 90% complete.
Remaining VME components (3 penteks)
will be installed by the end of this week.
The controls linux PC should be in, soon.
Current holdup is lack of long fibers
to connect the reflective memory loops to the DSC, DAQs,
and controls PCs.
- Main IFO ASC and LSC:
Jay reports that the rack and wiring diagrams are 90% complete.
All that needs to be added are any QPDs used for beam centering.
- Jay, Ben and Bob have met and agreed to
running and labelling cables they way it is done at the sites.
A log book will be maintained for any changes to cabling,
and any cables that are not plugged in correctly will be
summarily removed.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
-
OPTICS PARTS LIST,
Received parts:
Input mode-matching telescope off-axis parabolic mirrors were received from
SORL, Guoy phase lenses for IMCR were received from CVI, replacement power
connector for the 4 W 940 nm laser was received from Applied Optics.
-
Orders pending:
Repair of two damaged tilt platforms expected 4/15 from Piezo Jena; 1
q-switch E/O shutter from Fast Pulse; 1 Brewster's angle polarizer for SPS
anamorphic prism steering mirror from KLC; Brewster's angle polarizer
mounts for the Faraday isolator are in process; alternative spherical
mirrors for MMT are expected from CVI in a few weeks.
-
FARADAY ISOLATOR:
Awaiting the polarizer mounts.
Should get them next week.
Then, final checkout of the system, extinction ratio, etc.
Then, on to Bob for cleaning and baking, and installation.
-
OPTICAL LEVER ASSY:
Reworked parts were received and are awaiting checking and assembly.
-
IFO STEERING MIRRORS:
Awaiting one PZT tilt platform.
Should arrive next week.
-
MODE MATCHING TELESCOPE
Replacement power connector for the missing power cable for the 4 W 940nm
alignment autocollimator laser was received, and a power cable was made by
Paul R. Received parabolic telescope mirrors, will do alignment week of 4/14.
Then, on to Bob for cleaning and baking, and installation.
- Alexei has made more measurement of the properties
of our first electro-optic shutter (EOS),
but managed to burn out the HV pulser in the process
(at a lower HV than it was supposed to be rated for).
We have 2 more, and the broken one will be sent back
for repair.
- The EOS transmitted power follows the predicted cosine curve,
but peak transmission occurs at
50% more HV than expected.
This may be due to the way Alexei has wired up the q-switch,
and he is trying to get the attention of folks
at the site who've done this before.
- Meanwhile, Alexei is preparing a 2nd EOS assembly.
A third awaits a back-ordered Q-switch.
And, two more EOS controllers are in progress at Wilson House.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Dennis is getting ethernet cables and hubs into the
remaining racks that need it, including our
auxiliary rack 1X1. He noticed that 1X1 will
have to be rebuilt, because the rails are in the wrong place,
so that the door won't close.
- Dennis has set up the screens for the video switch
in our auxiliary rack, and is setting up the
EPICS cpu in that rack to control it (and the EOSs,
mechanical shutters, illuminators, etc).
- Steve is installing the remaining camera mounts and viewports.
- The maglev turbopump came back from the manufacturer,
who couldn't reproduce its failure.
Steve will put it back in when he gets a chance.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob has finished some OSEMs for Hanford,
and shipped them out.
- Bob is doing some airbaking of aluminum pieces
for Ken Mailand, to try to darken them
for use as baffles.
- Bob has readied all the ovens for baking
the suspended optics, and the MMT and Faraday isolator.
April 4, 2003
- Dennis and Osamu are both on shift at LHO all this week.
- Suspended optics:
We are preparing to suspend our two ETMs in the next couple of weeks,
and shortly thereafter, our two recycling mirrors,
completing the suspended optics for the 40m.
- Helena cleaned the two ETMs.
They are ETM02 and 03.
Their radius of curvature are very close, 59.92m and 59.75m respectively.
The magnet/dumbell standoffs are also assembled.
She went over the bonding procedure with Steve.
- Bob is cleaning and baking the last earthquake stop
screws that are needed for the MOS suspensions
- Bob has fully assembled the two MOS and two SOS suspensions.
Janeen reviewed the suspensions and they look ready
to go but for these screws.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott,
F. Nocera, D. Ugolini, S. Vass, C. Mow-Lowry):
- The beam on the FSS RFPD is jittering,
causing the signal to fluctuate.
Conor has been investigating.
Conor made several changes
to the PSL table around and downstream
of the AOM. There were two major concerns:
(1) The beam jitter of the double passed AOM beam and
(2) Fluctuating power levels.
Conor increased
the RF drive to the AOM through the VCO from 3.50
Volts to 5.00 V,
realigned the AOM,
and aligned the beam as close as possible to the PZT side of the
AOM crystal.
These three actions resulted in an increase in single pass efficiency
through the AOM from 40% to 75%.
After realignment and iterative
adjustment to the retro-reflector angle and the AOM angle, a maximum
double pass power of 19.3 mW was obtained, form a 31.5 mW incident
beam.
This is a double pass efficiency of around 60%. The beam jitter
appears to be gone, but this requires further investigation.
The single- and double-pass power fluctuations are still present, but
appear to be significantly reduced.
It may be necessary to translate the AOM along the
propagation axis to ensure it is at the beam waist.
After all these changes,
the FSS will have to be re-optimized.
- Ben is
working on a final design, layout, and packaging for the ISS DC PD.
He hopes to have it to the board house by Friday.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
The Digital Suspension Controllers are being rebuilt this week,
and Osamu and Dennis are at LHO,
so there's been no work on the MC.
- Core digital suspension controllers (DSC), MC WFS,
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
-
Ben and Bob are rewiring the DSC system.
They have finished the crate and module rearrangement,
and the cross connect re-wiring, on 1Y4 and 1Y5, and will go
on to the back panel and front panel wiring starting today.
- Jay has modified the system drawings for the IO WFS rack
to combine two VME half-crates into one split-backplane crate.
This crate collects signals from the IO WFSs through Pentek ADCs
and thence to a linux box via RM for ASC filtering,
sends signals to the IO PZT steering mirrors through a Pentek DAC,
collects fast signals from the PSL through an ISC110B
and thence to DAQS via RM,
collects the MC length control signal from the MC servo
through Pentek ADC and thence to the DSC system via RM.
The other half of the crate is an EPICS IOC
for signals from the PSL and MC.
- From Rolf:
LSC code updated to include addition photodiode correction filter banks and
outputs; undergoing testing with 40m system.
- From Rolf:
New digital suspension software for 40m lab should be ready in the next few
days. Still to do:
- Waiting new high speed reflective memory boards. Call last Thursday
said they were shipping, but just received call today that they have not shipped
yet. They will ship today.
- Waiting rack mount 3.0 GHz P4 processor (should arrive today).
- Finishing cleanup work on timing diagnostics and data acquisition/GDS.
- From Rolf:
Started testing digital IO WFS system.
This should be ready to install at 40m lab early next week.
- Jay reports that the system drawings for our LSC / ASC system
are around 90% complete.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
- OPTICS PARTS LIST, Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are expected first
week in April from SORL; repair of two damaged tilt platforms expected
first week in April from Piezo Jena; 1 q-switch E/O shutter from Fast
Pulse; 1 Brewster's angle polarizer for SPS anamorphic prism steering
mirror from KLC; Brewster's angle polarizer mounts for the Faraday isolator
are in process; spherical mirrors for MMT are expected from CVI in a few
weeks; Guoy phase lenses for IMCR are expected from CVI in by 4/7;
replacement power connector for the 4 W 940n from Applied Optics is
expected by 4/7.
-
FARADAY ISOLATOR:
Working drawings for the Brewster's angle polarizer mounts for the Faraday
isolator were completed, and parts are being manufactured.
-
OPTICAL LEVER ASSY:
Reworked parts were received and are awaiting checking and assembly.
-
IFO STEERING MIRRORS:
Parts are awaiting checking.
-
MODE MATCHING TELESCOPE:
Replacement power connector for the missing power cable for the 4 W 940nm
alignment autocollimator laser was ordered. Awaiting telescope mirrors.
-
INTEGRATED LAYOUT DRAWING:
The ILD was revised to incorporate the new Brewster's angle Faraday
isolator, the SOS anamorphis prism mirror, and the revised SPS beam path.
- Mike has ordered some replacement Guoy telescope lenses
for the IO WFS, that are still missing.
- Alexei has made one electro-optic shutter (EOS) work.
He resolved some questions about how to wire up the
Q-switch, and where to ground it.
The EPICS controls are not yet ready, so he's patching around that
with an old 24-volt power supply and a function generator.
He tested the EOS controller box, and works ok for a while;
after about 10 minutes, it no longer send the correct gate
signal to the pulser.
But until then, he can adjust the HV and observes the output
power to vary from near-zero to near-max. He is optimizing
the HV and alignment.
After resolving all the remaining problems, he will
install the shutter in the MCR beamline,
then turn to the EOS's needed for the SP and AP beamlines.
A 2nd Q-switch is in hand, a third on back-order.
Two more controllers are in the shop.
-
Ben ordered some SHV connectors to connect the HV to the Q-switches;
they should arrive by the end of the week.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The maglev TP1 was at the manufacturer for repairs, but they
found no problem. They've shipped it back,
we should get it by the end of the week.
- Steve has set up the camera to view ITMy,
in addition to cameras already in place for MC1, MC2, MC3, ITMx, and BS.
- The CC gauge near TP3 is not working; the controller
has a bad board. It's been sent out for repair.
- Steve completed the laser inventory forms
required by the safety officers.
- Our second new dry scroll pump is making
squeeking noises, just as the first one did before it failed.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob is baking the remaining EQ stop screws for our suspensions.
- Bob finished a bake job for Lee.
- Bob has finished cleaning and baking a new set of
cleanroom tools for use in the South Annex.
March 28, 2003
-
40m Laboratory Upgrade Progress Report to the
Technical Advisory Committee,
March 19, 2003, LIGO-G030033-00-R, O. Miyakawa; and
response of the TAC (K. Strain, M. Zucker).
- Also at the LSC meeting, Dennis Ugolini's application
for Trinity University to join the LSC we approved.
- Dennis and Osamu are both on shift at LHO all next week.
- Conor Mow-Lowry from ANU is joining the 40m team
for a 5-month visit. Make him welcome!
- Suspended optics:
- Oplev QPDs for the 3 installed core optics
(BS, ITMx, ITMy) are in place and see signals,
through to the interface boards.
Four more Oplev QPDs are ready for installation.
The interface boards are part of the DSC system,
which is being completely re-wired this week.
- Steve and Helena have glued magnets onto dumbbells
for the two ETMs, in preparation for suspending them
in the next week or 2.
- Bob has completely assembled the two MOS's
for the ETMs, and the two SOS's for the PRM and SRM.
A few more vented EQ stop screws are still in the shop.
Janeen will carefully inspect the suspensions, soon.
- Mark Barton is testing the silver-tipped EQ stops
being developed by Steve.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
- Osamu turned up the laser power to maximum, about 7 watts,
into the PMC. Only ~ 3 W was transmitted through the PMC.
Osamu and Conor will work on improving the transmissivity.
- Osamu tried tuning the PMC servo notch filter,
changing it from 35 kHz to 31.5 kHz,
to resuce the frequency noise applied on the beam
by the PMC (and measured by the MC). It didn't help.
The PMC is being excited by acoustic noise; Osamu suspects
the vacuum pumps.
- The beam on the FSS RFPD is jittering,
causing the signal to fluctuate.
Osamu, Alexei and Conor will investigate.
- We are also planning on implementing mods to the FSS
that are recommended by Rick Savage,
and mods to the MCS recommended by Daniel Sigg.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu measured the cross-over frequency between the
MCL and MCF servo paths, with the new (Pentek) path for the
MCL signal. It's still at 26 Hz, but the phase margin has increased
from 10degrees to 95degrees.
The new noise curve no longer has a peak at 26Hz.
- Osamu installed software compensating filters for the
filtering in the Pentek Interface board,
and measured the transfer function to verify
that they were doing the right thing.
- Osamu turned up the PSL power to maximum (~ 3 W out of the PMC).
After attenuating the sensor beams into the photodiodes and cameras,
he re-measured the frequency noise, and found it to be unchanged
with respect to low-power (~ 300 mW).
- Osamu studied the MC2 suspension sensing noise,
and the damping Q, for various
settings of the position (and P,Y) gain G.
He measured Q ~ 4/G.
He finds that sensor noise sets in for gain > 0.3,
or Q ~ 12. Jay seemed to recall that the sites operate
with Q in that range, as well.
- Osamu then measured the PSL frequency noise
for different damping gains, and finds a strong
contribution to the overall noise, in the ~100-200 Hz region,
for gains > 0.3. He finds G = 0.1 to be optimal.
However, the MC won't lock robustly with such low gain.
We can imagine acquiring lock with higher gain,
then reducing it for low-noise detection operation.
- Osamu also noticed a dramatic drop in the 60-Hz-harmonics
noise when the damping gain was turned down.
- Osamu turned on the hardware dewhitening,
and the sensor noise went down. But, the univ-dewhite
board introduces an offset, so lock is not stable.
Jay says something is wrong, and he and Ben
will look into it (after the DSC re-wire).
- Alexei made some beautiful measurements of
the MC finesse. He actuated on the laser current shunt,
and observed the effect on the light intensity
before, and after, the MC. Both magnitude and phase of the
resulting transfer function are consistent with
a finesse between 1400 and 1460 (design is 1550).
- We have found our missing WFS's,
and Alexei installed them in the MCR beamline.
A couple of Guoy phase telescope lenses are still missing,
Alexei and Mike will hunt.
Ben and Bob are almost done with the cabling for the
the WFS ASC for the MC.
- Core digital suspension controllers (DSC),
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
-
Ben has finished the wiring diagrams, system drawings,
and cross connect list for the DSC re-layout.
Ben and Bob are now in the process of ripping apart our
DSC system, and rebuilding and re-wiring it.
- From Rolf: -- VME/PC digital suspensions (DSC):
We ran into a problem with the dual Xeon processor PC. Something comes
in every 64 seconds and causes a 200usec delay in our code. This is
not seen when our code runs on a Pentium 4 unit. After several days of
searching for the problem, we opted to finish the software and run on
Pentium 4 boxes for now. We'll come back to the Xeon problem as time
permits. At some point, we also want to investigate why our code runs
slower on the 2.8GHz Xeon than on the 2.6GHz P4.
Otherwise, on the PC side, the code is complete and undergoing further
testing. On the VME side, the DAQ for sensors/coils was added and
tested. So, by early next week, we should be ready to move the system
into place at the 40m lab.
- From Rolf: -- Digital IO WFS:
The VME side is up and running. In the 40m lab version, this VME unit
will also do the DAQ for PSL channels and any other DAQ channel
connections in the IO area. Work on that part of the software is in
progress.
The PC side is nearing the point of initial testing. This unit may
show up at the 40m lab later than next week, but is not required for
initial DSC operations (required MCL signal is already present from IO
WFS VME).
- From Jay: --- 40 Meter ASC/LSC:
System drawings have been started and should be complete by 4/4/03.
- Our SR785, which arrived broken,
has been repaired by the manufacturer, and returned.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
- OPTICS PARTS LIST, Received parts:
5 CX-ST50 CCD cameras from Aegis for the ISC tables; insulating bushing
from Accurate Screw Machine for the LSC photodiode assy; 1 q-switch E/O
shutter from Fast Pulse; 3 Brewster's angle polarizers for input Faraday
isolator and SPS anamorphic prism steering mirror; QPD riser mounts and
insulator from ASCO.
- Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are expected
first week in April from SORL; repair of two damaged tilt platforms
expected first week in April from Piezo Jena; 1 q-switch E/O shutter from
Fast Pulse.
-
FARADAY ISOLATOR:
In process of detailing the redesigned polarizer mounts for the Faraday
isolator with Brewster's angle polarizers.
-
OPTICAL LEVER ASSY:
Reworked parts were received and are awaiting checking and assembly.
-
IFO STEERING MIRRORS:
Parts are awaiting checking.
-
MODE MATCHING TELESCOPE:
The wrong curvature spherical mirrors were received for the interim MMT;
they were sent back, and replacement mirrors are expected in a few weeks.
The COS autocollimator alignment equipment, which will be used for aligning
the MMT, was presumed missing in action, but the shipping container from
LLO was finally discovered in the 40 m lab masquerading as a scope stand.
All the COS alignment equipment is accounted for except for a power cable
and a 10V, 2A power supply to run the 4 W 940nm alignment autocollimator laser.
- Alexei has installed the EOS optics on the MCR and SP beamlines.
He also installed CCD cameras on all the beamlines,
and Bob is running video cables from them
to the video switch in rack 1X1,
and from the switch to the control room.
Dennis will get the video switch state code and EPICS screens
from the sites, and install them.
- Steve ordered a 100 mw YAG laser from CrystalLaser for optical sensing
beam alignment.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The maglev TP1, which failed during last month's pumpdown,
refuses to fail at the manufacturer. They are sending it back.
- Our second new dry scroll pump is making
squeeking noises, just as the first one did before it failed.
- Steve regenerated the cryopump, and calibrated the new RGA filament.
- Steve and Bob installed several camera mounts
and cameras that view the suspended optics,
and new viewport covers and illuminators.
We now have very nice views of the MC1, MC3, BS, and ITMx optics.
The remaining cameras and illuminators will go in soon.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob is baking a chamber for Lee.
- Bob has a new set of clean tools for use in the South Annex cleanroom.
March 14, 2003
- The 40 Meter Technical Advisory Committee will meet
at 3:15 CST, Wednesday 3/19/03, at the LSC meeting at LLO.
Osamu will present our status report.
- Also at the LSC meeting, Dennis will present his
application for Trinity University to join the LSC.
- Suspended optics:
- Ben has designed a rigid and insulated
table mount for the oplev QPDs; 7 of them are being
manufactured now, and will be done by nend of this week.
- Bob is completing the MOS suspensions,
including the newest rev mods.
EQ stop screws are still in the shop.
Should be ready next week.
We plan to suspending ETMx and ETMy in the near future.
- Steve continues to pursue EQ stop tip R&D,
in coordination with Janeen and Mark Barton.
He has switched from indium wire (too soft)
to silver.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
- Dennis and Osamu measured the phase noise
of our VCO, in situ. They had to rig up a simple servo to stabilize
the Marconi oscillator to the VCO at low frequencies,
so that they could measure the VCO phase noise at high frequencies.
Thanks to Rich Abbott for the servo design!
The noise, expressed as frequency noise,
is roughly flat at 5e-3 Hz/rtHz from 100 Hz to 10kHz,
above which, the Marconi is insufficiently stable.
This noise is roughly a factor 2 better than
what is reported at the sites (~ 1e-2 Hz/rtHz),
and is completely consistent with the mode cleaner noise curve
in that frequency range.
Dennis and Osamu will now calibrate the VCO response
in Hz/volt.
- Osamu plans to reduce the low-f gain of the VCO,
thus increasing the dynamic range and eliminating saturation,
to compensate for
the increased seismic noise at the 40m relative to the sites.
- Osamu and Alexei improved the FRC alignment,
and found and fixed a place where the reflected beam
was clipping a mirror mount.
Now, the excess noise noticed in the MC error signal last week is gone.
- Osamu retuned the beam alignment on the PSL table,
so the initial pointing into the MC has changed.
- We are also planning on implementing mods to the FSS
that are recommended by Rick Savage,
and mods to the MCS recommended by Daniel Sigg.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
After the work described above, Osamu and Alexei recovered
robust locking of trhe MC, and re-measured the frequency noise.
It is now the same as it was before last week's pump-down.
- There's still excess noise from 100-300 Hz
at the new cross-over frequency between MCL and MCF.
This should go away when additional filtering is added to MCL.
Osamu is working on that, now.
- Osamu and Alexei set up the OSA at MC transmitted
and observed the transmitted 33 MHz sidebands
(and no reflected 29 MHz sidebands).
They optimized the tranmission by tuning the Marconi frequency;
maximum was at 33.194709 MHz, corresponding to a MC half-length
of 13.547 m. Just right.
They are trying to understand, and increase,
the sideband modulation depth.
They will work on quantifying the sideband transmission,
but it looks consistent with the total transmission (~ 95%).
- They measure a MC visibility of 1 - 0.052
(ie, a trasnmission of ~ 95%),
which is as good as we've seen before, and close to specs.
- Ben and Bob continue working on the cabling for the
the WFS ASC for the MC. They're almost done,
but are awaiting more RG405 cable.
- Our MC WFS's are missing...! We're looking for them.
- Lori is still working on the MC WFS ASC software
(at Wilson House).
- Core digital suspension controllers (DSC),
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
-
Ben is ~25% through the drawings for the re-wiring of the
DSC system (newly designed by Rolf to be
PC-based, with significantly less VME-based processing).
He hopes to be finished by next week,
and then he and Bob can start the re-wiring.
- Jay continues to work on the drawings for
a LIGO-I-like LSC system
for the 40m dual-recycled IFO,
including 8 I/Q demod boards from LSC PD's.
- Ben has made arrangements for Bob to
return the SR785 analyzer that isn't working.
Bob shipped it out yesterday.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
- OPTICS PARTS LIST, Received parts:
drive electronics to drive the x and y axes of the 2nd PZT vacuum IFO
steering mirror were received; re-worked IFO MMT parts and light-weight PZT
steering mirror holder received.
-
Orders pending:
Order was placed with KLC for Brewster's angle polarizers for input Faraday
isolator. Input mode-matching telescope off-axis parabolic mirrors are
expected first week in April from SORL; repair of two damaged tilt
platforms expected first week in April from Piezo Jena; 5 CX-ST50 CCD
cameras from Aegis for the ISC tables; 3, 33% 45S polarization beam
splitters from CVI for the ISC tables; insulating bushing from Accurate
Screw Machine for the LSC photodiode assy; 2 q-switch E/O shutters from
Fast Pulse for the ISC tables; QPD riser mounts and insulator from ASCO.
-
FARADAY ISOLATOR:
In process of detailing the redesigned polarizer mounts for the Faraday
isolator with Brewster's angle polarizers.
-
OPTICAL LEVER ASSY:
Reworked parts were received and are awaiting checking and assembly.
-
IFO STEERING MIRRORS:
All the parts were received and will be checked before cleaning, baking and
assembly. Lee will assemble the DLC mounts.
-
MODE MATCHING TELESCOPE:
All the parts are in hand for the interim, spherical mirror version of the
MMT. The telescope will be assembled and aligned for testing next week,
before being taken apart again for cleaning, baking, and final assembly.
The silvered parabolic mirrors should be available by early April.
-
ERRANT BEAM BAFFLES:
Mike is working on a new baffle design using coated aluminum,
which will be used for the 40m.
- Steve will order some 100 mw YAG lasers for optical sensing
beam alignment.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The maglev TP1 failed during last week's pumpdown.
Steve was able to reset it, but it failed again
a short while later.
He has removed it and is crating it up to be sent back
to the manufacturer for repair.
- We are now running with all 4 ion pumps.
- Steve is preparing to install all the camera mounts
and cameras that view the suspended optics,
as well as the new viewport covers and illuminators.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob ordered cleanroom supplies and tools for the south annex lab.
- Bob continues to work on OSEMs for GinGin.
- Bob is ready to bake out a chamber for Lee, as soon as it arrives.
March 7, 2003
- Overall status and near-term plans:
- We pumped back down last Friday.
There were a variety of problems (see below), but none too serious.
- All 6 suspended optics (MC1, MC2, MC3, BS, ITMx, ITMy)
are installed in their chambers, and are being damped by the DSC system.
- The PSL and mode cleaner are performing reasonably well;
details below.
- We are preparing to completely rebuild our DSC system
as discussed below. Hope to complete this within one month.
- We are preparing to suspend our remaining optics:
ETMx, ETMy, PRM, SRM. Hope to complete this within one month.
- IFO sensing optical trains are all installed; details below.
- Suspended optics:
- Dennis, Bob, and Ben are setting up oplev QPDs and cables
to readout the
optical levers on all the core optics.
- Ben has designed a rigid and insulated
table mount for the oplev QPDs; 7 of them are being
manufactured now, and will be done by next week.
- Bob is acquiring, and cleaning and baking,
the remaining missing parts
to complete the remaining suspensions
(for ETMx and ETMy, and PRM and SRM)
and two MOS's (for ETMx and ETMy).
- OSEMs for these suspensions have long been ready,
but Bob discovered that the screw holes in the back
were 180degrees away from their correct positions.
This is not a problem; the OSEMs themselves can be rotated
to compensate.
- Steve has acquired some indium wire,
and will investigate its use
to replace the viton and springs in the suspension
earthquake stops.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- After pumpdown, Osamu and Dennis re-established MC lock.
The MC2 length control (MCL) is going through a Pentek now, instead of
an ISC110B. There was a sign flip due to this change,
which was compensated for with a jumper on the MCS board.
- The Pentek Interface Board introduced some new filtering,
which reduces the phase difference between the MCL and MCF loops.
Osamu measured the new OLTF and time delay, and
is modeling and understanding the differences.
The phase improvement helps lock acquisition and
the stability of lock.
- However, the changes necessitate the addition of
(software) filtering in the MCL loop to keep its
high gain at low frequencies, while giving more
authority to MCF (and thus the frequency stabilization)
at higher frequencies. Osamu will attempt to implement
the same filtering that is now done at the sites.
- Osamu sees a different noise spectrum with these changes:
(a) above 400 Hz, the noise spectrum is the same as before;
(b) the peak due to the 180degree phase difference
between MCL and MCF at the cross-over frequency of 30 Hz is gone;
(c) instead, there is a new large peak at the new
cross-over frequency of 100 Hz. This should go away when
additional filtering is added to MCL;
(d) Line harmonics at 120 and 180 Hz are now much larger;
not understood why.
- However, we will soon be completely rebuilding the DSC
system, which should improve the 60-Hz-harmonics pickup
greatly.
- Ben and Jay
fixed problems with the switching of the
universal dewhitening boards,
and they now no longer introduce excess noise
in the 40-60 Hz region.
- Ben and Bob are working on the cabling for the
the WFS ASC for the MC. They're almost done.
Some needed connectors were ordered and should be in sometime soon.
- Lori is still working on the MC WFS ASC software
(at Wilson House).
The sites want this system as well (right after S2).
Jay and Rolf await specifications for this system for the sites,
which will require a review.
- Core digital suspension controllers (DSC),
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- From Rolf:
Continued work on using a PC in conjunction with a VME crate to run the
suspensions on the 40m. We pretty much have a full system running now and have
done some initial testing. It looks like on the VME side, we can do all the I/O
plus data acquisition for 8 optics with one VME crate. There is no longer a
distinction on the VME side of large or small optics, so we can run all 40m lab
vertex optics with this one crate. The fact that the VME crate also does handles
all the DAQ channels (sensor/coil readouts) eliminates the need for a separate
DAQ VME crate.
-
On the PC side, it look like one 2.5GHz P4 box can run all the control
algorithms for 5 optics and still get its output to the VME unit in time. We ran
it is high as 6 optics, but I/O timing with the VME unit became border line. Ben has
ordered a dual 2.8GHz Xeon processor unit, which should be in late next
week. We hope to be able to run all the 40m lab optics (10) with this one box.
-
In the course of the next week or two, we need to do some finishing and clean up
work on the software. This includes getting all the white/dewhite and
run/acquire switching in. We also want to use this system to test if we can
trap ICS110B ADC channel hopping (by forcing it to jump). If we can trap it in
some fashion, then this trap code would be also applied to DAQ and watchdog
timer software.
- Jay and Ben are working on drawing up all the rewiring necessary
to implement this new DSC design. No new hardware is required;
in fact, the new design makes efficient use of the existing hardware,
freeing up quite a few modules... which we need for the LSC system!
- Jay is drawing up a LIGO-I-like LSC system
for the 40m dual-recycled IFO,
including 8 I/Q demod boards from LSC PD's.
-
Rolf is developing a number of ways to improve I/O in the LSC system,
offloading the work to the VME IO bridge chip,
freeing up the CPU for LSC filtering alone.
He will test this scheme at the 40m in a couple of weeks.
- Jay and Rolf borrowed a Pentek from our DSC system
to run some tests; as a result, we had to move
the BS to the SRM DSC, temporarily.
- Ben sent back the blown RAID array disk to IBM.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
- Dennis and Osamu are attempting to measure the phase noise
of our VCO, in situ. They are struggling with some apparent instability...
- Osamu is developing plans to modify the gain
and dynamic range of our VCO, to compensate for
the increased seismic noise at the 40m relative to the sites.
- Osamu and Alexei are improving the FRC alignment.
- Rich moved the ISS hardware from the 40 to
Peter King's lab for further development.
Our PSL table was shaking too much!
- We are also planning on implementing mods to the FSS
that are recommended by Rick Savage,
and mods to the MCS recommended by Daniel Sigg.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
- Alexei and Lisa completed the installation of the optics for the POB,
POX, TRX, and TRY sensing beamlines.
Now, all sensing beamlines needed for the first phase
of the 40m experiment are in place.
A long list of missing parts
(LSC PDs, WFSs, monitoring QPDs, EOSs, MM lenses, OSAs, cameras)
has been compiled and will be chased down by Mike Smith and Ben Abbott.
- Alexei will soon begin the assembly and commissioning of
electro-optic shutters (EOSs) for the MCR, AP and SP beams.
-
OPTICS PARTS LIST,
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are expected
3/10/03 from SORL; drive electronics to drive the x and y axes of the 2nd
PZT vacuum IFO steering mirror are expected 3/3/03 from Piezo-Jena; repair
of two damaged tilt platforms expected week of 4/7. Re-worked IFO MMT parts
and light-weight PZT steering mirror holder are pending.
-
FARADAY ISOLATOR:
A discussion with Karl Lambrecht revealed that glan laser polarizing prisms
have uncoated air-gap surfaces not at Brewster's angle, and therefore a
reflection loss of a few percent for each of the four air gap surfaces is
to be expected, which will result in a transmissivity of around 90-94 %. In
addition, since the polarizing prisms are designed for broadband usage, in
order to meet the total internal reflection angles at near IR wavelengths
the prism entrance angle must be tilted in the horizontal plane. These
facts explain the behavior of our tested Faraday isolator, which required
that we tilt the polarizer horizontally in order to achieve a decent
extinction ratio. Osamu also pointed out that the beam from the NPRO laser
that we used to measure the extinction ratio was fairly divergent, and
seemed to have a halo of scattered light around the main beam, which would
degrade the measured extinction ratio.
I have redesigned the Faraday isolator to incorporate Brewster's angle
polarizers, which we know from the measured LIGO COS output Faraday
isolator performance, that will have a much higher throughput and
extinction ratio than the normal glan laser polarizer. The astigmatism of
the reflected output beam from the Brewster's angle polarizer will be
compensated by using a Brewster's angle prism steering mirror, which
exactly undoes the horizontal magnification of the output beam profile
caused by the Brewster's angle polarizer.
Hope to complete the redesign in a week,
and have the device rebuilt and ready for installation in a month.
-
OPTICAL LEVER ASSY:
Reworked parts were received and are awaiting checking and assembly.
-
IFO STEERING MIRRORS:
The IFO beam displacement PZT steering mirror was moved from the MMT2
mirror to a separate mirror holder placed on the table next to the
mode-matching telescope (MMT). This required two additional folding mirrors
to jog the output beam from the MMT to the re-located PZT steering mirror
and back to the original beam path, adding an additional optical path
length from the MMT to the IFO beam waist. Greater than 99.9% mode-matching
of the MMT output beam into the IFO beam waist can still be obtained with
the increased path length by a slight change in the defocus of the MMT.
This was checked, independently, by Alexei.
- Mike is working on a new design for baffles, using AR-coated aluminum
rather than black glass.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The 40m was pumped back down on Friday.
- The maglev TP1 failed, and appears to be dead.
It is 10 years old; one of the very few devices
remaining from the old vacuum system.
Steve is talking with the manufacturer to see if
a quick fix is available. Else, a repair, if possible,
will be at least $4K. A new replacement is $16K.
- Without TP1, Dennis and Steve pumped from 500 to 25 mtorr
using TP2 and TP3 (through TP1).
That took a couple of days!
- Then, the cryopump
CP1 took over and has brought us down to 1.8e-6 torr
and falling.
- In the process of doing this unusual procedure,
a software interlock was tripped off an an unanticipated way,
shutting VC1 (the valve in front of CP1).
It didn't cause any problems.
Nonetheless, Dennis has rewritten the software interlock code
to make it much simpler and better behaved,
and will install it at the next convenient opportunity.
- CC1 has been observed to fluctuate a lot.
Steve had installed a new CC1, and switch to using it; it fluctuates much less.
- Steve switched on the ion pumps, but the SE IP belched
nastily. This had been observed before.
Steve is arranging to run 3 of the 4 ion pumps, leaving out the SE.
- Steve replaced the filament on the RGA and on CC4;
both are behaving reasonably now.
- Our new in-vacuum cables,
which have a non-insulated copper braiding,
are lying on the optical tables and the floor of the chamber.
They exit through pin 25 of the feedthrough.
That will be left dangling (not grounded), so as to avoid
ground loops.
-
South Annex Bake Ovens (Taylor, Cardenas):
-
Bob sent baked HAM spacers to Ken at MIT.
- Bob continues to work on OSEMs for GinGin.
- Bob has placed the new RGA in service, and compared it
with the old RGA. All looks good, and this will eliminate
the major source of downtime in the lab.
- Bob is baking out a chamber for Lee.
February 28, 2003
- Suspended optics:
- The 40m has been vented since Thursday to install
suspended optics.
- The BS, ITMx, and ITMy were installed in their
respective chambers by Steve, Dennis, and Osamu.
- They were all hooked up to their digital suspension controllers,
and they all are damping fine.
- Steve, Dennis, Osamu, and Alexei installed
optical levers on all 3 optics,
using small red lasers and in-vacuum mirrors.
Getting 5-7% of the light back; not bad.
Detectors not yet installed.
- Bob has assembled two SOS's (for PRM and SRM)
and two MOS's (for ETMx and ETMy),
in preparation for suspending the optics.
A few missing parts (screws, top assembly) are missing,
and have been ordered. The OSEMs are ready.
Janeen will do some mechanical tests
on the MOS.
- Steve is investigating the use of indium,
to replace the viton and springs in the suspension
earthquake stops. He's been discussing this with Mark Barton.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu measured the seismic noise
on top of the MC2 stack (up to 100 Hz, but with little
coherence with the floor above 50 Hz; from 50-100 Hz, it's probably
dominated by acoustic noise).
Including the pendulum TF, the curve explains the
MC noise spectrum well, below 50 Hz,
except for:
(a) f < 1 Hz, which is very time-variable;
(b) bounce mode peak at 16 Hz;
(c) peak at 30 Hz, right near the cross-over frequency
between the MCL and MCF servo paths;
the servos are 180degrees out of phase there,
and that needs to be fixed.
- After all the installation,
Dennis and Osamu re-established alignment of the MC optics,
and observed fringes while in air.
The light power was very low, so the MC servo signal
was very small; too small to lock robustly.
-
Still, it looks like the modified MCL path
(through a Pentek ADC instead of an ICS110B) works.
- Ben's re-wiring for the universal dewhitening board
was completed and checked out.
Many problems with the board were discovered and fixed.
However, the software is not controlling the
hardware universal dewhitening properly;
Ben and Alex Ivanov are working together to fix it.
- All the electronics required to complete
the WFS ASC for the MC have been passed on to Lori,
to complete the ASC software.
- Core digital suspension controllers (DSC),
and other Electronics (B. Abbott, Heefner, Bork, Taylor):
- Rolf and Jay are developing a
complete re-layout of our DSC system,
using a commodity PC rather than a VME Pentium to do the filtering,
leaving the VME Pentium to do IO only.
Instead of 4 VME crates to run 8 DSC's,
(limited by the filtering in the VME Pentium),
only ONE would be needed
(freeing up modules for completion of our
endstation DSCs and LSC system).
Tests at Wilson House are ongoing; should know whether the
new scheme will work in the next week.
Jay and Ben will rework the rack wiring (1Y4 and 1Y5).
We hope to meke the mods by the end of March.
- Ben and Jay will review the necessary mods
to get gps timing signals to the end racks.
- Jay is drawing up a LIGO-I-like LSC system
for the 40m dual-recycled IFO,
including 8 I/Q demod boards from LSC PD's.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
- We are planning on making phase noise measurements
to our VCO, and potentially also increasing its dynamic range
(to compensate for the higher seismic noise at the 40m lab).
- We are also reviewing the mods to the FSS
that are recommended by Rick Savage.
- Work on ISS has been slow this week;
Flavio is sick and Rich is on vacation.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
- Alex and Lisa completed the installation of the optics for the SP
beamline. Alexei gave a list of missing parts to Mike, who is
updating the parts list.
- Alex has completed his code and a nice GUI for calculating
the beam size and Guoy phase for all beamlines in the main IFO.
As a first exercise, he'll study the effect of moving the
PZT steering mirror from the MMT to the next table (which Mike found
was necessary for mechanical reasons).
- Alex will soon begin the assembly and commissioning of an
electro-optic shutter for the MCR, AP and SP beams.
-
OPTICS PARTS LIST,
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are expected
3/10/03 from SORL; drive electronics to drive the x and y axes of the
2nd PZT vacuum IFO steering mirror are expected 3/3/03 from
Piezo-Jena; repair of two damaged tilt platforms expected week of
4/7. Re-worked IFO MMT parts and light-weight PZT steering mirror
holder are pending. 1.5 in mirrors for the light-weight PZT steering
mirrors are pending from CVI.
-
FARADAY ISOLATOR:
The Faraday isolator was assembled and aligned by Mike and Alex.
The transmissivity was
0.97 and the extinction ratio was an appalling 0.11. Subsequently, the
horizontal input and output polarizers were rotated by approximately 3
deg in the horizontal plane and the extinction ratio improved to
2.5E-3, with the transmissivity dropping to 0.91. Coincidentally, the
3 deg rotation brought the front face of each polarizer normal to the
beam; however, the polarizers were designed with a 3 deg wedge on the
entrance face, so that the beam would not enter normal to the face to
avoid glint reflections. Clearly something is wrong, and further
testing and discussions with Karl Lambrecht and EOT will be necessary
before we can resolve the problem.
-
OPTICAL LEVER ASSY:
Reworked parts were received and are awaiting checking and assembly.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The 40m has been vented since Thursday,
for optics installation.
We'll pump back down on Friday.
- Steve noted that our new in-vacuum cables,
which have a non-insulated copper braiding,
are lying on the optical tables and the floor of the chamber,
and Jay said that this was not good.
Steve and Osamu will look for evidence of ground loops
with this situation.
- Steve replaced the failed TP3 dry scroll forepump
with a spare. He's not sure why the pump failed.
- Steve and Bob are adding a new large
dry scroll forepump behind TP2.
-
South Annex Bake Ovens (Taylor, Cardenas):
-
Bob completed bake jobs for Janeen, Mike Smith,
Ken Mason, and Larry Jones.
- Bob is assembling the in-vacuum camera mirror parts for the 40m.
A missing screw has been ordered.
- Bob is making 5 more OSEMs for Janeen / Glasgow.
February 21, 2003
- Suspended optics:
- The 40m has been vented since Thursday to install
suspended optics.
-
Steve, Dennis, and Osamu installed
ITMx in its chamber
on Friday, and cabled up the the DSC.
Several problems with the DSC cables were discovered
(flipping of connectors), which blew out the whitening board.
The cables and board were promptly fixed,
with help from Rich and Ben,
and DSC damping was established. The table was levelled
and all OSEMs read in the middle of their range.
- BS was installed, DSC damping established,
and table levelled for OSEM centering, on Tuesday.
- ITMy was installed, DSC damping established,
and table levelled for OSEM centering, on Thursday.
- Dennis used DI N2 to blow dust off of the mirrors before installation.
- Steve checked that the suspension wire was in the correct place,
after installation.
- Steve will try to set up in-vac mirrors for oplevs
on these 3 newly installed optics, before pump-down.
- Steve will also see if he can install
in-vac mirrors for camera views of the optics, before pump-down.
- Bob has assembling one of 2 SOS's (for PRM and SRM)
and one of 2 MOS's (for ETMx and ETMy),
in preparation for suspending the optics.
The OSEMs are ready. Janeen will do some mechanical tests
on the MOS.
- The old (green light) BS, in its SOS suspension,
was removed from the chamber. It is available to whoever might need it.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu measured the MC noise one last time before venting.
It was ~ 5-10 dB worse than usual, above 1kHz. Not sure why.
- Osamu, Dennis, and Ben are reviewing the modifications that
Daniel Sigg suggested to our MC servo board,
to increase our UGF from 67 kHz to ~ 100 kHz,
and are preparing to implement them.
- Ben has moved
the MC length control to MC2
from an ICS110B to a Pentek ADC.
He and Bob are now working on rewiring
to use a universal dewhitener instead of the current
SOS dewhitener for the MC2 output to the coil driver.
- Ben has obtained all the electronics required to complete
the WFS ASC for the MC. He will work with Bob on all the cabling.
Jay says that Lori is almost ready with the ASC software.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
- We are planning on making the mods to our FSS
that are recommended by Rick Savage,
to our FSS board and RF summing box,
to increase our UGF from 300 kHz to 600 kHz.
- The ISS PD is now downstream of the PMC.
It continues to work well, but an out-of-loop PD
reads more noise, and extreme sensitivity to acoustic
and mechanical vibrations on the PSL table.
- Using a QPD, Rich has established that the apparent
intensity noise is strongly correlated with beam jitter
on the sensing PD.
- Rich continues the struggle to obtain -160 dB,
with help from Dennis and Ben (Flavio is on vacation).
- Core digital suspension controllers (DSC),
and other Electronics (B. Abbott, Heefner, Taylor):
- Rolf proposes a complete re-layout of our DSC system,
using a commodity PC rather than a VME Pentium to do the filtering,
leaving the VME Pentium to do IO only.
A fiber link shuffles data between the 2 computers.
Instead of 4 VME crates to run 8 DSC's,
(limited by the filtering in the VME Pentium),
only 2 would be needed.
And, there'd be cpu cycles to spare (unlike the present situation).
This has already been tested at Wilson House.
This will require significant re-wiring.
Jay will take the opportunity to split analog and digital
between the two racks (1Y4 and 1Y5).
- Ben and Jay will review the necessary mods
to get gps timing signals to the MC ASC system,
the end racks, and the future LSC system.
- Jay is drawing up a LIGO-I-like LSC system
for the 40m dual-recycled IFO,
including 8 I/Q demod boards from LSC PD's.
He is considering incorporating a redesign of the
LSC whitening filter boards.
He's also thinking about a redesign of the
IQ demod boards, to fix known problems
and to easily incorporate double demodulation.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
- Alex and Lisa completed the installation of the optics for the AP1
beamline, and are nearing completion for the SP beamline.
Alexei gave a list of missing parts to Mike, who is
updating the parts list.
- Alex is nearing completion of his code and a nice GUI for calculating
the beam size and Guoy phase for all beamlines in the main IFO.
- Alex will soon begin the assembly and commissioning of an
electro-optic shutter for the MCR beam
(they are also needed for the AP and SP beams).
-
OPTICS PARTS LIST,
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are expected
3/10/03 from SORL; drive electronics to drive the x and y axes of the 2nd
PZT vacuum IFO steering mirror are expected 3/3/03 from Piezo-Jena; repair
of two damaged tilt platforms expected week of 4/7.
-
IFO MODE-MATCHING TELESCOPE:
All the telescope parts were assembled okay. However, the PZT tilt platform
was damaged during assembly into the MMT. I have decided to remove the tilt
mirror from the MMT assembly, because the assembly is risky and the
parabolic mirror presents too large a cantilevered load on the PZT
mechanism. An adapter that attaches the mirror holder directly to the
secondary mirror mount was designed. The PZT tilt mirror will be mounted
separately.
-
FARADAY ISOLATOR:
The reworked Faraday isolator is awaiting assembly and alignment. An
alignment procedure is being written.
-
OPTICAL LEVER ASSY:
Reworked parts were received and are awaiting checking and assembly.
-
VAC STEERING MIRROR:
A light-weight mirror holder for a 1.5 in dia x 0.25 in thick steering
mirror, instead of the original 2 in mirror, was designed to be used for
the IFO steering mirrors that are mounted on the PZT tilt platforms in
separate DLC mirror mounts. The first steering mirror, SM1, will be located
next to the MMT and an additional turning mirror willbe used to return the
output beam from the MMT back to SM1. The second steering mirror, SM2 will
be located near the PRM as before, but will utilize a smaller 1.5 in
light-weight mirror holder on the PZT tilt platform.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The 40m has been vented since Thursday,
for optics installation.
We'll pump back down sometime in the next week.
- The TP3 dry scroll forepump failed on Sunday night,
causing the pressure to rise in the RGA and annulus regions.
CC4 did not switch off, as it should.
Steve is investigating the cause for both these failures.
- Steve realized that the counterweights
used to balance the optical tables in the chambers
are not vented; so they trap air in the table holes.
He is now placing the counterweights on washers to prevent this.
- Osamu plans to measure the horizontal transfer function
of the small MC2 stack, before we pump down.
-
South Annex Bake Ovens (Taylor, Cardenas):
-
Bob completed bake jobs on Janeen's OSEMs for GINGIN
and Ken's HAM spacers.
- Bob baked in-vacuum camera mirror parts for the 40m.
February 14, 2003
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu estimated the contribution of the measured
frequency noise to the main IFO GW sensitivity
(assuming a CMRR of 1/100),
and compared it with our design sensitivity.
It barely meets the specs, whereas a factor 10
safety margin is desired.
Improvements to the servos (described below)
will help a lot, and a common mode servo will
help a lot. So we should be in good shape with frequency noise
when we commission the main IFO.
- Osamu presented his studies of PSL / MC frequency noise
(transparencies)
at last Monday's commissioning telecon.
There were lots of good ideas and suggestions.
- In particular, Rick Savage suggested that we modify
our FSS board and RF summing box,
to increase our UGF from 300 kHz to 600 kHz.
Osamu, Dennis, and Ben are reviewing the modifications
and preparing to implement them.
- Daniel Sigg suggested modifications to our MC servo board
to increase our UGF from 67 kHz to ~ 100 kHz.
Osamu, Dennis, and Ben are reviewing the modifications
and preparing to implement them.
- Ben is working on the mods
to the MC length control to MC2:
using a Pentek ADC instead of the ICS110B,
and using a universal dewhitener instead of the current
SOS dewhitener.
Ben developed a test procedure for the Pentek Generic Interface Board
Driver, and tested and installed it at the 40m.
He has altered the MC2 Universal Dewhite boards to fit the component
values given to him by Rana, and brought them to the 40m Lab.
All the boards are in place, but
the changes require some rewiring,
and Ben is modifying the protel drawing before the
wiring mods are made.
- Ben has obtained all the electronics required to complete
the WFS ASC for the MC. He will work with Bob on all the cabling.
Jay says that Lori is almost ready with the ASC software.
- We vented today (Thursday) to install suspended optics.
Plan is to pump back down on Wednesday morning,
re-establish the MC noise behavior,
and begin to implement the mods to the FSS
and MC servos, one step at a time.
- Core digital suspension controllers (DSC),
and other Electronics (B. Abbott, Heefner, Taylor):
- Ben and Jay will begin purchasing the
additional electronics needed to complete the end racks
(Pentiums, Penteks, ISC110B's, and custom modules; for
ETMx and ETMy DSC, and transmitted port sensing).
- Ben and Jay will review the necessary mods
to get gps timing signals to the MC ASC system,
the end racks, and the future LSC system.
- Jay is drawing up a LIGO-I-like LSC system
for the 40m dual-recycled IFO,
including 8 I/Q demod boards from LSC PD's.
Mike Smith estimates ~ 20 mW of laser power
on the asymmetric port LSCPD's,
so it should not be necessary to have more than one LSCPD
for each degree of freedom to be sensed.
(Of course, this means that our shot noise limit
will be larger than we thought, but for the 40m,
this may be a good thing!).
- Jay and Ben will start thinking about
the design of a "double-demod" board for
sensing signals at (33 x 166) MHz.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
-
Ben has made a new mount for the ISS DC photodiode.
It is a very sturdy
monolithic aluminum block the holds only the photodiode.
From there, it is connected to the
PD circuitry by a short shielded cable. This was done in an attempt
to minimize acoustic sensitivity of the PD enclosure.
The ISS is no longer sensitive to vibrations of this component,
but the bottom line noise in the ISS is unchanged.
- Next step is to move the ISS PD from its current position
upstream of the PMC to downstream, to take advantage of the
increased stability of the PMC-filtered beam.
An additional ISS PD would look at the MC-transmitted light,
and the servo would blend these two signals together.
- Rich Abbott improved the current shunt actuator,
replacing several components, including an amplifier that was
limiting the slew rate.
Results of the test with the new shunt are not yet in.
- Meanwhile, Steve took the opportunity to clean and vacuum
out the Lightwave laser box, while it was open to replace
the current shunt. It still had some detritus
from a small water leak many months ago.
- Dennis has completed the PSL part of the
"Comprehensive 40m Procedures Manual", and posted it
near the PSL.
- Optical sensing (Smith, Ourjoumtsev, Goggin, Miyakawa):
- Alex is completing the installation of the optics for the AP1
beamline, including some lenses that just arrived yesterday.
He and Lisa Goggin will proceed with the SP optical sensing train,
then on to POB, POY, TRx, and TRy beams.
- Alex is continuing to develop his code and a nice GUI for calculating
the beam size and Guoy phase for all beamlines in the main IFO.
- Steve ordered four 1mW 670nm Coherent diodes
with power supplies and mounts, for oplevs.
He measured the reflectivity of the BS and ITM at an incident
angle ~35 degrees. From front surface, reflected ~5%
and the back surface ~15%.
-
IFO MODE-MATCHING TELESCOPE:
All the MMT parts for the alternate (spherical mirrors) telescope are in
house and are in process of being checked and assembled before cleaning and
baking (next week).
Input mode-matching telescope off-axis parabolic mirrors are expected
3/10/03 from SORL.
Drive electronics to drive the x and y axes of the 2nd
PZT vacuum IFO steering mirror (mounted on the MMT)
are expected 3/3/03 from Piezo-Jena.
The MMT also contains a pico-motor for focusing;
in-vacuum cables for this device need to be designed
and made with proper shielding.
-
FARADAY ISOLATOR:
The reworked Faraday isolator assembly has been cleaned and baked and is
awaiting assembly and alignment.
-
OPTICAL LEVER ASSY:
Several parts of the optical lever focus lens assembly are being reworked
to enable electrical isolation of the QPD from the table mounting base. The
lenses were assembled into the lens tube.
-
OPTICAL SENSING:
The beam size matching lenses for the AP1 optical train were designed, were
ordered, and were received. The layout drawing of the AP1 optical table was
updated with the revised component locations. An assembly drawing for the
IMCR, SPS, and AP1 sensing beam's E-O shutters was made for clarification
of assembly, because each beam uses different size polarizing beam
splitters that require different spacer mounts. A new spacer was designed
for the IMCR E-O assy. The parts list is being updated.
- Optics (Billingsley, Armandula), suspensions (Romie), OSEMs (Bob):
- Dennis and Steve vented the 40m today (Thursday) to install
the 3 suspended optics (BS, ITMx, ITMy) on Friday and Monday,
cable them up, coarse align and damp with the DSC system.
-
Janeen originally ordered 7 SOS suspensions for the 40m,
with the assumptions that one was a spare.
That spare is the one Mark is using for his earthquake stop testing.
Bob and Janeen have verified that the "6th" SOS suspension
is indeed in the 40m lab, and is in fact
already cleaned and baked and ready for assembly.
Today, Janeen ordered mechanical parts for a new spare for the 40m,
as Mark assumes testing will be ongoing for a while.
- Bob is assembling the 2 SOS's (for PRM and SRM)
and 2 MOS's (for ETMx and ETMy), in preparation for suspending the optics.
- Bob has finished baking, cleaning, and scanning the 24 OSEMs
needed to complete the 40m suspended optics, and they are ready
for installation.
- Bob and Steve checked the DI water in the 40m South Annex;
it is 2 MOhm. Helena says that we need 18 MOhm DI water for
cleaning the remaining optcs before suspending them.
Helena will thus prepare the PRM, SRM, ETMx and ETMy
optics in the Bridge optics lab
before bringing them over to the 40m,
as she did with the already-suspended MC1, MC2, MC3, BS, ITMx, ITMy.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Alex Ourjoumtsev is now fully trained in laser safety.
- We vented today (Thursday).
Plan is to pump back down on Wednesday morning.
- Dennis continues to work on a procedures manual
for all 40m systems and components.
- Two large storage containers (one for the 40m and one for CDS)
were installed in the storage area south of the South Annex
on Monday, with help from Bob.
They're already filling up!
- A UPS was installed in the vacuum controls rack,
and Steve is running all the pumps to test its ability
to hold the power.
- The CC1 gauge controller has been reporting fluctuating
pressure readings, and Steve reports that this is
as expected, in our current pressure range.
- Steve and Larry Jones made a filter for the N2 jet,
to provide the cleanest jet for blast-cleaning the optics surfaces.
- Camera mounts and illuminators for viewports,
designed by Larry and fabricated at CES,
are now in hand.
An in-vacuum mirror for viewing the optics with the cameras
is being cleaned by Helena.
-
South Annex Bake Ovens (Taylor, Cardenas):
-
Bob cleaned and has started the bake job on Janeen and Ken's HAM spacers.
They will be ready on Wed. of next week.
- Bob cleaned and assembled four Hybrid OSEMs for Janeen.
- Bob cleaned and baked the Faraday Isolator parts for Mike. They are ready.
- Bob cleaned and baked the camera mirror parts for Larry & Steve.
- Bob has received the new RGA and will test it next week.
February 7, 2003
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu has prepared a set of
transparencies
summarizing his studies of PSL / MC frequency noise,
which he will present at next Monday's commissioning telecon.
- Osamu has compared his OLTF measurment of the MCL and MCF loops
with the detailed model by Rana. He finds beautiful agreement
iff an additional 4.5 msec phase delay is present in the MCL path.
This is presumably due to the ADC (currently an ISC110B) and
SOS dewhitener; at the sites, they use a
Pentek and universal dewhitener.
- Ben is arranging to replace
the ISC110B and SOS dewhitener
with a Pentek and universal dewhitener.
Ben is testing a required Pentek Generic Input Module.
This will go into the DSC rack to make use of the unused
Pentek ADC channels there.
When we have a MC ASC crate (with penteks, Pentium,
and reflective memory), we'll move the MCL
Generic Input Module to the MC rack.
-
Ben has calculated the required filtering on
the MC2 universal dewhite boards,
but will instead wait for
Jay to hear from Russ or Rana to tell us
the exact component values
that they used instead of just the transfer function,
so that the 40m boards are site compatible.
(We will use rev B5 for the core optics,
but Jay thinks there's a "rev B3+" for MC2).
- Osamu measured the contribution to the frequency noise
due to the coil drivers. This is negligible compared
to frequency noise,
but will become important for the main IFO
asymmetric port noise (assuming frequency noise is rejected
to 1% at the asymmetric port).
- Core digital suspension controllers (DSC), and other Electronics (B. Abbott, Taylor):
- All of the DSC's for the BS, PRM, SRM, ITMx and ITMy
are complete and fully tested.
- Ben has identified some ~ $90K in additional electronics
purchases need to complete the end racks
(Pentiums, Penteks, ISC110B's, and custom modules; for
ETMx and ETMy DSC, and transmitted port sensing).
He and Jay will begin purchasing this equipment.
- Jay is drawing up a LIGO-I-like LSC system
for the 40m dual-recycled IFO, and estimates
that it will require ~ $100K in additional electronics.
- We will hold off on the design of the WFS-based ASC system,
for two reasons: it will be expensive and not essential
at the beginning (we can use the oplevs, as at the sites), and
new techniques for WFS at 200 MHz must be developed.
However, Jay will leave room in the racks for an ASC system!
- Ben has acquired a PZT driver and ordered a Kepco 100v PS
to complete the MC alignment control system
sensing and actuation system.
Ben wrote a test procedure for the PZT driver,
and has tested and installed it at the 40m.
We also need the VME system and
software, and Jay reports that Lori is
nearly ready with it.
- Our new and much-needed SR785 signal analyzer
is not working correctly, and we are communicating with
the manufacturer on how to fix it.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
-
Flavio has demonstrated better than -140 dB relative intensity noise
between 80-2000 Hz (see
plot)
but there clearly are large contributions from acoustic noise
on the PSL table, especially the HEPA filters.
(Osamu sees the same thing).
The target is -160 dB.
- Ben is working on a repackaging of the ISS PD
to mount it on a rigid block, making it less sensitive
to acoustic noise.
- After discussions with Stan, Rich believes that the
excess noise is due to slew-rate limitation at high frequency
(a time delay)
causing a saturation at low frequency.
One remedy being explored is to replace the amplifier in the laser
current shunt (the actuator) with a faster one.
- We have observed poor transmission through the PSL PMC,
but Dennis suspects its due to mode-hopping of the laser.
He observes large changes in laser power
when the PSL FSS lock is re-acquired without first zeroing
the slow loop slider.
If lock is lost and re-acquired with a large slow loop
slider value, the NPRO mode-hops.
Everyone promised to follow the standard procedure
of zeroing the slow loop slider before beginning to re-acquire lock.
Meanwhile, Osamu and Alex Ourjoumtsev will re-measure the PMC
transmission.
- Alex Ourjoumtsev re-aligned the FSS reference cavity (FRC),
and also the cameras and photodiodes looking at both
the reflected and transmitted beams.
He found that the FRC transmitted beam was almost completely
off the monitoring PD, and fixed it.
- Optical sensing (Smith):
- Osamu and Alex Ourjoumtsev have begun to assemble the
main IFO sensing optics. They laid down most of the optics for the AP1
beamline, and made a list of missing parts.
They will continue, with help from Lisa Goggin,
with the SP, POB, POY, TRx, and TRy beams.
- Alex is writing code and a nice GUI for calculating
the beam size and Guoy phase for all beamlines in the main IFO.
-
OPTICS PARTS LIST,
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are expected end
of Feb. from SORL; drive electronics to drive the x and y axes of the 2nd
PZT vacuum IFO steering mirror are pending from Piezo-Jena.
-
IFO MODE-MATCHING TELESCOPE:
All the MMT parts for the alternate (spherical mirrors) telescope are in
house and are in process of being checked and assembled before cleaning and
baking.
-
FARADAY ISOLATOR:
The reworked Faraday isolator parts are being cleaned and baked.
-
OPTICAL LEVER ASSY
Several parts of the optical lever focus lens assembly are being reworked
to enable electrical isolation of the QPD from the table mounting base. The
lenses were assembled into the lens tube.
- Optics (Billingsley, Armandula), suspensions (Romie), OSEMs (Bob):
- Our BS, ITMx, and ITMy, are suspended and sitting on the
South Annex clean room flow bench. They have clean OSEMs,
are balanced and have been damped successfully,
and are ready for installation as soon as we are.
-
Bob has the ETM suspension parts (MOS),
and one of the two RM suspension parts (SOS),
cleaned and baked.
The other is still being used by Janeen.
Bob is meeting with Janeen to go over all the parts,
and begin assembly in preparation for suspending the
remaining core optics.
- Bob has 24 OSEMs for the remaining core optics suspensions
assembled, tested, cleaned and baking;
they get RGA scanned on Monday.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Dennis continues to work on a procedures manual
for all 40m systems and components.
- The fence enclosing the storage area south of the South Annex
has been torn down to allow for the installation
of two large storage containers on Monday
(one for the 40m and one for CDS).
- Dennis noticed an anomalous loss of N2
(used for vacuum valve pneumatics)
during a switchover from one bottle to another, for unknown reasons.
He has searched for, but found, no leak.
He's seen no further evidence of anomalous loss.
- A UPS was installed in the vacuum controls rack.
Ever since then, the CC1 gauge controller
has been acting funny, showing a much larger, and fluctuating,
total pressure.
Steve is back from vacation next week and will investigate.
- Camera mounts and illuminators for viewports
are still being worked at CES; expect them in 1-2 weeks.
-
South Annex Bake Ovens (Taylor, Cardenas):
Bob is cleaning and baking in-vacuum mirrors
for camera views.
January 31, 2003
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu discovered a misalignment (of unknown but recent origin)
in the input beam to the MC.
He has re-aligned, and measured a MC visibility of 95%
(was 96.5%).
The frequency noise is back to where it was.
- Osamu continues to investigate the origin of
various noise sources in the PSL frequency noise
as measured by the MC.
He's developing methods to measure the contribution
of various electronics noise (especially the VCO)
to the frequency noise.
- The large 7 Hz oscillation is associated
with actuating with MC1 or MC3, and goes away
when actuating with MC2. This has been traced to a phase delay
in the SOS dewhiteners.
MC2 also has an SOS dewhitener, but it was turned off.
We will replace the MC2 SOS dewhitener
with a universal dewhitener and AI board.
Ben reports that these are now in fabrication.
- The MC length control OLG shows a large delay,
amounting to a loss of 50degrees of phase margin at 30 Hz.
This has been traced to the fact that the length control signal
is being digitized by an ISC 110B.
At the sites, a Pentek ADC is being used.
We will switch to a Pentek.
For this we need a Pentek interface board and cable.
Ben reports that the interface board is now being fabricated.
- Core digital suspension controllers (DSC), and other Electronics (B. Abbott, Taylor):
- Ben and Dennis have finished testing all of the hardware and software
for all 6 DSC's in rack 1Y4 (ETMx/ETMy, PRM/BS, and SRM/MC2),
including all the satellite amplifiers,
and they are now all working well.
-
Alex Ivanov fixed some remaining problems with the SRM DSC software.
- Ben has inventoried all the electronics we need
to complete the end racks (with DSC's for the ETMs)
and the mode cleaner WFS system.
He continues to work with the CDS group to obtain all the hardware.
- To complete the MC alignment control system,
We need a PZT driver and 100 V power supply;
Ben will acquire these.
We also need software, and Jay reports that Lori is
nearly ready with it.
- Jay is starting to look at the design of the
main interferometer length control electronics,
which will look like the Initial LIGO design.
An Advanced-LIGO-like design is in the future.
- Ben ordered and received a much-needed SR785 signal analyzer.
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
- Ben continues to work with Fred Mann on a better design
for the DC PD box, to
allow for changes in height while staying as rigid as possible.
- Osamu, Steve, and Alex Ourjoumtsev are preparing to
work on the mode matching
into the PMC to increase the transmitted power.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Received parts:
Re-worked half-wave plates were received from KLC, for the Faraday isolator.
-
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are expected end
of Feb. from SORL; drive electronics to drive the x and y axes of the 2nd
PZT vacuum IFO steering mirror are pending from Piezo-Jena. MMT telescope
parts are being reworked. Alternative mirror holders for holding spherical
mirrors are being fabricated.
-
IFO MODE-MATCHING TELESCOPE:
A correct drawing was received from Piezp-Jena for the hole pattern in the
PZT mirror. Modifications to the MMT drawings were made and parts were sent
out for rework.
-
FARADAY ISOLATOR:
The Faraday rotator was received from EOT, and the actual part dimensions
are different than the data sheet dimensions. Therefore, several fabricated
parts of the Faraday isolator assembly will have to be reworked to
accomodate the actual dimensions of the Faraday rotator.
Hopefully done in 1-2 weeks.
-
OPTICAL LEVER:
Some of the mechanical parts for magnified focus lens are still in process
of being fabricated.
- Alex Ourjoumtsev is beginning to inventory all the components
of the sensing beamlines.
- Alex is also calculating the beam size and Guoy phase
at all points in the sensing beamlines.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Dennis continues to work on a procedures manual
for all 40m systems and components.
- Steve did a vacuum test of an optical viewport
that was accidentally chipped at CES,
and it looked fine to him.
- Rather than mount an in-vac mirror for camera viewing
directly onto one of our viewports,
Steve will have CES mount it onto a zero-length reducer flange,
so that accidents like this won't happen again.
- Camera mounts and illuminators for viewports
are still being worked at CES; expect them in 2-3 weeks.
- Steve ordered two large storage containers,
one for the 40m and one for CDS.
They'll sit outside in the cage to the south of the 40m.
-
South Annex Bake Ovens (Taylor, Cardenas):
- All bake ovens are in good repair and available.
- Bob is on vacation.
January 24, 2003
- Plans for 40m:
In the next few months, we expect to install
most/all of the remaining instrumentation
(suspended optics, DSCs, optical sensing trains, etc)
to begin our interferometer experiment,
*except* for the length and alignment
control systems (LSC and ASC).
These are complex and expensive systems.
Without them, we can only control one or 2 degrees of freedom
at a time.
However, Jay points out that
it is clearly too early to design a real
Advanced LIGO control scheme, and thoughts on how to
"do it right" are only beginning to take shape.
One doesn't want to start too early, because
computers and ADC/DAC modules keep getting better.
Also, the 40m doesn't have multiple suspensions,
and this will be a central issue in the design of
the Advanced LIGO LSC and ASC systems.
So, we should not rush into our "Advanced LIGO controls"
experiment. However, we are eager to proceed with our
"Advanced LIGO interferometry experiment".
It should be possible to do so, with an Initial LIGO
controls architecture, which might then have to be
replaced with a better-thought-out Advanced LIGO controls
architecture later on. We have to decide how to proceed
in the near term!
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu continues to investigate the origin of
various noise sources in the PSL frequency noise
as measured by the MC.
- He has traced the 60 Hz harmonics peaks to the
MC2 DSC. If he length actuates instead with MC1 or MC3,
the 60 Hz harmonics peaks go away. Under investigation.
- The large 7 Hz oscillation, by contrast, is associated
with actuating with MC1 or MC3, and goes away
when actuating with MC2!
Recall that MC1 and MC3 DSC's are in rack 1Y5, and operate
at 2048 Hz;
MC2's DSC is in rack 1Y4 and operates at 16384 Hz.
- A big peak at ~16.5 Hz is believed to be the suspension
bounce mode.
Dennis has tried several notch filters designed with PHOTON,
but they don't have much effect. Under investigation.
- Loose screws in the PSL and AP1 tables were tied down
by Steve and Larry.It made a small (~ 3 dB) improvement
in the broad-band frequency noise.
- The cluster of peaks from 500-700 Hz are likely due
to vibrating mirror mounts on the PSL table.
Osamu moved one mount from the periscope
to the table and eliminated one peak at ~ 600 Hz.
Osamu is pretty sure it's due to beam jitter
(due to vibrating mounts) downstream of the PMC.
We are considering stiffening the periscope.
- Broadband frequency noise above 2 kHz is due to PMC and FSS noise.
The frequency stability servo (FSS)
has not been tuned up since we started actuating
on the VCO with the MC error signal.
The UGF is worse than before (it's ~ 250 kHz, should be > 1 MHz!).
Osamu will continue to look at this.
- Still, the frequency noise is now bettere than spec
over most of the spectrum!
- Core digital suspension controllers (DSC), and other Electronics (B. Abbott, Taylor):
- Dennis and Ben found numerous problems with the
DSC software, and then Alex Ivanov came in and fixed almost all of them!
Now the DSC software loads correctly for all 6 DSC's
in rack 1Y4 (ETMx/ETMy, PRM/BS, and SRM/MC2).
There were lots of problems with the databases, and Dennis
has fixed most or all of them.
The rack power supplies were current limiting, so the
current limits were set higher, but still safe.
Numerous cabling problems were found and fixed.
- Dennis and Ben have now checked out all of the
new 6 DSC's, and they all damp MC2 well.
All 8 satellite amplifiers (including ones for the ETMs)
have been checked out. They have some problems
(wrong gain resistors) which will be fixed, next.
- Alex fixed it so that if the frame builder is rebooted,
or if for any reason the DAQS crashes, it will automatically restart.
- Still some problems: most but not all excitation test points work.
Alex is still looking at it.
- Also, the new Pentiums forget where they are supposed to go
to find their startup.cmd; we don't know why.
So, if/when they get rebooted, a laborious procedure
must be followed to get the DSC code running again.
- We still need to implement appropriate filtering for our
5" ("MOS") test mass suspensions;
Jay says that, to lowest order, only the gain needs to be adjusted.
- Ben has inventoried all the electronics we need
to complete the end racks (with DSC's for the ETMs)
and the mode cleaner WFS system.
He's working with the CDS group to obtain all the hardware,
and he just ordered 2 new VME crates that are required.
Alex says that he will be ready to install the ETMx/y DSC software
as soon as the hardware is in place.
- We will push for completion of the MC alignment control.
We need a PZT driver from CDS.
Ben reports that Laurie will be available to implement
the digital control software for the system
during the "E9 lull in CDS workload" ;)
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini, S. Vass):
- The laser power fluctuations observed by Osamu and Steve
appear to be correlated with chiller temperature variations,
and we suspect that the latter variations may be due to the ISS system;
this is under investigation.
- Flavio continues to make good progress on the ISS at the 40m PSL.
- Ben is working with Fred Mann on a better design for the DC PD box, to
allow for changes in height while staying as rigid as possible.
- Osamu and Steve plan on improving the mode matching
into the PMC to increase the transmitted power.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Received parts:
Most of the mechanical parts for the mode matching telescope were received.
Mounting collar for mounting the PZT tilt platform onto the DLC vacuum
mirror mount and the mirror holder were received from CA Machine; but
because of wrong hole pattern information, the mounting holes of the
secondary mirror holder don't match with the PZT tilt platform and the
mirror holder will have to be reworked..
-
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are expected end
of Feb. from SORL; re-worked half-wave plates are expected this week from
KLC, for the Faraday isolator; drive electronics to drive the x and y axes
of the 2nd PZT vacuum IFO steering mirror are pending from Piezo-Jena.
-
IFO MODE-MATCHING TELESCOPE:
Because of wrong hole pattern information, the mounting holes of the
secondary mirror holder don't match with the PZT tilt platform and the
mirror holder will have to be reworked. Alternative mirror holders for
holding spherical mirrors were designed and are being fabricated; spherical
mirrors will be used in the interim until the parabolic mirrors are received.
Hope to assemble system in next few weeks.
-
OPTICAL LEVER:
Some of the mechanical parts for magnified focus lens are still in process
of being fabricated.
-
FARADAY ISOLATOR:
The HWP assembly from KLC is in shipment.
All of the other parts have been cleaned and baked.
Hope to assemble system in next week.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Loose screws in the PSL and AP1 tables have been fastened down.
- Steve is working with Larry on a particle filter
for the N2 purge line.
- Steve is working with Larry on aluminum racks
to hold chamber doors, to replace the wood ones.
- CES mounted an in-vac mirror for camera viewing
onto one of our viewports, but they chipped the glass
on the viewport.
Steve will do a vacuum test to see
whether it presents a risk for installation.
-
South Annex Bake Ovens (Taylor, Cardenas):
- In-vacuum mirrors are being prepared for installation
by Steve and Bob. They have been marking the mirrors
with an etching pen, on the sides.
They learned that mirrors from CVI need special
low-temp baking or the coatings will peel off!
- Bob is cleaning, baking, and testing the OSEMs
that he built to complete all the 40m optics.
He notes that we can expect a ~ 25% failure rate,
but he can catch the failures early and reliably.
- All bake ovens are in good repair and available.
January 17, 2003
- Student Alexei Ourjoumtsev, from
Ecole Normale Superieure in Paris,
is visiting us for 6 months.
He will be focusing on the implementation,
optimization, and characterization of the alignment
sensing and control for our suspended-mass mode cleaner.
He will also contribute to the commissioning of the
our new faraday isolator and MMT systems
(with Mike Smith), and our new optical sensing trains.
Please make him welcome!
- A Safety audit team, headed by Bill Tyler,
visited the 40 Meter lab on Thursday morning.
A variety of safety and ergonomic issues were discussed
with the 40m lab team, and action items identified.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- There was a lull in ISS commissioning and other activity,
so that the MC was allowed to maintain lock continuously for
39 hours over the last weekend; it may be a record.
- Osamu continues to measure and analyze the frequency noise
of the PSL, using the mode cleaner error signal.
- The 7 Hz oscillation that prevented the MC servo gain
from being turned up, disappeared when MC2's suspension controls
moved from the 1Y5 rack (running at 2048 Hz) to the 1Y4 rack
(running at 16 kHz). It re-appears when length control is
applied to Mc1 or MC3 (still in the 2048 Hz rack).
This could have something to do with digital filtering
on the ISC110B which digitizes the OSEM sensor signals.
Investigation continues.
- Now, a peak ~ 18 Hz dominates the MC frequency noise spectrum.
It is likely that this is the suspension bounce mode,
and Dennis will implement a digital notch filter
for all 3 suspended optics.
- There is a family of noise peaks at 500-700 Hz
in the frequency noise spectrum. Osamu believes that he
has traced it to mirror mounts on the periscope
at the end of the PSL table. He will try different
mirror mounting schemes.
- Osamu traced broad-band noise to loose scres on the
PSL and other optical tables. Larry Jones implementing
some hardware to prevent these screws from vibrating.
- Osamu continues to investigate the excess noise
in the 40-200 Hz region, which he suspects is alignment noise
in the MC suspensions. He is trying to excite the
pitch and yaw of the mirrors, but the digital excitation points
don't appear to be working.
- Osamu is working with Alexei and Ben to implement
alignment control of the MC launch beam.
- Osamu found that the spectrum analyzer itself was
contributing noise to the noise measurements,
and is now filtering the signal being sent to the analyzer.
- The line harmonic noise (60 Hz multiples)
remains large, despite grounding of the DSC cables.
We continue to investigate.
- Ben remade the LO cable for the mode cleaner servo. The phase delay is
now optimized.
- Dennis and Ben altered the generic DAQ interface board to allow 16kHz
MC signals (MC Trans and MC Refl DC light) to be brought into DAQ.
Now, these signals are available in frames, dataviewer, and DTT.
- Core digital suspension controllers (DSC), and other Electronics (B. Abbott, Taylor):
- Dennis and Ben insulated the backs of seven Satellite Amplifier
Termination boards, and put them into the remaining 7 Sat Amps that we have
for the 40m.
- Dennis and Ben are now attempting to test the new suspension controllers
with the 3 suspended optics that are still sitting on a bench
in the South Annex: BS, ITMx, ITMy.
They have assembled all the electronics and cabling.
They are encountering a variety of problems with the DSC software
for which they need the help of Alex Ivanov.
- We still need to implement appropriate filtering for our
5" ("MOS") test mass suspensions. Ben will talk to Jay about this.
- Bob has wired up as much as he can on the 1X4 end station rack,
until Ben gives him more to do.
- We will push for completion of the MC alignment control.
We need a PZT driver from CDS.
Ben reports that Laurie will be available to implement
the digital control software for the system
during the "E9 lull in CDS workload" ;)
- PSL and ISS (O. Miyakawa, B. Abbott, R. Abbott, F. Nocera, D. Ugolini):
- Flavio, Rich, and Ben
continue to work on ISS at the 40m PSL.
Flavio is cleaning up all the cables and pickoffs,
and will re-test with the PD downstream of the PMC
(but still before the MC).
- Osamu and Steve completed their measurements of the
beam power everywhere on the PSL table,
showing no anomalies in the power budget.
- However,
they observed noticable intensity variations,
and they continue to investigate.
- They plan on improving the mode matching
into the PMC to increase the transmitted power.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Received parts:
Some of the mechanical parts for the mode matching telescope were received.
-
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are pending
from SORL; re-worked half-wave plates from KLC, for the Faraday
isolator; drive electronics to drive the x and y axes of the 2nd PZT
vacuum IFO steering mirror, from Piezo-Jena. Mounting collar for
mounting the PZT tilt platform onto the DLC vacuum mirror mount and
the mirror holder, from CA Machine.
-
IFO MODE-MATCHING TELESCOPE:
Some of the telescope mechanical parts are still in process of being fabricated.
Hope to have the parabolic mirrors, and begin to assemble the
telescope, within the month.
-
OPTICAL LEVER:
Mechanical parts for magnified focus lens are in process of being
fabricated by two outside machine shops.
Hope to assemble prototype in next couple of weeks.
-
FARADAY ISOLATOR:
The HWP assembly from KLC is in shipment.
All of the other parts have been cleaned and baked.
Hope to assemble system in next couple of weeks.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Dennis discovered that the autoburt system failed
to create a "2003" directory, and thus did not store
autoburt files for the 1st week of 2003. He has fixed it.
- Housings for illuminators and cameras
for the chamber viewports are still in fabrication at CES.
Expect them in the next 2 weeks.
- Beam tubes from ports to optical tables,
specially designed by Larry, are still in fabrication at CES.
Expect them in the next month.
- The crane repairman repaired the vertex crane,
and Steve reports that all 3 cranes are working properly.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob completed a bake job on the Faraday Isolator TGG
rods and magnet.
- Bob has prepared 12 long and 12 short OSEM coil bodies for the 40m and they
are now in the oven for the hot bake @ 200C.
He also has built enough boards to complete all the 40m OSEMs.
- Steve and Bob have been marking the small in-vacuum optics
with an etching tool, prior to clean / bake.
- Bob continues to assemble an inventory of the clean room,
and do maintenance on the bake ovens.
January 10, 2003
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu has been measuring and analyzing the frequency noise
of the PSL, using the mode cleaner error signal.
After much work, the noise is 10x lower than it was last month
(between 40-400 Hz).
Except for narrow-band peaks (60 Hz harmonics and
an excess from 500-750 Hz which may be due to the periscope),
the noise spectrum meets the spec from 50 - 10,000 Hz.
see plot in 40m ilog.
- The improvement was mainly due to the ability to turn up
the MC length servo gain.
The gain was limited because of the presence of a 7 Hz
oscillation, which is believed to originate on the PSL table;
Flavio saw it while working on the ISS.
It might even be due to the ISS; this is under investigation.
It's gone now, due either to changes in the ISS, OR
due to the movement of the MC2 digital suspension controls
from rack 1Y5 to 1Y4. Not sure, but we'll figure it out.
- Anyway, with the 7 Hz gone, Osamu turned up the
MC length control gain. He believes that this reduced the coupling
of alignment noise in the MC suspensions to the MC error signal
between 40-400 Hz, leading to the observed in total
MC error signal in that band.
- However, the line harmonic noise (60 Hz multiples)
is now larger.
This is likely due to the movement of the MC2 digital suspension controls
from rack 1Y5 to 1Y4.
Ben says that new cables definitely need better grounding,
and he'll do that.
- With the higher MC length control gain,
the x-over frequency from length to frequency control
has gone up from 6.7 Hz to 26.6 Hz.
That has improved the noise and also the lock stability
(no VCO saturation);
however, the net effect is that the MC contributes less to
the laser frequency stabilization.
- To assess this, Osamu has compared the frequency noise
to the required stability for the main interferometer
(assuming CM rejection to 1%).
He finds that we barely meet specs (a terrific achievement!),
except in the region
where GW sensing is optimized with RSE detuning (4000 Hz for the 40 m).
A common mode servo will improve this.
- We will measure the frequency noise (and CM rejection)
with a short-arm Michelson
core interferometer as soon as we have assembled one.
- Osamu has assembled a frequency noise budget from
many sources: seismic, PSL/FSS frequency noise,
intensity noise, shot noise, mode cleaner sensing noise,
PMC length noise.
It almost saturates the total observed noise,
but not completely.
see plot in 40m ilog.
- These results are very impressive, and Osamu will present them
in a commissioning meeting very soon.
- Core digital suspension controllers (DSC), and other Electronics (B. Abbott, Taylor):
- Our new DSC rack (1Y4) is almost fully instrumented.
Four of 6 controllers (for MC2, BS, ITMx, ITMy)
are fully working, but only the MC2 controller
has yet been fully tested.
Ben ran timing cables to all the front end controllers in the rack.
The controllers for the two recycling mirrors
require only a pentium and 2 penteks.
- Dennis et al will test the new controllers
with the 3 suspended optics that are still sitting on a bench
in the South Annex: BS, ITMx, ITMy.
- Dennis is looking into what filters need modification
for our test masses, which are more massive
than our SOS optics and with different pendulum, pitch, yaw frequencies.
- Dennis and Ben are chasing down the source of the 60 Hz
noise which appears to be associated with the MC DSC electronics.
- Ben has assembled an inventory of electronics
modules that will be needed to complete the
End Racks.
He talked to Todd, and they have worked out an agreement to fill the
list.
- Bob continues to work on the wiring of
the south end (1Y9) rack,
the east end (1X4) rack,
and the auxiliary controls rack (1X1).
- Ben installed a
permanent (3m long) MC servo LO cable.
- Still need to arrange for the MC Trans and MC Refl DC light
to get to the DAQ for 16K logging.
- We will push for completion of the WFS alignment control.
We need a PZT driver from CDS, and
the completion of digital ASC control software and hardware
(at the sites, ASC for the MC is done with analog electronics).
- Dennis and AJW are reviewing all the info that
gets logged to frames from fast and slow channels,
to make sure it is all correct and as desired.
- PSL (O. Miyakawa, M. Smith):
- Osamu and Steve measured
beam power everywhere on the PSL table.
None of the PDs we have can take the full power;
they are attenuating the power in various ways.
- The power survey shows no anomalies,
except for a large loss of power in the PMC
transmitted beam (T < 50%; used to be ~ 80%,
and should be ~ 87%).
Presumably, the mode matching and/or alignment
has been screwed up, and Osamu will re-optimize.
- Intensity stabilization (B. Abbott, R. Abbott, F. Nocera, D. Ugolini):
- Flavio, Rich, and Ben
continue to work on ISS at the 40m PSL,
with their improved servo with two actuators:
a DC-coupled path with LF actuation on the
current adjust on the laser power supply,
and an AC-coupled path with HF actuation on the current shunt
on the laser package.
- As of Wednesday, they've gotten it all to work,
achieving intensity noise suppression of ~ 140 dB
above a few hundred Hz, with large bandwidth.
The remaining required 20 dB may be harder to get,
for optical reasons (polarization-dependent effects, etc).
- They did this with the ISS PD upstream of the PMC.
Now, they're cleaning up all the cables and pickoffs,
and will re-test with the PD downstream of the PMC
(but still before the MC).
- Ben sent packaged ISS PD's to all the sites:
two to Hanford, and one to
Livingston.
These were followed by their tester boards, travellers, and
test procedures.
He is interfacing with Flavio regarding his use of the DC PD in his
Intensity Servo.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Received parts:
Faraday rotator from EOT was received and is being baked. All lenses for
the optical lever prototype were received.
-
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are pending from
SORL; re-worked half-wave plates from KLC, for the Faraday isolator; drive
electronics to drive the x and y axes of the 2nd PZT vacuum IFO steering
mirror, from Piezo-Jena.
-
IFO MODE-MATCHING TELESCOPE:
Telescope mechanical parts are in process of being fabricated.
Hope to have the parabolic mirrors, and begin to assemble the
telescope, within the month.
-
OPTICAL LEVER:
Mechanical parts for magnified focus lens are being fabricated by two
outside machine shops.
Hope to assemble prototype in next couple of weeks.
-
IFO STEERING MIRROR:
A purchase requisition for the mounting collar for mounting the PZT tilt
platform onto the DLC vacuum mirror mount and the mirror holder was issued.
-
FARADAY ISOLATOR:
Waiting on the HWP assembly from KLC.
Hope to assemble system in next couple of weeks.
- Modeling of Advanced LIGO in E2E (Miyakawa):
Osamu continues to work on
the design of a dual-recycled summation cavity module.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Dennis has changed the passwords on all 40m lab accounts
on all platforms.
- Housings for illuminators and cameras
for the chamber viewports are in fabrication at CES.
- Dennis is working with TMC on our STACIS seismic isolation
problems (which are multiplying).
This will require some effort, but it not a high priority at the moment.
- Per request from Bill Tyler,
Steve assembled an inventory of all lab lasers,
summarized all the things we did
in response to last year's safety audit,
and is assembling a folder full of safety information,
minutes, etc.
- The end cranes are now fully repaired and working,
but the repairman broke the vertex crane in the process.
Hope to have it fixed by the end of the week.
- We will have a safety audit of the lab next week.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob did 6 bake jobs over the holidays,
from Mike Smith and Janeen.
- Bob cleaned, and is baking, the faraday isolator parts.
- Bob repaired some problems with one bke oven,
and is planning routine maintenance tasks.
- Bob and Janeen have agreed on QC procedures for
the OSEMs he's been building.
- Bob gave a bunch of OSEMS that were for the 40m to Janeen,
so he will be making new ones over the next month.
- In response to a safety inspection of the South Annex,
Bob has moved all the flammable cleaning chemicals
to a locked cabinet in the gated area outside the lab.
He has also arranged for carpenters to stiffen his equipment racks.
December 20, 2002
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- All 3 MC suspended optics are again damped.
The MC length control is being applied to MC2.
The MC now acquires and maintains lock reliably.
- A lens on the PSL table was accidentally bumped,
so Osamu realigned the beam all the way through to the MC.
He then measured the visibility of the MC to be 95%,
the best we've achieved so far.
- Osamu had changed a filter on the PMC servo board
and then turned up the gain on the PMC length control servo;
UGF is now 7.6 kHz.
As a result, frequency noise out of the PMC,
as measured by the MC, has gone down significantly in the
100-500 Hz region.
- Frequency noise as measured by the MC is now within specs
above 200 Hz. From 50-200 Hz, we suspect that alignment noise
dominates.
We will check this by playing with the gain of the pitch
and yaw damping servos for the MC suspensions.
-
We will push for completion of the WFS alignment control.
We need a PZT driver from CDS, and
the completion of digital ASC control software
(at the sites, ASC for the MC is done with analog electronics).
- At lower frequencies, there's lots of noise
when the PSL enclosure HEPA filter is turned on.
We're not sure if the noise is transmitted mechanically
or acoustically; but we will try various acoustic
and mechanical shielding.
- Core digital suspension controllers (DSC), and other Electronics (B. Abbott, Taylor):
- Alex Ivanov is completing the remaining work
on new software for the DSC system.
- After chasing down some birthing problems
with our newly-modified digital suspension controllers,
all 3 MC suspended optics are nicely damped;
many thanks to Alex Ivanov!
- Dennis re-diagonalized MC2 after its controls
moved to a different crate, and saw little change.
- Dennis is looking into what filters need modification
for our test masses, which are more massive
than our SOS optics and with different pendulum, pitch, yaw frequencies.
- Dennis and Ben are chasing down the source of the 60 Hz
noise which appears to be associated with the de-whitening filter
for MC2.
We've been running with hardware dewhitening turned off for MC2.
We suspect an ungrounded cable to the dewhitening board,
and Ben will investigate.
- Ben and Bob are running a few more cables:
timing cables from the GPS fanout to the DSC front end crates;
permanent (3m long) MC servo LO cable;
cable for 16K readout of MCR and MCT power signals.
- Bob continues to work on the wiring of
the south end (1Y9) rack,
the east end (1X4) rack,
and the auxiliary controls rack (1X1).
- Ben has placed an order with Todd
for all our remaining needed electrooptics:
LSCPDs, WFSs, QPDs, oplev QPDs, electrooptic shutter controllers.
- We will need another GPS receiver and timing fanout module
to service the front end crates for the end suspensions
and for the LSC and ASC systems.
- Dennis and AJW are reviewing all the info that
gets logged to frames from fast and slow channels,
to make sure it is all correct and as desired.
- PSL (O. Miyakawa, M. Smith):
- Osamu and Steve are measuring the
beam power everywhere on the PSL table.
- After that, they will set the beam attentuators
to provide maximum beam to the PMC,
and appropriate levels of beam into the
PMC reflected RFPD, the ISS PD, and then into the mode cleaner.
- Intensity stabilization (B. Abbott, R. Abbott, F. Nocera, D. Ugolini):
- Flavio, Rich, and Ben
continue to work on ISS at the 40m PSL.
- They are hampered by intermittant very large intensity fluctuations
which saturate their PD and servo.
Osamu does not believe it's on the beam; we suspect the ISS PD itself.
They will investigate.
- They are developing a servo with two actuators:
a DC-coupled path with LF actuation on the
current adjust on the laser power supply,
and an AC-coupled path with HF actuation on the current shunt
on the laser package.
- Ben is making several ISS PD's for the sites.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
3 each, 1in mirror mounts are pending from Newport; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; Faraday rotator
from EOT; . The half-wave plates from KLC, for the Faraday isolator, are
being re-worked to vacuum-compatibility standards.
An additional set of servo controlled drive electronics to drive the x and
y axes of the 2nd PZT vacuum IFO steering mirror was ordered.
Lenses for the optical lever prototype were ordered.
-
IFO MODE-MATCHING TELESCOPE:
Telescope mechanical parts are in process of being fabricated.
-
OPTICAL LEVER:
Working drawings for magnified focus lens are complete and were released to
DCC. RFQ's were sent out to two machine shops.
Mike will design the required power supplies and controls
for the lasers and the zoom lenses.
-
IFO STEERING MIRROR:
The mounting collar for mounting the PZT tilt platform onto the DLC vacuum
mirror mount and the mirror holder are in the process of being designed.
- Modeling of Advanced LIGO in E2E (Miyakawa):
Osamu is studying the design of the power-recycled summation cavity
in E2E, and how to generalize it for a dual-recycled
summation cavity.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Larry Jones has designed housings for illuminators
for the chamber viewports, and they have been sent to CES
for fabrication.
- Dennis is working with TMC on our STACIS seismic isolation
pedestal problem (we have one, but they did not see it
when we sent it back to them for repair).
- Per suggestion from Helena,
Steve is looking into replacing the HEPA filters,
and installing a de-ionization bar,
on our south annex flow benches.
- Per request from Bill Tyler,
Steve will assemble an inventory of all lab lasers,
and will summarize all the things we did
in response to last year's safety audit.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob is working through a long list of bake jobs
from Mike Smith and Janeen.
- Bob is working with Janeen and the advanced suspensions
crew to resolve problems with the OSEMs that he made for them.
- We are looking into the purchase of a new RGA system (Dycor LC 200M)
to replace one that is not repairable.
December 13, 2002
- Core IFO:
We continue to work towards constructing a short-arm Michelson
with our three newly suspended optics (BS, ITMx, ITMy).
The digital suspension controllers are nearly ready
and we hope to have 3 suspended optics (BS, ITMx, ITMy)
damped in the next week or 2. (Exactly what I said last week!).
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Alex has completed most of the work on the digital suspension controllers (DSC),
and all three suspended MC mirrors are now being damped with the new system.
Osamu is working on re-aqcuiring MC lock as I write.
- Osamu quantitatively compared the laser frequency noise
as measured in the PSL PMC and in the suspended mass mode cleaner.
He finds excellent agreement (ie, the MC frequency noise
is saturated by the frequency noise transmitted by the PMC)
in the ~300 - 20K Hz region,
except for a broad peak around 500 Hz and a narrow one around 12 kHz.
The origins of these excess noise peaks are unknown and will be hunted down.
- Above 20kHz, shot noise in the PMC measurement dominates,
and we will address this by increasing the laser power in the PMC.
We had been attenuating the beam upstream of the PMC,
and we will stop doing that, but not before Osamu completes
new measurements with the MC.
- Still on the to-do list:
permanent (3m long) MC servo LO cable;
cable for 16K readout of MCR and MCT power signals.
- Core digital suspension controllers (DSC), and other Electronics (B. Abbott, Taylor):
- Alex Ivanov has nearly completed work on new software
for the DSC system: upgrading the SOS controller software,
new code for core optics controller hardware,
DAQS and EPICS links, new EPICS screens, etc.
- Ben and Bob have finished all mods to the
40m vertex suspensions wiring:
moving MC2 controls from 1Y5-7 to
1Y4-33 and SRM controls from 1Y4-8 to 1Y4-33,
including all the associated EPICS controls wiring and database changes.
- Ben and Dennis have finished testing all the
epics controls and readbacks for the 40m vertex suspensions controls.
- All hardware for the 40m vertex suspensions controls
are in place except for one Pentium and 2 timing modules,
which are under test at Wilson House.
- We now have all three suspended MC optics damped
by the new system, and are close to being able to
damp three more suspended optics (BS, ITMx, ITMy).
- Bob continues to work on the wiring of
the south end (1Y9) rack,
the east end (1X4) rack,
and the auxiliary controls rack (1X1).
- Dennis put all of the STACIS readback info into master.config
for logging to frames.
- PSL (O. Miyakawa, M. Smith):
- Osamu continues to study PSL PMC noise, as discussed above.
- A lens near the PMC was bumped yesterday,
and Osamu is working on re-establishing good alignment of the beam
downstream.
- Osamu finds that the PSL PMC frequency noise requirement
(T990025-00-D, p28, fig18)
is inconsistent with the overall PSL frequency noise requirement
(T990025-00-D, p19, fig9, or T970080-09-D, pg 10, table 1).
Fortunately, the PMC performs at least a factor 10 better than
the design requirement (even on our noisy PSL table),
allowing us to (just barely) meet the overall PSL spec.
- Steve purchased a compact laser power PD
to make it easier to study the laser power everywhere on the
crowded PSL table.
- Ben worked with Flavio on the ISS actuation at the 40m.
- Ben continues to test the DC PD for ISS
to prepare it for delivery to the sites in
time for S2.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Received parts:
3 PZT tilt platforms and 1 servo control drive electronics and strain gauge
read-out electronics from Piezosystems Jena.
- OPTICS PARTS LIST,
Orders pending:
3 each, 1in mirror mounts are pending from Newport; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; Faraday rotator
from EOT; . The half-wave plates from KLC, for the Faraday isolator, are
being re-worked to vacuum-compatibility standards.
Only one set of servo controlled drive electronics to drive the x and y
axes of the two PZT vacuum IFO steering mirrors was inadvertently ordered.
A second set will be ordered.
-
Part numbers were scribed and the in-vacuum mirrors and beam splitters are
being cleaned and baked.
-
FARADAY ISOLATOR:
Faraday Isolator mechanical parts and polarizing prisms for Faraday
isolator have been cleaned and baked, and are awaiting assembly.
Hope to have it ready for installation by next month.
-
IFO MODE-MATCHING TELESCOPE:
Telescope mechanical parts are in process of being fabricated.
Hope to have it ready for installation by next month.
-
OPTICAL LEVER:
Working drawings for magnified focus lens are almost complete.
Hope to have an assembled prototype by next month.
-
Mike assembled a list of electro-optical parts
(LSCPD's, WFS's, QPD's, oplev QPD's, EOS's)
needed to complete the core IFO sensing,
and Mike and AJW have "placed the order" with the Wilson House,
through Ben.
- Modeling of Advanced LIGO in E2E (Miyakawa):
Osamu continues to come up to speed with E2E / Han2K / SimLIGO
in his spare time, and is making progress.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Steve fitted a video camera with a telecope
and can now easily see the wire, standoff, and magnet assemblises
on the optics, *through* the OSEM hole.
This will be very helpful during installation,
debugging, and repairs of our suspended optics in the vacuum chambers.
- A STACIS seismic isolation pedestal was oscillating,
so we sent it back to TMC for repair.
They found nothing wrong with it, and returned it to us.
Steve and Dennis have re-installed it, and it is still misbehaving. Sigh.
- Steve purchased some needed video monitors.
-
South Annex Bake Ovens (Taylor, Cardenas):
- A load of mechanical parts for the 40m Faraday Isolator has been
cleaned, baked, scanned, and packaged with traveller, ready for assembly.
- Bob has bake loads in 3 ovens:
some 40m OSEM parts; stainless steel for Janeen,
and a big Al load for Janeen.
- Several more bake loads are in the queue.
- Bob wants to purchase a new RGA system (Dycor LC 200M)
to replace one that is not repairable.
December 6, 2002
- Core IFO:
We continue to work towards constructing a short-arm Michelson
with our three newly suspended optics (BS, ITMx, ITMy).
The digital suspension controllers are nearly ready
and we hope to have 3 suspended optics (BS, ITMx, ITMy)
damped in the next week or 2.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Currently, work on the digital suspension controllers (DSC)
means that the MC cannot acquire lock.
We hope to get back to MC lack in the next few days.
- Osamu measured the intensity noise after the PSL PMC,
and estimated its contribution to the frequency noise in the PSL
as monitored by the MC.
It is ~ 50db below the observed frequency noise (ie, negligible).
It contributes due to a non-zero offset of the MC servo
from exact resonance; Osamu estimates this to be
around 6e-12 m.
It's different from lock to lock; Osamu will study the variations.
It is possible to better zero this offset, but Osamu
does not think that it will be necessary, since the
contribution to frequency noise is so small.
However, this intensity noise
will contribute to noise in the main IFO GW channel
due to the imperfect contrast defect; so it
definitely should be reduced (by the ISS servo, being commissioned now).
- Steve and Osamu have searched for couplings of
mechanical and/or acoustic noise onto the beam in the
PMC and MC. They find no evidence for noise from
the air conditioning, vacuum pumps, room lights, etc.
- On the other hand, they have
determined that the PMC,
mounted firmly on the PSL table, is very sensitive
to mechanical and/or acoustic noise at the PSL table.
A small tap on the table or table legs is easily seen
in the PMC servo error signal.
This introduces intensity and frequency
noise onto the beam.
(No such coupling was observed for the frequency stability servo).
This noise is clearly seen in the MC frequency noise spectrum.
- Osamu and Steve are investigating two fixes:
the first is to better isolate the PMC from noise.
Steve is trying out different acoustic shields,
and is thinking about placing the PMC on a sheet of rubber.
He will check out the effect of the laser cooling water.
- Another fix is to
increase the PMC servo gain to tie it better to the quiet
(FSS-stabilized) input beam.
Osamu noted that the PMC servo gain was limited by a 66 kHz
(mechanical) resonance; the notch filter
in the servo card was not well tuned to that resonance,
even with the trim pot turned all the way.
Osamu changed a capacitor on the board,
and successfully notched out the resonance.
He was able to turn up the PMC gain slider
from 15 dB to 30 dB,
increasing the UGF from 1.5 kHz to 5.8 kHz (spec is 3.0 kHz).
He will check the effect of these changes on the beam
(as monitored by the MC error signal)
as soon as th upgrade of the DSC system
is complete (so that we can re-aquire MC lock).
- Still on the to-do list:
permanent (3m long) MC servo LO cable;
cable for 16K readout of MCR and MCT power signals.
- Core digital suspension controllers (DSC), and other Electronics (B. Abbott, Taylor):
- Alex Ivanov has been working hard on software
for the DSC system: upgrading the SOS controller software,
new code for core optics controller hardware,
DAQS and EPICS links, new EPICS screens, etc.
- Ben has finished re-drawing the wiring diagrams for the 40m vertex
suspensions.
These changes include moving MC2 controls from 1Y5-7 to
1Y4-33 and SRM controls from 1Y4-8 to 1Y4-33.
It also included all of the
associated epics control and other changes that was dictated
by these other changes.
- Ben has most or all of the modules in place,
and he and Bob are making the wiring changes.
Hope to be complete by the end of the week!
- Dennis is helping with the CPU boards, boot software,
EPICS data bases, etc,
in the DSC electronics rack (1Y4).
- Bob continues to work on the wiring of
the south end (1Y9) rack,
the east end (1X4) rack,
and the auxiliary controls rack (1X1).
- The stand-along SOS analog suspension controller
that we borrowed from Betsy will be used by
Paul Russell for Janeen's earthquake stop rework prototyping
(which ises an SOS borrowed from us).
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Received parts:
1.5 in and 2.0 in fixed vacuum mirror mounts.
-
Orders pending:
3 each, 1in mirror mounts are pending from Newport; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; Faraday rotator
from EOT; 3 PZT tilt platforms and 2 servo control drive electronics and
strain gauge read-out electronics from Piezosystems Jena.
-
In-vacuum mirrors and beam splitters are being cleaned and baked.
-
FARADAY ISOLATOR:
Faraday Isolator mechanical parts are being cleaned and baked. Polarizing
prisms for Faraday isolator have been cleaned by Helena
and are ready for baking.
The half-wave
plates from KLC, for the Faraday isolator, are being re-worked to
vacuum-compatibility standards.
Expect the Faraday Rotator in a couple of weeks.
Hope to have a complete system within a month.
-
IFO MODE-MATCHING TELESCOPE:
Telescope mechanical parts are in process of being fabricated.
Expect off-axis parabolic mirrors in a month,
Hope to have a complete system shortly thereafter.
-
OPTICAL LAYOUT:
An ASAP ray model of the 40m IFO optical beams is complete.
An
evaluation copy of Hijaak, file conversion software, was used to convert
the ASAP graphic files to DWG drawing files, which were then x-refed onto
the integrated layout drawing.
Ghost beams
were generated; beam dumps, baffles, and pick-off mirrors were placed and
oriented in the integrated layout drawing to agree with the ASAP model.
-
OPTICAL LEVER:
IR laser and projection telescope for optical lever prototype were
received. Working drawings for magnified focus lens are in process.
A cheaper and more local source for a suitable 830-nm laser
has been found. The laser power / controls must be designed.
-
INITIAL POINTING BEAM
A pick-off beam to monitor the position of the initial pointing beam on the
power recycling mirror was added to the integrated layout drawing.
- Optics (Billingsley, Armandula), suspensions (Romie), OSEMs (Bob):
- Our BS, ITMx, and ITMy, are suspended and sitting on the
South Annex clean room flow bench. They have clean OSEMs,
are balanced and have been damped successfully,
and are ready for installation as soon as our DSC system is ready for them.
-
Mods to the ETM suspension parts (MOS) are complete.
Bob Taylor has the traveler and reworked parts for cleaning and baking.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Steve replaced the backup batteries on the maglev turbopump (TP2)
power supply.
- Larry Wallace ordered a UPS system for our vacuum rack,
to replace the one that tripped off 2 weeks ago,
bringing the vacuum controls down.
- The misbehaving STACIS seismic isolator (SENW-x)
was repaired by TMC and is enroute back to us.
- CES is working on the anodized custom beam tubes
(between chamber viewports and sensing tables)
that were designed by Larry Jones; should be ready by January.
- CES is working on the camera viewport mounts and
in-vacuum mirror mounts for the cameras that view
the core optics beam spots,
that were designed by Larry Jones; should be ready by January.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob is working through many bake jobs for the coming months,
including parts for the Faraday Isolator and MMT,
in-vacuum mirrors, OSEMs, and 6 loads for Janeen.
- Bob has received a re-worked RGA head for oven C.
A second re-worked RGA head (a spare) was sent back due to many problems.
November 22, 2002
- Core IFO:
We continue to work towards constructing a short-arm Michelson
with our three newly suspended optics (BS, ITMx, ITMy).
The suspended optics are ready to go.
Currently, there's much effort towards getting the
digital suspension controllers for those optics going.
Mike Smith is assembling a faraday isolator and crude
mode matching telescope.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- After re-aligning our two IOO pockels cells,
Osamu got the MC visibility up to 91.7%.
- Osamu is reviewing all the RF signals in the MC controls rack,
and determined the optimal signal strength for the
local oscillator into the MC servo
to get the strongest and cleanest error signal.
- Osamu optimized the gain on the PSL
frequency stability servo (FSS). He turned the gain up a bit
from where it was before.
This allowed him to turn up the MC servo gain in both paths.
As a result, the mode cleaner servo UGF could be pushed up
from ~ 50 kHz to 67 kHz, with a phase margin of 28degrees.
The resultant frequency noise is now a few dB lower.
- The PSL frequency noise as measured by the MC (in loop)
is now close to specs, but there remains excess noise:
seismic, from 10-30 Hz; acoustic, from 30-300 Hz;
(believed to be) acoustic, from 300-3000 Hz;
and electronic, above 4 kHz.
Osamu will continue to investigate.
- Dennis and Ben made another phase shifting cable for the MC servo
This one is longer, as we were 180 deg. off for the last
one. We can now lock using this cable; but it's a temporary BNC-to-SMA;
a proper permanent (3m long) cable will be made soon.
- Ben has made a path for the mode cleaner fast signals into DAQ.
Filters on the AA DAQ interface board have been switched to 16 kHz.
Some of the gains need to be adjusted to deal with the signals at hand.
And, one more 4-pin-lemo cable needs to be run.
One channel, at least, is being correctly read out,
and a DTT spectrum looked right.
However, it looks like one half of an ISC110b ADC (16 of 32 channels)
is dead.
- Core digital suspension controllers, and other Electronics (B. Abbott, Taylor):
- Rolf says that Alex will work towards getting
digital suspension controller software up and running
for our vertex core suspensions.
He's already putting 2 VME pentiums through their paces.
The DAQS system will have to be upgraded
(in particular, the test point manager in DAQSCTRL0,
so that we can excite pitch and yaw degrees of freedom with GDS).
The SOS control software will also be upgraded.
And, he will arrange to have EPICS screens automatically generated
for the 40m, as well as for the sites.
- Rolf tells us that we can't control 5 vertex core optics
(BS, PRM, SRM, ITMx, ITMy) with only 2 front-end output crates,
as we originally thought.
Ben is rearranging some of the crates in the 1Y4 and 1Y5 racks to allow
another output crate.
- Rolf tells us that we can extract data from
the DSC reflective memory into EPICS, using a Sun
EPICS server (this is a new and welcome development).
We will get a new Blade 100, and are scrambling
to find 2 reflective memory PCI cards (VMIPCI-5579)
for the DAQS and DSC reflective memory networks.
An alternative is to use our under-utilized br40m,
which already has a DAQS reflective memory PCI card.
- Rolf tells us that we will want to upgrade to
2 Giga Baud Reflective Memory with Fiber Optic connections
(Our current RM network is 250 MB).
We'll need on the order of 10 cards, at ~ $2K/card.
- Ben has finished testing the epics control of the
core optics DSC rack, after fixing some problems.
- Bob has moved crates from the south end (1Y9) rack
to the east end (1X4) rack, which has been wired and powered.
Now he's working on the south end rack.
- Dennis has almost completed and checked out the EPICS database
for the EPICS control (C1MOSAUX) in the core optics DSC rack (1Y4).
It successfully exhanges information with the watchdog code in 1Y5.
- All of the Pentiums for 1Y4 are
now in hand, and the Penteks should be by the end of next week.
All cables, satellite amplifier boxes, etc, are ready.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
3 each, 1in mirror mounts are pending from Newport; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; IFLEX1000 IR
laser for optical lever is pending from Point Source Ltd; ; polarizers for
Faraday isolator from KLC; Faraday rotator from EOT; 3 PZT tilt platforms
and 2 servo control drive electronics and strain gauge read-out electronics
from Piezosystems Jena; 1.5 in and 2in fixed vacuum mirror mounts from ASCO
are expected by 11/16/02.
-
FARADAY ISOLATOR:
Faraday Isolator mechanical parts were check-assembled and are ready for
cleaning and baking. The half-wave plates were received from KLC, but they
will be sent back for re-work since they were not manufactured to
vacuum-compatibility standards.
-
IFO MODE-MATCHING TELESCOPE:
Working drawings for the telescope mechanical parts are complete and were
released to the DCC. An RFQ package was sent to two machine shops for bid.
-
OPTICAL LAYOUT:
An ASAP ray model of the 40m IFO optical beams is complete except for the
two end chambers. Ghost beams were generated and beam dumps, baffles, and
pick-off mirrors were placed and oriented in the ASAP model. An evaluation
copy of Hijaak, file conversion software, was obtained in order to convert
the ASAP graphic files to a DWG drawing file that can be imported into the
ACAD 40m optical layout.
- Alignment: Mike has all the equipment for initial
alignment of the 40m core IFO and sensing beams,
including an 850-nm laser with a reticule pattern.
- Optics (Billingsley, Armandula), suspensions (Romie), OSEMs (Bob):
- Our BS, ITMx, and ITMy, are suspended and sitting on the
South Annex clean room flow bench. They have clean OSEMs,
are balanced and have been damped successfully,
and are ready for installation as soon as our DSC system is ready for them.
-
Janeen made small changes to the 40m test mass suspension
top assembly drawing.
- Bob continues to assemble and test OSEMs
for the remaining 40m suspensions, and for other projects.
Janeen is using one of the 40m SOS's for earthquake stop testing.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Our PEM EPICS server cpu
(particle counter, STACIS, weather station)
was crashing daily. Dennis commented-out the reading
of the weather station, which is half broken
and useless anyway, and the crshes have disappeared.
- Steve reports that the vacuum system has been running
in "vibration-free" mode (ion pumps only) for 22 days,
with no problems, and AMU 41 peak has been low
(previously, the IP's were belching on occasion; this has stopped happening).
- The vacuum controls crate lost power shortly after midnight on
November 20. This appears to have been caused by the UPS system
tripping off. Steve notes that the battery was due to be replaced
2 months ago. The hardware interlocks all worked correctly,
and the vacuum system experienced no problems.
Steve has taken the UPS out of the system.
He'll replace the battery, but it is not clear whether
we want this thing back in!
We will investigate UPS systems for other places around the lab.
-
South Annex Bake Ovens (Taylor, Cardenas):
Bob is scheduling many bake jobs for the coming months,
including parts for the Faraday Isolator and MMT,
in-vacuum mirrors, OSEMs, and 6 loads for Janeen.
November 15, 2002
- Core IFO:
We continue to work towards constructing a short-arm Michelson
with our three newly suspended optics (BS, ITMx, ITMy).
We need to complete, and commission, the digital suspension controllers
for those optics; assemble and install a faraday isolator,
mode matching telescope, optical levers, and cameras.
And, we won't have length or aligment control systems.
We will rig something up with SR560's to control the Michelson.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Dennis and Ben made the phase shifting cable for the MC servo
local oscillator (we had been using a Marconi for the task!).
The LO signal is now 20 times bigger than before,
increasing the gain by that amount.
We will need to turn the gain back down in order to get the MC to lock.
Work in progress.
- Osamu has measured the intensity noise at the MOPA, the PMC,
and the output of the MC. The MC intensity noise has a big broad peak
at the pendulum (1 Hz) and pitch and yaw resonances.
Osamu measured these spectra with the PSL enclosure HEPA filter
on and off, and he sees a huge difference,
a clear factor 10 above 200 Hz.
- The intensity noise out of the PMC is a bit higher
than out of the MOPA; Osamu suspects acoustic noise
introducing intensity noise in the PMC, and will continue
to investigate.
- Osamu measured the PSL frequency noise using the MC as an
out-of-loop reference.
With the HEPA filter turned off, the frequency noise is almost
within spec above 300 Hz.
Osamu will optimize this by adjusting the gain in the PSL
frequency servo.
- In both the intensity noise and frequency noise spectra,
acoustic noise appears to dominate below 300 Hz.
Osamu will investigate and try to track down the source.
- Steve and Larry Jones are investigating ways of making the
MC2 suspension chamber less sensitive to
people walking by.
- Ben and Dennis continue to work on getting the mode cleaner
fast signals into the DAQ at 16384.
- Electronics (B. Abbott, Taylor):
- Bob has completed the cross-connect wiring for 1X4,
the east end rack, and powered it up.
He will move to 1Y9 (the south end rack) next.
Power for 1Y4 (the DSC for the vertex core suspensions)
is in.
- Dennis booted up the
EPICS control cpu (C1MOSAUX) in 1Y4,
the DSC for the vertex core suspensions.
Dennis has put together the EPICS database for it, and
Ben has put together the EPICS screens.
Ben and Lisa Goggin have begun checking out
the EPICS controls
They're having some trouble with the switch control through the XYCOM
220. Work in progress.
- Ben has delivered the remaining 7 suspension
satellite amplifier boxes required for the core optics.
- Ben is acquiring hardware for the end racks
(DSC, oplev, etc).
He is also acquiring optical levers and other components necessary for
suspensions completion.
- We await installation of the
code for the core optics
suspension controller rack (1Y4)
by Rolf and/or Alex. Their availability is in question...
- All of the Pentiums for 1Y4 are
now in hand, and the Penteks should be by the end of next week.
- Ben continues to work on the interface between the Glasgow suspension
electronics and CIT electronics.
He has begun testing the Dspace whitening interface board, and it seems
to be functional, and working as expected so far.
- Optical sensing (Smith):
- OPTICS PARTS LIST,
Orders pending:
3 each, 1in mirror mounts are pending from Newport; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; IFLEX1000 IR
laser for optical lever is pending from Point Source Ltd; ; polarizers and
half-wave plates for Faraday isolator from KLC; Faraday rotator from EOT; 3
PZT tilt platforms and 2 servo control drive electronics and strain gauge
read-out electronics from Piezosystems Jena; 1.5 in and 2in fixed vacuum
mirror mounts and an adapter spacer from ASCO are expected by 11/16/02.
- FARADAY ISOLATOR:
Faraday Isolator mechanical parts were received from CA Machine Co.
Mike will begin to assemble it, soon.
- IFO MODE-MATCHING TELESCOPE:
Working drawings for the telescope mechanical parts are expected to be
completed by 11/15, and will be sent out for quotes
shortly thereafter.
- OPTICAL LAYOUT:
An optical layout of the 40m IFO using ASAP has verified the ACAD layout
that was based on hand calculations of the beam trajectories. Ghost beams
will be generated with ASAP to determine the detailed placement of pick-off
mirrors and beam dumps, etc.
- Mike will try to add a QPD just before the beam
enters the main IFO, to monitor drifts in the beam position there.
The beam angle will be
monitored by a QPD ("initial pointing") at the east end.
- Optics (Billingsley, Armandula), suspensions (Romie), OSEMs (Bob):
- Our BS, ITMx, and ITMy, are suspended and sitting on the
South Annex clean room flow bench.
-
Last week, Steve and Osamu swapped out dirty OSEMs for clean ones
in our ITMx, ITMy, and BS, in the South Annex test bench.
Although the ITMs (on bigger suspension towers)
damped just fine, the BS did not damp properly
(with our test-bench stand-alone
analog suspension controller).
The wire was found to be touching the side magnet stand-off.
On advice from Janeen, Helena, and Betsy,
Steve replaced the wire according to procedures.
But, the new wire is also touching the side magnet stand-off.
And, it still did not damp properly.
Bob made a 40m long suspension controller cable
and ran it from our digital suspension controller system
to the test bench where the BS is sitting.
It damped well, with no problem.
We conclude that the stand-alone
analog suspension controller has developed a problem which
shows up only for SOS's.
Anyway, we now have a working suspended BS
and a nice long cable for running the DSC to the South Annex test bench.
-
Janeen wrote up the DCN
for the the remaining two 40m TM suspension changes.
Dennis signed the DCN and the test mass supsension parts are at CES
for rework. Mike expects to complete the work by Thanksgiving. Bob
Taylor is expecting them on Dec 2nd for cleaning and baking. They will
be assembled soon after that.
- Janeen borrowed one of our unassembled SOS suspensions
for prototyping some earthquake stop re-designs.
- Bob continues to build and clean OSEMs.
He has enough long and short OSEM bodies to build
all the remaining ones needed for the 40m core optics.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Dennis is arranging the shipment of one of our
STACIS seismic isolators (SENW-x) to TMC for repair.
- Larry Jones will work on camera mounts for viewing
the suspended core optics.
- Larry Jones is designing beam tubes from the IFO exit ports
to the optical sensing tables.
- Steve is arranging for crane power disconnects / protection
to be installed on all of our cranes.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob reports that two RGA heads sent to Dycor for repair
will cost $4660.
November 8, 2002
- Core IFO:
-
We are working towards constructing a short-arm Michelson
with our three newly suspended optics (BS, ITMx, ITMy).
-
We should have complete suspension controllers for those optics
in the next couple of weeks, and aim to have them installed
into the vacuum chambers, and damped, by the end of this month.
- We won't have final versions of three key elements of
the input optics
(from the suspended mass mode cleaner into the core IFO)
for another couple of months:
Faraday isolator, MMT, and steering mirrors.
Without a finished Faraday isolator, we are investigating various
ways to bring out the bright port signal for locking the
Michelson.
-
We also won't have final versions of the optical lever telescopes,
so we will assemble temporary versions.
We are working towards having cameras looking
at all the suspended optics.
- And, we won't have length or aligment control systems.
We will rig something up with SR560's to control the Michelson.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- ISS work at the PSL has meant that the MC has not been maintained
in lock for most of this week.
- Osamu and Steve continue to study effect of seismic and acoustic noise
(at MC2) on the MC lock stability.
- Steve discovered that there is a channel in the concrete floor
cutting east-west right underneath the MC end chamber;
this is likely contributing to the sensitivity of our MC lock
to motion near that chamber.
Steve proposes supporting the MC end chamber table
on some steel beams to "bridge" the channel.
- Osamu measured the mode-cleaner frequency noise while *clapping*,
and found a significant increase in the noise between 200 Hz and
1 kHz, suggesting that acoustic noise dominates here.
It may be coming in through the PSL enclosure, and we are considering
acoustic shields such as are employed at the sites.
-
Osamu found that an increase in the MCA gain causes an exponentially-
growing 7 Hz oscillation that quickly saturates the VCO path and
breaks lock. He
thinks it is a result of a 7 Hz resonance in the end chamber stack,
and will continue to investigate.
- Osamu found that if you increase the normal daily seismic noise by
about a factor of 4, the MC will not be able to hold lock. So nobody
should be kicking the end chamber.
- Ben made a generic DAQ interface card to get the mode cleaner
fast signals into the DAQ at 16384,
and has made and run the cables to the DAQ rack.
He's swapping the filter chips in the anti-alias chassis.
- Dennis and Ben will get the fast channels
into master.config.
- Intensity stabilization (B. Abbott, R. Abbott, F. Nocera, D. Ugolini):
- Ben and Flavio continue to
work on the PSL ISS, which is working,
but an order of magnitude short of spec.
-
Seven ISS DC photodiode PCB boards are stuffed, and await testing.
- Electronics (B. Abbott, Taylor):
- Bob assembled the cross-connects for the two end racks
(for the ETM suspension controllers, and transmitted beam sensing).
He is already beginning the wiring on the east end.
Ben is populating the racks with crates and modules.
- Dennis and Ben are getting ethernet into our core optics
suspension controller rack (1Y4).
- Rolf says that the code for the core optics
suspension controller rack (1Y4)
is very similar to the sites and should take only 2 days
to install.
- Jay plans to think about the mode cleaner digital WFS
code with Laurie.
- All of the Pentiums for 1Y4 are
now in hand, and the Penteks should be by the end of next week.
- Ben continues to design the interface between the Glasgow suspension
electronics and CIT electronics.
The Dspace whitening interface boards are being stuffed.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
3 each, 1in mirror mounts are pending from Newport; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; IFLEX1000 IR
laser for optical lever is pending from Point Source Ltd; ; polarizers and
half-wave plates for Faraday isolator from KLC; Faraday rotator from EOT; 3
PZT tilt platforms and 2 servo control drive electronics and strain gauge
read-out electronics from Piezosystems Jena; 1.5 in and 2in fixed vacuum
mirror mounts and an adapter spacer from ASCO are expected by 11/16/02;
Faraday Isolator mechanical parts from CA Machine Co are expected by 11/9/02.
- FARADAY ISOLATOR:
Awaiting parts.
-
IFO MODE-MATCHING TELESCOPE:
Redesign of the remote focus mechanism for telescope housing are almost
complete; a vertical degree of freedom adjustment was added to the
secondary mirror mount, similar to the LIGO design.
- Optics (Billingsley, Armandula), suspensions (Romie), OSEMs (Bob):
- Our BS, ITMx, and ITMy, are suspended and sitting on the
South Annex clean room flow bench.
- Steve, Dennis, and Osamu have swapped the dirty OSEMs
on our suspended ITMs with clean ones, and rebalanced them.
They're having a lot of trouble with the BS, which isn't damping
properly. The wire appears to be touching the side magnet.
Investigation continues.
- Janeen is writing up the DCN
for the the remaining two 40m TM suspension changes.
She expects that the re-machining should take a week,
and then another week for cleaning and baking.
- Janeen will borrow one of our unassembled SOS suspensions
for prototyping some earthquake stop re-designs.
- Bob continues to build and clean OSEMs.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- Dennis is working on getting RGA information into the DAQ system.
- Dennis is pusuing repair of one of our
STACIS seismic isolators (SENW-x).
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob is baking more OSEM parts.
He's preparing for a big (600+ pieces) bake job for Janeen.
November 1, 2002
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu is studying the effect of seismic and acoustic noise
(at MC2) on the MC lock stability.
He estimated the contribution of seismic and acoustic noise
to the MC frequency noise, and it quantitively explains
the noise spectrum below 30 Hz (but he's still working on refining this).
Seismic noise at the 40m is
10 times noisier than typical seismic motin of 10^(-7)/f^(-2).
- Osamu finds that lock is lost after an impulsive event
(deep-knee bends near MC2, shouting, etc)
with low frequencies, below a few Hz.
Lock is lost when the MC frequency loop error signal runs out of dynamic range.
The MC length loop does have enough dynamic range, but not enough gain.
The proposed cure is to increase the length path gain
at low frequencies, which is difficult because of a
7 Hz oscillation in that path at high gain, which
Osamu does not yet understand.
He will continue to investigate the MCL path.
- The MC beamtube appears to act like a microphone,
amplifying acoustic noise at the MC2 table.
The MC2 table itself may also be behaving this way,
with a resonance at ~ 50 Hz.
- Steve put a box of sand around the MC beamtube
to damp acoustic noise from propagating into MC2;
Osamu finds that it does indeed reduce vibrations
at the MC2 table by 5-20 dB between 10-500 Hz.
- Two notable acoustic noise sources are the
dry scroll pumps and the HEPA filter on
the PSL enclosure. These generate +20 dB noise peaks
at the MC2 table, at 830 and 500 Hz, respectively.
These don't seem to affect the lock, and
Osamu does not think these are a problem.
- Dennis is working on implementing
a resonant gain stage in the MC length path,
at the bounce frequency of 16.3 Hz.
So far, it just causes the MC to lose lock;
Dennis continues to tune the parameters.
(The work is hampered by the fact that we still don't
have fast MC signals in DTT/DAQ; but we will, soon).
- An earthquake (4.8M) a couple of days ago
knocked all the suspensions out of whack,
and the watchdogs that limit the actuation
appear to have worked correctly.
- Intensity stabilization (B. Abbott, R. Abbott, F. Nocera, D. Ugolini):
- Ben continues to work with Flavio and Rich on the
testing of the Intensity Stabilization
Servo (ISS) at the 40m.
- Ben continues to stuff the ISS DC photodiode PCB board.
- Electronics (B. Abbott, Taylor):
- Ben has consulted with Richard M about how
to get fast signals from ISS and MC into DAQ.
He has a second DAQ interface board, and there
should be sufficient empty channels in our
DAQ Lemo Intfc Board to accomodate them.
- Ben has begun stuffing the end racks (mostly DSC stuff for the ETMs)
in order to get an idea of what we have, and what we need.
Bob will start working on the cross-connects for these racks.
- Steve and Bob have made implemented protective trays
and cable strain relief for the 3 installed satellite amplifiers.
- Ben is testing 7 more satellite amplifiers
for the core optics DSCs.
- Completion of the vertex core optics DSC system
(rack 1Y4) awaits Penteks, Pentiums, and software.
We aim to have a working system in 2 weeks.
- Ben continues to design the interface between the Glasgow suspension
electronics and CIT electronics.
The Dspace whitening interface and interface boards were finished and
were sent to PCB Express last week.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
29 each, 1in mirror mounts are pending from Newport; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; IFLEX1000 IR
laser for optical lever is pending from Point Source Ltd; ; polarizers and
half-wave plates for Faraday isolator from KLC; Faraday rotator from EOT; 3
PZT tilt platforms and 2 servo control drive electronics and strain gauge
read-out electronics from Piezosystems Jena; 1.5 in and 2in fixed vacuum
mirror mounts and an adapter spacer from ASCO; Faraday Isolator mechanical
parts from CA Machine Co.
-
FARADAY ISOLATOR:
Awaiting parts.
-
IFO MODE-MATCHING TELESCOPE:
Detail working drawings for telescope housing are complete; however, the
remote focus mechanism will be re-designed for a more cost-effective approach.
Aiming for a complete system in 1 month.
- LIGO:
Working with Dennis Rose to analyze all potential stray laser beams in the
2K and 4K IFOs that might damage the COC suspension wires and/or electronic
cables.
- Optics (Billingsley, Armandula), suspensions (Romie), OSEMs (Bob):
- Our BS, ITMx, and ITMy, are suspended and sitting on the
South Annex clean room flow bench.
- Steve, Dennis and Osamu will swap out dirty OSEMs for new clean ones
in these 3 suspended optics, next week.
- Janeen is making drawing changes for 40m TM suspension optimizations.
Will continue and then gets the parts reworked.
- Bob continues to build and clean OSEMs.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- The ion pumps continue to belch out on occasion;
CC1 pressure is observed to jump up for a few minutes
every once in a while. It's not a serious problem.
- Dennis will try to get RGA information into the DAQ system.
- Dennis has fixed the hair-trigger software interlocks
on the vacuum system, eliminating spurious trips.
- Dennis installed a long ethernet cable to read out the
STACIS SV controller; now all controllers are being read out
and logged.
- One STACIS seismic isolator (SENW-x) is failing;
this is the third such failure since the system was installed.
Also, one of the
controllers (now at the east end) is reading faults from all three
feet, even though the isolators are fine and the EPICS readings
are normal.
Dennis will pursue this.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob is putting his new oven F through its paces.
- Bob is repairing temperature controllers
to ensure a full complement for all 5 bake ovens.
October 25, 2002
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu put together a very detailed
status report
on the performance of the 40m mode cleaner, with comparisons
to models and to the sites, and a preliminary noise budget.
- We worked through this document in a telecon with
Peter Fritschel, Rana, and others. This was very helpful,
cleared up many sources of confusion, and put us on a good track.
- Bottom line: the PSL/IOO/MC works pretty well,
not too different from the sites, and we know what to work on
(the usual suspects):
- To further suppress frequency noise,
we must turn up the gain of the MC servo
(increase the UGF beyond 30 kHz);
but this will not work stably until we first
turn up the gain in the PSL frequency stability servo
(increase its UGF beyond 300 kHz).
There's precious little phase margin to do this,
so we will look for contributors to this phase.
- Reduction of excess electronics noise.
- Reduction of excess seismic noise, with suspicion
centering on the table that supports the MC2 chamber.
- Osamu continues to make ever more careful
measurements of frequency noise and its contributors.
- Osamu found that the large, time-dependent 60 Hz harmonics peaks
in the MC intensity noise spectrum
were an artifact of his measurement method, and he fixed it.
- Osamu, Steve and Dennis are studying the
ambient and impulsive seismic and acoustic noise
on MC2, and searching for ways to suppress it.
Steve built a "sandbox" to damp acoustic excitation
of the beam tube. He's exploring ways to damp or
eliminate acoustic noise from the table on which the MC2
chamber rests.
But, everything rests on a 4" concrete slab,
which bends whenever anyone walks by.
-
Digital Suspension Controllers
(B. Abbott, Heefner, Taylor, Ugolini, Miyakawa):
- Dennis has been trying to reduce the 16 Hz bounce mode
with the suspension controller damping.
We are learning that this isn't possible...
instead, we should remove sources of excitation,
by adding resonant gain at 16 Hz to the signal from the
MC servo to MC2.
Dennis will try to implement this.
- The DSC crashed yesterday, and Dennis traced it
to some connectors that had come loose,
pulling the power supply down.
He pushed them back in, and everything came back up fine.
- Intensity stabilization (B. Abbott, R. Abbott, F. Nocera, D. Ugolini):
- Ben continues to work with Flavio and Rich on the
testing of the Intensity Stabilization
Servo (ISS) at the 40m.
The inner loop is working.
- Ben continues to stuff the ISS DC photodiode PCB board.
- Dennis has set up ISS EPICS screens, databases, control channels,
autoburt files, etc.
- Electronics (B. Abbott, Taylor):
- The Satellite amplifier boxes for the remaining 7 core optics
suspensions are being stuffed, and they should be ready
for installation shortly.
Steve and Bob are working on protective boxes and cable strain relief
for these.
- Completion of the vertex core optics DSC system
(rack 1Y4) awaits Penteks, Pentiums, and software.
- Ben continues to design the interface between the Glasgow suspension
electronics and CIT electronics.
The PCB for the Dspace whitening interface is finished.
Ben should send it to PCB Express tomorrow.
There is one more simple interface board to be layed out.
- DAQ (Ugolini, Ivanov):
- Ever since the dataviewer upgrade last month by Alex,
some channels (deviating from the C1:XXX-YYY_ZZZ syntax)
cannot be displayed in dataviewer.
Dennis is modifying their names in master.config to fix this.
- Need to get fast signals from ISS and MC into DAQ.
Ben will find out how it's done at the sites.
There are sufficient empty channels in our
DAQ Lemo Intfc Board to accomodate them.
- Our AWG crashed yesterday, for unknown reasons.
Alex rebooted it, and it came up fine.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
67 each, 1in mirror mounts are pending from Newport; miscellaneous
optical posts and mounts are pending from ASCO; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; IFLEX1000
IR laser for optical lever is pending from Point Source Ltd; ;
polarizers and half-wave plates for Faraday isolator from KLC; Faraday
rotator from EOT; 3 PZT tilt platforms and 2 servo control drive
electronics and strain gauge read-out electronics from Piezosystems
Jena; 1.5 in and 2in fixed vacuum mirror mounts and an adapter spacer
from ASCO; Faraday Isolator mechanical parts from CA Machine Co.
-
FARADAY ISOLATOR:
Awaiting parts.
-
IFO MODE-MATCHING TELESCOPE:
Corrected a small error in the specification of the primary mirror;
alerted SORL about the change, which won't impact their production
schedule. Detail working drawings for telescope housing are in process.
-
Facilities and vacuum envelope (Ugolini, Vass, Jones):
- All 4 ion pumps up and going. After a few days of outgassing,
AMU 41 is falling again.
- Varian has agreed to send us a higher capacity dry scroll pump
to back up TP3, to replace the under-spec pump they sold us.
- The ion pumps software interlock tripped off a couple of times
due to pressure glitches. Dennis has put a 5-second timer
on the SW interlock.
He also fixed software problems associated with turbopump readout
and VC1 control.
- Dennis added ion pump readout to frames.
- Dennis is stringing long ethernet cables to read out the
STACIS SV controller and MCCM pressure gauge.
- One STACIS seismic isolator is failing, and
its controller is also behaving funny.
Dennis will pursue this.
- Steve and Larry have completed the construction
and installation of table covers for all optical sensing tables.
Now Larry can custom-fit beam tubes.
- The south end crane was repaired. The repairman recommends
installation of relay switches to protect the crane power
supplies, which have been failing at an alarming rate.
-
South Annex Bake Ovens (Taylor, Cardenas):
- Bob is testing the effect of 114degree water bake
on fully assembled OSEMs.
Two of 18 new OSEMs were baked this way,
and 2 failed electronics tests afterwards.
Bob identified the problems. It's a good "stress test"!
- 16 Fully assembled and clean OSEMs are ready to be
installed in our 3 suspended optics,
replacing the dirty OSEMs that were used
to hang them. Bob thinks he knows how to get these clean.
- Bob is building end-assemblies for more OSEMs.
- Bob is putting his new oven F temperature
controller (and the new oven F) through its paces.
October 18, 2002
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- Osamu measured the intensity noise of the MC transmitted light
with a thorlabs PD and spectrum analyzer.
It wasn't clear how to interpret it.
He will repeat the measurement with the new ISS servo on and off,
and will also measure and compare with the PSL intensity noise.
- Osamu remeasured the MC length, by placing a small 3kHz
signal on MC2, and checking for a dip in
its presence in Q-demodulated
MC reflected light, as he stepped through the resonant RF frequency.
He obtained L = 13.5469328(2) m, where the 0.2 um error
is due to the resonant RF frequency readback. Of course,
other errors dominate; but this measurement is likely good
to a fraction of a mm. The design is 13.542 m, so we are < 5 mm off.
We'll adjust the PRC length accordingly (when we install it!),
but the PRC is low finesse so it shouldn't matter much.
- Osamu has been investigating the MC transmitted frequency noise
(by measuring the MC error signal).
It is orders of magnitude larger than spec at high frequencies,
and Osamu has demonstrated that both PSL frequency noise
and MC length noise contribute.
Since we believe that our PSL and MC perform about as well
as the ones at the sites do, we wonder if the sites measure
similar MC transmitted frequency noise.
We will try to compare notes with site experts.
- Large 60 Hz and harmonics lines are present in the
MC transmitted frequency noise spectrum, and they are
strongly time-dependent (they're now 40 dB lower
than they were last week).
We are searching for culprits.
- Although we can aquire and maintain lock reliably,
during the day, in "aqcuire" mode, maintaining lock in
detection mode is fragile. Suspicion rests on excess seismic
noise in the MC2 suspension. This suspension sits in a small
chamber, with a small seigmic stack, with resonant
frequencies between 12 and 55 Hz. This chamber sits on a
metal table, which can be shaky; and that,
in turn, sits on our 4" concrete slab lab floor.
It's easy to imagine how human activity can transmit
seismic motion into MC2.
We will look into ways of reducing the coupling.
- We still need to get the automatic switching
from acquisition to detection mode.
- Dennis continues to work on the MC commissioning document.
-
Suspension Controllers
(B. Abbott, Heefner, Taylor, Ugolini, Miyakawa):
- Ever since the MC suspensions were adjusted
during our last vent, there has been no evidence of anomalous
excitation of the roll mode at 23 Hz. Dennis has removed the
notch filters that we put in last month, and we've had no
problems with it.
- Dennis has been testing bounce mode (16 Hz) filters
and has had no effect on the suspension.
He'll look more at how it's done at the sites.
- Jay suggests we look into getting the new
"FOTON" filter design tool.
- Electronics (B. Abbott, Taylor):
- Ben continues to work with Flavio and Rich on the
testing of the Intensity Stabilization
Servo (ISS) at the 40m.
The ISS DC photodiode PCB board is arriving tomorrow. Stuffing will
begin late this week.
- The Satellite amplifier boxes for the remaining 7 core optics
suspensions are finished being fabricated, they are
being filled with boards in the back shop, and they should be ready shortly.
- Completion of the vertex core optics DSC system
(rack 1Y4) awaits Penteks, Pentiums, and software.
All the wiring is done.
- Mike will compile a list of all electrooptics required
from Wilson House: oplev QPDs, IR QPDs, WFS PDs, LSC PDs, etc.
- Ben is assembling all 40m electronics schematics in a White Book.
- Ben continues to design the interface between the Glasgow suspension
electronics and CIT electronics.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
67 each, 1in mirror mounts are pending from Newport; miscellaneous
optical posts and mounts are pending from ASCO; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; IFLEX1000
IR laser for optical lever is pending from Point Source Ltd; ;
polarizers and half-wave plates for Faraday isolator from KLC; Faraday
rotator from EOT; 3 PZT tilt platforms and 2 servo control drive
electronics and strain gauge read-out electronics from Piezosystems
Jena; 1.5 in and 2in fixed vacuum mirror mounts and an adapter spacer
from ASCO; Faraday Isolator mechanical parts from CA Machine Co.
-
New orders received:
Tilted spherical mirrors for a temporary IFO MM telescope and 2 deg
wedged beam-splitter for sampling the initial pointing beam were
received from CVI.
-
OPTICAL LEVER FOCUS LENS:
Detail working drawings are on hold.
-
FARADAY ISOLATOR:
Awaiting parts.
-
IFO MODE-MATCHING TELESCOPE
Detail working drawings are in process .
-
IO POSITION AND ANGLE SENSOR
Pending a new alignment procedure.
- Optics (Billingsley, Armandula) and suspensions (Romie):
- Our BS, ITMx, and ITMy, are suspended and sitting on the
South Annex clean room flow bench.
- Janeen has
started making drawing changes for 40m TM suspension optimizations.
- Computing:
Steve's and Bob's PCs were upgraded from W98 to W2K,
and now there is no PC in our lab which can read
the floppies from the HP spectrum analyzers, which require the
DOS "lif" command, unavailable on W2K.
We will try to obtain a W98 box to serve this purpose.
-
Facilities and vacuum envelope (Vass, Jones):
- Steve and Dennis got all 4 ion pumps up and going.
- Dennis has installed a second MVME162 cpu (scipe4/c1vac2)
in the vacuum epics crate
to read out the ion pump and turbopump controllers.
After some effort, it works fine.
- Dennis is working on a short list of additional
readout tasks: readout of pressure gauge near the MCCM chamber;
readout of new SV ion pump controller, which is newer and different
than the other 3; new turbopump controller spits out gibberish
when in transition from standby to full speed, and the state code
must ignore it; obtain long ethernet cables to read out the
STACIS SV controller and MCCM pressure gauge.
-
South Annex Bake Ovens (Taylor, Cardenas):
- RGA scans of OSEMs newly built by Bob
have come back dirty. Bob and Steve established that
the problem is with the RGA. Bob moved the OSEMs to another
vacuum oven with a cleaner RGA head, and the scans came
back clean and within specs.
Bob is sending the dirty RGA head back for re-conditioning.
- Bob baked one fully assembled OSEM at 120degC
(a "water bake"), despite fears that it would damage
the LED/PD assembly. It did not; the baked OSEM
performed electronically as well as it did before bake.
Thus, it appears that Bob can recover the 15
dirty, un-baked but fully assembled OSEMs that were used
to suspend our BS, ITMx, ITMy optics,
without dis-assembling them.
-
Bob
has built a neat oven temperature controller for oven F.
After discovering that one of the 5 temp controllers
was uncalibrated, it works fine.
October 11, 2002
- AJW presented the
40m program, G020429-00.pdf
at the AdvLIGO R&D review on October 8.
Mike Smith presented a
proposal for a feasibility test
of a photon actuator for AdvLIGO at the 40m.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- We pumped down last week.
- Ben switched the resistor values in the satellite amplifiers
for all 3 MC suspension controllers,
and revved the drawing in the DCC (D961289-C).
- Dennis re-diagonalized the input and output matrices of the
MC1, MC2, MC3 suspension controllers.
- After re-establishing alignment of the MC,
attempts to lock were
unsuccessful until Osamu turned the gain on the MC path down
by a factor 10 (using the suspension controller output matrix,
since it was already at the minimum in the MC servo screen).
Shortly thereafter, Dennis noticed that the pole-zero filters
were not turned back on.
After turning them back on with EPICS, lock was easily acquired
and maintained with the nominal gain settings.
- Dennis has added autoburt to IOO so that the pole-zero filters
are automatically turned back on after rebooting the DSC;
in addition, lights were added to the suspension controller screen
to indicate whether the PZ filters are on or not.
- Osamu remeasured the visibility of the MC to be 88.7%.
- Osamu measured the power fluctuation in the reflected light
to be 0.4% of off-resonant reflected power.
It had been 4%. Improvement is attributed to repair of MC1 OSEMs
last week, yielding better damping.
- Osamu measured the frequency noise of the MC from the MC servo
error signal, and found it to be much higher than spec, above 100 Hz.
This does not seem to be due to oscillation of the PSL FSS.
He will investigate, and compare with the sites.
- Osamu plans to optimize the gain of the MC servo,
and the gains of the suspension damping.
He'll also measure the MC transmitted light intensity fluctuations,
transverse profile, angle jitter, and RFAM.
And he'll re-measure the MC length.
- Since Ben worked on the MC servo board to eliminate a
small DC offset which interrupts lock when switching
from acquisition to detection mode,
there hasn't been strong evidence of this problem;
but we'll look closer tomorrow.
- We still need to get the automatic switching
from acquisition to detection mode.
- Ben will work with Rich Abbott and Flavio
to install and test the inner and outer ISS loops
(before and after the MC) in the next few weeks.
Ben sent out the gerber files for the ISS DC photodiode PCB.
It should return sometime next week ready for stuffing.
- Dennis continues to work on the MC commissioning document.
-
Suspension Controllers
(B. Abbott, Heefner, Taylor, Ugolini, Miyakawa):
- Ben has changed the resistors (and thus the readout gain)
on the satellite amplifiers for all 3 suspensions,
from 40 kohm to 29.4 kohm
(to get the OSEM sensor full scale match the ADC full scale).
He revved the satellite amplifier schematics in the DCC to show the
changes that have been done to those in the 40m (D961289-C).
- Ben is having the the Satellite amplifier boxes for all the
core optics suspension controllers fabricated, and they should be
ready by the end of next week.
- We still have to notch out the 16 Hz bounce mode,
and understand the origin of the 23.7 Hz roll mode excitation.
- We hope to get the latest greatest DSC software
from Rolf, including software for the vertex core optics DSC.
- Richard McCarthy will allow us to keep the
stand-alone suspension controller that we borrowed to
suspend optics in the South Annex.
Ben will fix it up, so that we can adjust the gains, etc.
- PSL (O. Miyakawa, M. Smith):
- Osamu re-measured the frequency noise of the
frequency stability servo (FSS),
which is still within spec (and thus not explaining
the apperent excess frequency noise in the MC).
- Osamu continues to write the PSL re-commissioning document.
- Osamu and Mike Smith
continue to work on the calibration of the
input optics beam position and angle sensors (QPDs and associated optics,
looking at the beam picked off just before it leaves the PSL table).
- Electronics (B. Abbott, Taylor):
- Bob and Ben are continuing work on the wiring for the
core optics DSC rack (1Y4); they are close to completion.
From there, they go on to the ends (1Y10 and 1X4).
- Bob also continues to work on wiring and cabling of the
auxiliary rack (1X1: video switch, camera power,
illuminator controls, mechanical and EO shutter controls).
- Electronics in process at Wilson House:
6 satellite amplifiers,
universal dewhitening boards,
parts for the DSC for the ends.
- Reports that Penteks have arrived for the vertex DSCs
were premature. We await them.
- Ben continues to design the interface between the Glasgow suspension
electronics and CIT electronics.
- Optical sensing (Smith):
-
OPTICS PARTS LIST,
Orders pending:
67 each, 1in mirror mounts are pending from Newport; miscellaneous
optical posts and mounts are pending from ASCO; input mode-matching
telescope off-axis parabolic mirrors are pending from SORL; IFLEX1000
IR laser for optical lever is pending from Point Source Ltd; ;
polarizers and half-wave plates for Faraday isolator from KLC; Faraday
rotator from EOT; 3 PZT tilt platforms and 2 servo control drive
electronics and strain gauge read-out electronics were ordered from
Piezosystems Jena; 1.5 in and 2in fixed vacuum mirror mounts and an
adapter spacer were ordered from ASCO; 2 deg wedged beam-splitter for
sampling the initial pointing beam was ordered.
-
New orders received:
Mirror clips for vac mirror mounts were received from CA Machine Co.
-
OPTICAL LEVER FOCUS LENS:
Detail working drawings are on hold.
-
FARADAY ISOLATOR:
Detail working drawings are complete and were issued as Rev A drawings
with the DCC. Faraday Isolator
mechanical parts were ordered from CA Machine Co.
-
IFO MODE-MATCHING TELESCOPE:
Detail working drawings are in process.
Tilted spherical
mirrors of approximately the correct focal lengths for a temporary IFO
MM telescope were ordered from CVI.
-
IO POSITION AND ANGLE SENSOR:
A translation stage with a fine adjustment screw was installed in the
angle sensor. Osamu and I were not able to properly align the angle
sensor because there are too many degrees of freedom requiring the
correct placement of 4 lenses in the optical train. A new alignment
procedure will be developed to overcome this problem.
- Optics (Billingsley, Armandula) and suspensions (Romie):
- Our BS, ITMx, and ITMy, are suspended and sitting on the
South Annex clean room flow bench.
- Bob is finished baking 7 short and 14 long
OSEMs to replace the dirty ones in the above suspensions.
Dennis and Steve will replace the dirty with the clean OSEMs
in the next 2 weeks,
and Bob will try to salvage the dirty ones.
He continues to prepare the remaining OSEMs needed for our core optics.
-
Facilities and vacuum envelope (Vass, Jones):
- We pumped down without much problem at the end of last week.
- The V1 valve tripped shut due to a software interlock,
which checks for a problem with our new turbopumps.
In fact, this happened 3 times, and we suspect that it is due
to one-shot brief glitches in communication with the turbopump
controller.
Dennis has put in a counter, so that communication with the
controller must fail 5 times in a row (over ~ 7 seconds)
before V1 trips shut. No trips have been observed since this change.
- Dennis has installed a second MVME162 cpu (scipe4/c1vac2)
in the vacuum epics crate
to read out the ion pump and turbopump controllers.
(The readout by the first cpu would hang after some days,
and we suspect that it was too much of a burden for one cpu).
We will be watching it closely!
-
South Annex Bake Ovens (Taylor, Cardenas):
Bob is suspicious that one of our Dycor RGA 200 systems is beyond repair
and is requesting $7K for a new Dycor LC RGA.
October 4, 2002
- Final papers from all 5 SURF students have been completed
and submitted to the SURF office and to LIGO DCC.
Check them out at the
40m web page.
- Mike Smith is proposing to use the 40m for a feasibility test
of a photon actuator for AdvLIGO,
which he will describe at the AdvLIGO R&D review on October 8.
-
Suspension Controllers
(B. Abbott, Heefner, Taylor, Ugolini, Miyakawa):
- Dennis and Steve have properly shimmed the MC1
suspension (with a 0.28 mm thick piece of metal) so that
all OSEMs read back near the middle of their range.
They have rebalanced the OSEMs on MC1 and MC3,
and checked for sensible readback from OSEMs on all 3 suspensions.
- Ben has changed the resistors (and thus the readout gain)
on the satellite amplifiers for all 3 suspensions,
from 40 kohm to 29.4 kohm
(to get the OSEM sensor full scale match the ADC full scale).
Full scale is 2 V, and all OSEMs are near 1 V.
All yaw offsets are < 0.2 V.
- We are now pumping down, and Dennis will re-diagonalize
all 3 suspensions shortly thereafter.
- We still have to notch out the 16 Hz bounce mode,
and understand the origin of the 23.7 Hz roll mode excitation.
- We hope to get the latest greatest DSC software
from Rolf, including software for the vertex core optics DSC.
-
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass, Abbott):
- As mentioned above, OSEMs on all 3 suspensions
have been checkout out, and they're all near to the middle
of their range.
- Dennis, Osamu and Steve have re-established alignment
of the suspensions, with the PSL beam, prior to pumpdown.
Clean TEM00 fringes were observed.
- Ben swapped out an 1125 on our Mode Cleaner Servo board in hopes that the
boost gain induced offset will be minimized. We will test the change tomorrow.
-
Dennis continues to work on the M