Installation and Commissioning Task
Overview
The installation and commissioning of the Advanced LIGO detector systems
is planned to be as rapid as possible in order to minimize the observatory
downtime. It requires the installation of all detector elements in all three
LIGO interferometers in a phased approach to best utilize the infrastructure
and manpower in the Laboratory and LSC. The subsystem teams are expected to
have pre-assembled and pre-tested components available for installation when
needed (some assembly and test can take place at the observatory sites in
advance).
Functional Requirements
At the end of the installation and commissioning period Advanced LIGO should
be running reliably near design sensitivity. The installation and commissioning
effort must be done simultaneously with continued observatory site and LIGO
Laboratory operations, though much of the staff will be diverted to installation
and commissioning tasks.
Concept/Options
The basic conceptual plan for the installation is as follows:
- The installation and commissioning phase is under the direction
and responsibility of the LIGO Laboratory. LSC members may contribute
and assist. We assume that developers of technology in the LSC will
participate in installation and commissioning of their respective
components, though our planning assumes much of the labor required
will come from the Laboratory staff or contractors.
- Full-scale subsystem testing is performed to prove out the design
and fabrication of components, assemblies and subsystems and their
interfaces wherever possible.
- System level testing of the full configuration (power and signal
recycled Michelson with Fabry-Perot arm cavities) with as much of
the full-scale hardware as possible (active seismic system, suspension
system, etc.) is performed on the Caltech 40 Meter Interferometer and
MIT LASTI testbeds
- Installation exercises will be carried out for the major mechanical
subsystems at the MIT LASTI testbed, training the subsystem and observatory
staff who will then carry our the installation at the observatories.
- Pre-assembly, pre-alignment and pre-testing (to the extent possible) is
carried out for all subsystems prior to installation into the system. For
example, the seismic systems will be fully preassembled and sealed for
transport from onsite staging buildings into the vacuum equipment areas.
Suspensions will be preassembled onsite up to attachment of the final silica
fibers and test masses. These will be installed at the time the vacuum system
is ready to receive the subsystems.
- In order to minimize observatory downtime, installation will not begin until
all required fabrication is complete and all required assembly and unit level
testing is complete.
- Two shifts of installation are planned only for labor-intensive activities
on the critical path and held in reserve for contingency for non-critical
tasks.
- The commissioning teams, as in initial LIGO, require expertise from multiple
disciplines and subsystems. Staffing for the design and development phases
of the Advanced LIGO effort are planned with the intent of providing this
expertise.
One possible option in the overall program, which has significant impact on the
installation and commissioning phase, is whether the initial LIGO 2 km interferometer
is converted to a 4-km interferometer or operated in the initial LIGO configuration.
The baseline for this proposal is that the 2km interferometer will be upgraded and the
arm length will be extended to 4 km.
R&D Status/Development Issues
A rapid and predictable installation schedule requires well thought out and tested
installation procedures and fixtures. LASTI will provide an opportunity to test these
installation procedures in full-scale chambers and to train team leaders. This
development is essential for successful installation of the interferometers.
System R&D and testing of the signal and power recycled configuration on the 40 Meter
testbed is essential for the commissioning team to gain the experience and expertise
that will be required.
Work Plan
In early 2007, the three initial LIGO interferometers will complete their coincident
observation run and the Livingston instrument will be turned off. This event will
trigger the start of installation activities. For many months prior to this point,
the subsystem components will have been pre-positioned at the sites, assembled and
tested, and the limiting pace should be set by the available skilled manpower. Near
the end of 2007, the initial LIGO Hanford instruments will be turned off. The seismic
isolation installation will be completed at Livingston by that time, and that
installation team will migrate to Hanford for the commencement of installation there.
This staggered pattern will continue with the suspensions, optics, and the other
subsystems.
This is the baseline plan. The status of the global observing networks, agreements
between projects, and scientific and technical developments may motivate altering
the order of upgraded interferometers or the interval between installations of the
successive interferometers.
The plan is to perform the physical installation as rapidly as possible to maximize
the time for debugging, characterization and commissioning. This is enabled by the
pre-deployment of all materials to the sites and by the full-scale testing which
minimizes the risk of rework.
The top-down schedule is shown in Figure 1.
click on the image to enlarge

Figure 1 Top-level Advanced LIGO installation schedule
Detail Requirement Sheets
Baseline Plan
|