> home > proposal > facility modification
Facility Modification
Overview
Advanced LIGO technical requirements will necessitate modifications and upgrades
to the LIGO buildings, and vacuum equipment. In addition, the strategy for executing
the Advanced LIGO construction will require some facility accommodations.
The principal impact on this WBS element is as follows:
- It is a program goal to minimize the period during which LIGO is not operating
interferometers for science. For this reason, major subsystems such as the
seismic isolation and suspension subsystems should be fully assembled and staged
in locations on the LIGO sites ready for installation into the vacuum system as
fully assembled and vacuum compatible units. This will require prepared assembly
and staging space, materials handling equipment, and softwall clean rooms.
- Increasing the arm cavity length for the Hanford 2-kilometer interferometer to
4 kilometers will require removing and reinstalling the existing mid-station
chambers and replacing them with spool pieces in the original locations. An alternate
strategy would be to fabricate additional vacuum tanks for the end stations, and
associated spool pieces and preparation. Moving the existing chambers is the
choice for the baseline design.
- The larger optical beams in the input optics section (and possibly the output
optics section) will necessitate changing out the input optics vacuum tube for
a larger diameter tube.
Functional Requirements
Vacuum Equipment
All vacuum equipment functional requirements are the same as those in the initial LIGO
design except that the vacuum level must be one order of magnitude lower (<10-7
torr). Additional equipment (chambers, spool pieces, softwall clean rooms) is needed to
accommodate additional arm cavity length for one interferometer and the desire for parallel
assembly and installation in more chambers and staging areas. A larger diameter spool piece
for the IO Mode Cleaner beam path (and possibly for a similar output mode cleaner) is
required. The seismic isolation system requirements call for the Advanced LIGO subsystems
to be compatible with the original LIGO vacuum envelope.
Beam Tube
The original end-pumped beam tube system requires no modifications or additions for
Advanced LIGO. There is sufficient margin in the present vacuum performance to permit
the operation of the more sensitive Advanced LIGO instrument with no changes.
Conventional Facilities
Preassembly of all large Advanced LIGO seismic isolation units prior to installation in
the vacuum tanks requires clean onsite staging and assembly space. At both the Hanford
and Livingston Observatories there exist suitable staging buildings with appropriate height
and basic configuration; portable clean rooms and benches are required. Transporters for
delivering fragile systems from the central buildings to the end stations are required.
Concept/Options
Vacuum Equipment
Two softwall cleanrooms of the BSC type will be acquired for seismic assembly in the
Hanford staging building. Two will be required for Livingston. For each of the interferometers,
additional clean rooms will be acquired to support parallel installation in additional
chambers to facilitate reducing the duration of Advanced LIGO installation.
Four additional spool pieces will be acquired to replace the Hanford mid-station BSC chambers
and to connect these chambers to the end-station BSC chambers once relocated. The chambers
will be removed and reinstalled at the end stations. An alternative approach involves acquiring
new BSC chambers and leaving the original chambers in place. Vacuum controls will be added at
the end stations to accommodate the BSC chambers in their new location.
The IO (and potentially the output) Mode Cleaner requires a larger diameter spool piece,
~15m in length, to accommodate the larger mirrors used.
The requirement of base pressure for Adv LIGO (<10-7 torr) is already met
by the present system (which is operating at <10-8 torr).
Beam Tube
No action needed. The original installation meets requirements for Advanced LIGO.
Conventional Facilities
The existing staging buildings at both observatories will require additions of flow
benches, fume hoods, vacuum bake ovens, and other minor equipment to support clean
processing operations. In addition, at LHO some retrofit of the HVAC system will be
necessary in the Staging Building to meet the cleanliness requirements. HEPA filters
and a more powerful motor are needed.
R&D Status/Development Issues
There are no development issues or R&D associated with this WBS element.
Work Plan
Long lead procurements dominate this schedule sensitive WBS element. With funding
assumed to commence in FY2005, contracts can be placed promptly for the softwall
clean rooms and flow benches. These must be in place prior to commencement of seismic
assembly by mid 2006. Procurement of vacuum equipment for conversion of the Hanford
2-kilometer interferometer should commence in 2006.
WBS Definition
This element includes modifications and additions to buildings, vacuum systems,
and permanent fixed infrastructure that are needed to support the Advanced LIGO
detectors. It does not include other facility additions or modifications carried
out as normal operations or maintenance tasks.
Detail Estimate Sheets
Baseline Plan
|