Cost and Schedule
Advanced LIGO Summary Schedue
Milestones for potentially critical path Advanced LIGO activities are listed
in Table 1. These milestones are coordinated with the development schedule.
Table 1 Advanced LIGO construction/installation summary milestones
| Milestone |
Date at End of Quarter per Calendar Year |
| NSF early funding for Core Optics available |
1 Apr 2004 |
| NSF funding for Advanced LIGO Construction available |
1 Apr 2005 |
| Vacuum equipment contract placed |
26 May 2005 |
| Vacuum equipment ready to install |
10 Nov 2006 |
| Clean rooms contract placed |
1 Apr 2005 |
| Clean rooms available for vacuum equipment area |
8 Mar 2007 |
| Seismic Isolation final design review |
17 Nov 2004 |
| Seismic Isolation assembly started |
11 Nov 2005 |
| Seismic Isolation ready for installation |
17 Aug 2006 |
| Suspension subsystem final design review |
8 Mar 2006 |
| Suspension subsystem first articles |
15 Nov 2006 |
| Suspension subsystem ready for installation |
2 May 2007 |
| Pre-Stabilized Laser final design review |
17 Aug 2005 |
| Pre-Stabilized Laser ready for installation |
2 Nov 2006 |
| Core Optics Components final design review |
27 Apr 2004 |
| Core Optics Components first articles available for Suspention |
2 Mar 2006 |
| Interferometer Sensing & Control final design review |
16 Jul 2005 |
| Installation begins at Livingston |
8 Mar 2007 |
| Installation begints at Hanford |
15 Nov 2007 |
| Commissioning begins at Livingston |
21 Sep 2007 |
| Commissioning begins at Hanford |
29 May 2008 |
| Livingston operational |
4 Mar 2009 |
| Hanford operational |
6 Jan 2010 |
Relationship to Laboratory Initial LIGO and Operations Schedule
Initial LIGO scientific operations will continue during 2007. Through 2006, LIGO
Laboratory staff supported under the existing Cooperative Agreement will be carrying
out the portions of the LSC R&D program related to Advanced LIGO. Advanced LIGO
construction funds will support incremental staff required to carry out Advanced LIGO
design, fabrication and assembly.
Following shutdown of the initial LIGO detector systems, a significant portion of the
LIGO Laboratory staff becomes available to support Advanced LIGO installation and
commissioning. In addition, incremental contractor staff will be added to support
installation. These contractors are budgeted in the Advanced LIGO construction estimate.
Participating LSC members from outside the LIGO Laboratory are expected to support
installation and commissioning of the LIGO systems.
Additional Cost and Schedule Information
Note: These entries are access-restricted
Advanced LIGO Cost Estimating Plan
Advanced LIGO WBS Layout
Advanced LIGO Cost Estimate Summary
Advanced LIGO Cost Profile/Request Forecast
Advanced LIGO Milestone Report
Advanced LIGO Schedule Summary
Advanced LIGO Schedule Summary by IFO
|