LIGO home page | LIGO Newsletter
contactsLIGO fact sheetLIGO chronologyLIGO articlesOther GW projectsLIGO photosignore
LIGO Press and MediaLIGO Chronology


1970s Feasibility studies and early work on laser interferometer GW detectors
1979 NSF funds Caltech and MIT for the laser interferometer research and development
1989 December Construction proposal for LIGO submitted to National Science Foundation
1990 May National Science Board approves LIGO construction proposal
1991 March LIGO project receives 19 site proposals from 17 states
1992 February NSF selects LIGO sites in Hanford, WA, and Livingston, LA
May LIGO Cooperative Agreement signed by NSF and Caltech
1993 Summer NSF review panel endorses technical status of LIGO
1994 July Groundbreaking at Hanford site
Winter Site construction activities underway at Livingston location
1996 October Installation of vacuum beam tubes begins at Hanford
1997 June First polished glass received by LIGO
July LIGO prototype demonstrates "splitting a fringe" at LIGO sensitivty goal
August Buildings at Hanford accepted and occupied
December LIGO receives final shipment of raw glass
1998 May First completed mirrors arrive at LIGO
September 40-Meter interferometer operated with LIGO optical configuration
December First completed mirrors arrive at LIGO
1999 April Polishing of mirrors
June Coating of mirrors complete
September First module at Livingston completes bake
November LIGO inauguration ceremony
2000 May Completed installation of interferometer components for Hanford two-kilometer interferometer
June Completed the bake of beam tube(s) at Livingston
October Achieved 'first lock' on Hanford 2-km interferometer in recombined configuration with both Fabry-Perot arms
2001 January Achieved 'first lock' on Hanford 2-km interferometer in power-recycled configuration
December E7 Engineering run, first coincident operation of all interferometers plus GEO600 interferometer in Germany and LSU bar detector
2002 August First data-collection Science Run (S1) emplying all three LIGO interferometers in conjunction with the GEO600 and TAMA300 (Japan) interferometers
2003 Feb-Apr Second Science Run (S2) operating with TAMA300 interferometer
Spring Further commissioning yields still greater sensitivity gains
Nov-Dec Third Science Run (S3) operating with GEO600 and TAMA300 interferometers
2004 Spring Seismic interference difficulties at Livingston overcome with installation of active anti-seismic system
Fall Hanford interferometers approach design sensitivity
2005 Feb-Mar Fourth Science Run (S4) performed
March LIGO design sensitivity achieved
Fall Demonstration of Advanced LIGO laser power
November Start of Science Run 5 (S5) - a cumulative year long data run at design sensiivity
2006 Jan-Dec S5 continues, new standards reached in interferometer performance and duty factors
November Science Education Center inaugurated at the LIGO Livingston Observatory
2007 January Agreement of collaboration ratified between LIGO and Virgo (Italy)
February Advanced LIGO funding included in Presidential FY08 budget
May Joint observations commence with Virgo
October S5 ends; one-year, two-site coincident data at design sensitivity accumulated
Fall Installation of readout enchancements begins
2008 Planned start of Advanced LIGO construction
2009 Planned start of S6 observation with enhanced initial LIGO instruments
2010 End of S6; initial LIGO operations conclude; Advanced LIGO installation begins
2012 Advanced LIGO installation completed
2013 First Advanced LIGO interferometer operational
2014 All Advanced LIGO interferometers operational; Advanced LIGO observations begin


updated 01.06.2005
© California Institute of Technology
webmaster

LIGO is supported by the National Science Foundation | nsf.gov